TTR
Transformer turns ratio testing (TTR) compares induced voltages after accounting for winding connections and tap position. On a 480 V delta to 208Y/120 V unit, the line-voltage ratio is about 2.31 while the winding ratio is about 4.00. Those are different reference conventions for the same equipment. Enter the vector group and nameplate voltages correctly, then calculate deviation against the expected ratio for the actual tap.
Transformer turns ratio test, measuring the ratio of primary to secondary turns against the nameplate
Convert the nameplate voltages to the right winding ratio
Rex Power Magnetics explains that a wye winding has line voltage equal to its phase voltage multiplied by the square root of three, while a delta winding has equal line and phase voltage. TTR interpretation therefore starts with which winding terminals the instrument excites and measures, together with the connection factor it applies.
For a 480 V delta to 208Y/120 V transformer, the nameplate line-voltage ratio is 480/208 = 2.3077. The individual winding ratio is about 480/120 = 4.00. Both numbers describe the same nominal transformer from different voltage references. Comparing an instrument's winding-ratio display with 2.3077 would create a large apparent error without any winding damage.
Calculate deviation from the expected ratio on that tap
Use deviation = 100 times (measured ratio minus expected ratio) divided by expected ratio. With an expected ratio of 4.000 and measured ratio of 3.990, deviation is -0.25 percent. Keep enough digits to distinguish the expected-value calculation from the instrument's rounding.
A higher-voltage primary tap changes the expected ratio. Rex Power Magnetics describes a positive primary tap as adding effective primary turns. Starting from an expected winding ratio of 4.000, a positive 2.5 percent tap changes the target to 4.100. A measured 4.090 is then about -0.244 percent from its tap target, not +2.25 percent from nominal. Put the tap-specific target beside each measured result in the transformer acceptance record.
AC excitation and phase angle belong in the instrument record
DV Power's TRT range measures turns ratio, excitation current, and phase shift, with model-dependent test voltages from 1 V AC to 500 V AC. The 1 V capability supports current-transformer ratio checks; it is not a blanket voltage recommendation for power transformers. DV Power identifies true three-phase excitation on selected models for special winding configurations. Save the actual mode and voltage so a later test reproduces the measurement conditions.
Interpret ratio readings with the other diagnostic tests
IEEE C57.152-2025 is the active diagnostic field-testing guide for liquid-filled transformers, regulators, and reactors. Its public description says to interpret multiple test results together and identifies manufacturer acceptance criteria as potentially taking precedence over the guide. Preserve excitation voltage, test direction, vector-group entry, phase angle, current, and expected-ratio convention so an anomalous ratio can be compared with the other evidence.
Distinctions
- Nameplate voltage ratio
- This can be a line-to-line ratio. The instrument's reported winding ratio can include the delta-wye connection factor.
- Winding resistance
- A stable voltage ratio can coexist with a poor conducting connection. Use the separate winding-resistance results to investigate that connection rather than treating a ratio result as a resistance measurement.
Frequently asked questions
Why does a 480 to 208 V transformer show a ratio near 4?
A delta primary winding sees 480 V while each wye secondary winding sees approximately 120 V. A winding-ratio display therefore reads about 4 rather than the line ratio of 2.3077.
Is TTR a DC test?
The induced-voltage ratio test uses AC excitation. Record its actual voltage and mode separately from DC insulation-resistance and winding-resistance tests.
Sources checked
Also defined as
- Datacenter: Turns-ratio test, comparing measured winding ratio to the nameplate ratio at each tap