Field glossary · component
CT / PT (VT)
Instrument transformers adapt power circuits to measurement inputs: a CT supplies scaled current, while a PT, also called a VT, supplies scaled voltage. ABB illustrates a 7200:120 V VT, a 60:1 ratio; current-transformer inputs commonly use 1 A or 5 A secondaries. Selection also needs the connected burden and accuracy class, because an accurate ratio at one burden does not establish performance with longer leads or during a fault.
Current and potential (voltage) transformers feeding meters and relays
Read the burden beside the CT ratio
ABB's instrument-transformer guide defines the 60 Hz B-0.2 metering burden as 0.2 ohm impedance at 0.9 power factor, equivalent to 5 VA at 5 A secondary current. It is not simply a 0.2 ohm resistor: ABB lists 0.18 ohm resistance plus an inductive component. Accuracy comparisons need the burden's magnitude and phase angle, including the instruments and complete lead loop.
For a resistive lead loop, 0.20 ohm at 5 A accounts for 5 squared x 0.20 = 5 VA. A 1 VA meter at unity power factor adds 0.04 ohm, making 0.24 ohm and 6 VA in total. That exceeds a 5 VA burden limit before terminals and test switches are included. For a meter with reactive burden, combine the resistance and reactance components instead of assuming that VA magnitudes add exactly.
CR Magnetics explains that a 0.3B-0.2 metering designation combines a 0.3 percent accuracy class with a 0.2 ohm burden specification; the percentage is not a promise independent of load. Keep the manufacturer's applicable current range and phase-angle limits with the nameplate record.
Why long CT leads favor a 1 A secondary
Schneider Electric states that changing from a 5 A secondary to a 1 A secondary reduces secondary wiring losses by a factor of 25 at the same lead resistance. For the 0.20 ohm loop above, the lead burden becomes 0.20 VA instead of 5 VA. That comparison explains the appeal of 1 A circuits on long runs; the receiving relay or meter still needs the matching current input.
CTs, low-power current sensors and Rogowski coils do not share one input convention. Read whether the device produces amperes, millivolts or another signal before selecting the meter channel. The EPMS commissioning guide covers ratio programming and polarity checks; burden arithmetic belongs with that same channel record.
Read a VT ratio without multiplying twice
ABB shows a 7200:120 V voltage transformer, giving a ratio of 60:1. At 118 V measured across that secondary winding, the corresponding primary-winding voltage is 7080 V. A meter already programmed for the 60:1 ratio reports the primary value; multiplying its display by 60 again creates a sixtyfold error.
Record which voltage pair the transformer actually spans. A phase-to-neutral connection and a phase-to-phase connection do not represent the same system voltage. ABB describes conventional VT outputs of 115 to 120 V, so match the meter's voltage input and ratio configuration to the transformer nameplate.
The secondary service arrangements also differ. ABB warns that an open CT secondary can develop high voltage while primary current flows; its current path needs the designated shorting provisions before a meter is removed. A VT supplies voltage across its burden, and shorting that secondary creates a fault. Identify the CT shorting block and VT isolation arrangement separately in the meter-replacement scope.
Decode a protection CT marked C400
CR Magnetics describes a C400, 5 A protection CT as developing 400 V at 20 times rated secondary current into a 4 ohm burden while limiting ratio error to 10 percent. The C identifies a construction whose relaying performance is calculable. This is a fault-duty accuracy designation, not a 400 V normal metering output.
IEEE lists C57.13-2016 as the active instrument-transformer requirements standard as of November 5, 2026; its published scope includes ratio, phase angle, excitation, polarity and resistance tests. Metering accuracy and protection accuracy therefore answer different questions. A meter-focused core is selected for normal-load measurement, while a protection core must reproduce fault current well enough for the relay's duty.
Distinctions
- CT versus VT connection
- A CT senses the current in a primary path; a conventional VT connects across the voltage being measured. CT secondary circuits use shorting provisions, while a VT secondary must not be treated as a circuit to short.
- Thermal burden versus accuracy burden
- An accuracy burden specifies the load for the stated ratio and phase performance. Remaining within a thermal burden rating establishes a heating limit only; it does not establish that the metering accuracy requirement is met.
Frequently asked questions
Does a higher VA CT automatically give better accuracy?
The accuracy class and its specified burden range control. Match the actual meter and lead burden to the transformer's published accuracy data; a larger VA number alone does not rank two CTs.
Sources checked
- ABB: Instrument Transformers, Technical Information and Application Guide, burden tables
- CR Magnetics: Instrument Transformers Application Guide, metering and relaying accuracy
- Schneider Electric: CT burden and 1 A versus 5 A secondary wiring losses
- IEEE: C57.13-2016 active standard status and test scope
Also defined as
- Datacenter: Current transformer and potential (voltage) transformer, the devices that scale current and voltage down to meter signals