%Z

Transformer %Z is impedance expressed on the unit's rated voltage and power base, so it must stay attached to the nameplate kVA. Two equal-size transformers with 4 percent and 6 percent impedance do not divide a parallel load equally: under matched voltage ratios and similar impedance angles, the lower-impedance unit carries 60 percent. The factory reference temperature and impedance tolerance also matter when comparing replacements or updating a fault-current model.

Transformer percent impedance from the nameplate, the percent of rated voltage that drives full-load current into a shorted secondary

Used across 2 Anvilfield field guides, most in Electrical.
Updated

Read the guarantee with its temperature and tolerance

Schneider Electric publishes a 4.75 percent impedance guarantee at a 75 C reference temperature for its 315 kVA Fast Trans distribution transformer, subject to a stated 10 percent tolerance. That tolerance is relative to the impedance value. It describes 4.275 to 5.225 percent, rather than adding or subtracting ten percentage points.

Schneider's same product guidance lists 5.0 percent for the 1,250 kVA size and 6.0 percent for the 2,000 kVA size, also at 75 C. These named product values show why a model and rating belong beside any quoted "typical impedance." Preserve the factory test result when it is available, rather than replacing it with a catalog nominal value.

At the low end of that 4.75 percent guarantee, 4.275 percent impedance gives 4.75/4.275 = 1.111 times the terminal fault-current estimate based on nominal impedance, with the same rated current and an infinite upstream source. The tolerance therefore produces an 11.1 percent increase in that simplified estimate. Carry the guaranteed minimum or delivered test value explicitly into the study rather than treating the catalog center value as the minimum.

Different impedances limit parallel-bank capacity

Schneider Electric's parallel-transformer guidance identifies matching phase-angle relationship, voltage ratio, and similar percentage impedance as conditions for successful parallel operation. It shows that unequal percentage impedances reduce the usable total load because one transformer reaches its rating first. The shared load does not divide by nameplate kVA alone.

Take two 1,000 kVA transformers with matched voltage ratios and phase angles, similar impedance angles, and negligible connecting impedance. At 4 percent and 6 percent impedance, they divide load in the inverse ratio, 6:4. At 1,600 kVA total, their shares are 960 kVA and 640 kVA. The 4 percent unit reaches 1,000 kVA when the pair supplies about 1,667 kVA, leaving about 333 kVA of the combined nameplate total unusable without overloading that unit.

Keep a load-sharing result distinct from a fault study

A parallel-load result divides operating load between sources; the available-fault-current study evaluates fault duty at a specified system location. Preserve separate cases for the tie open and closed. The 1,667 kVA load-sharing ceiling above describes a bank operating with the tie closed and does not supply a fault-current value for either case.

A replacement unit can match kVA and secondary voltage yet change both load division and fault duty. Put the delivered impedance, tap position, vector group, connecting conductor data, and factory reference conditions into the revised system model. Matching a nameplate voltage does not establish that an existing parallel bank retains its previous usable capacity.

Distinctions

Impedance in ohms
Percent impedance is normalized to rated voltage and power. The same %Z on unequal kVA ratings does not mean equal impedance in ohms.
Voltage ratio
A ratio mismatch can drive circulating current even before useful shared load is applied. Matching impedance does not correct that mismatch.

Frequently asked questions

Does a 10 percent impedance tolerance mean ten percentage points?

Apply the tolerance to the stated impedance. Ten percent of 4.75 percent is 0.475 percentage point.

Will two equal-kVA transformers share load equally?

They need compatible voltage ratios, phase relationships, impedances, and connecting paths. Equal kVA alone does not establish equal current sharing.

Sources checked

Also defined as

  • Transformer percent impedance, which sets the ceiling on secondary fault current
  • Percent impedance of a transformer, which sets its secondary fault current