ATS

ATS means automatic transfer switch, a controller-operated source selector with separate ratings for carrying load and surviving faults. Cummins illustrates the distinction with a 400 A switch tested at 480 V, 35,000 A, and 50 milliseconds. That fault qualification includes a duration; the 400 A load marking supplies neither a fault-current rating nor permission to substitute a slower upstream protective device.

Automatic transfer switch, which senses the loss of normal power and moves the load to the alternate source

Used across 6 Anvilfield field guides, most in Electrical.
Updated

Separate the load rating from the fault rating

A continuous ampere marking describes normal load duty; the withstand and closing rating, or WCR, describes a short-circuit qualification. Cummins T-011, Issue 4, reports low-voltage switch ratings from 10,000 to 100,000 A with instantaneous-trip breakers and up to 200,000 A with suitable current-limiting protection. These are combinations of switch and protection, not a conversion from frame amperes.

Preserve a photograph of the complete WCR marking with the upstream breaker or fuse identification for each source. A breaker replacement can invalidate a specific-device qualification even if the switch and feeder load stay unchanged. Use the ATS commissioning guide to carry that comparison into acceptance.

A time-based WCR includes a clearing-time condition

Cummins' UL 1008 training distinguishes a withstand and closing rating based on a specified duration from one based on a specified overcurrent protective device. Its explanation identifies 50 milliseconds as the familiar three-cycle rating at 60 Hz. A 100 millisecond interval is six cycles at the same frequency.

A switch qualified for a fault-current magnitude for 0.05 seconds does not establish performance at that magnitude for 0.10 seconds. Likewise, a higher rating achieved with a named breaker does not transfer to another breaker merely because both breakers carry the same continuous ampere rating. The protective-device model, settings, voltage, and clearing performance complete the comparison.

Keep the listing family and edition attached to the submittal

UL lists UL 1008, ninth edition, published in 2022 and revised August 25, 2026, as the active Transfer Switch Equipment standard. Its public scope covers transfer switches rated up to 1,000 V and excludes equipment rated above 1,000 V. That boundary matters when a project specification uses "ATS" for both low-voltage and medium-voltage equipment.

Ask the submittal to identify the listing and the exact configuration supplied, including service-equipment and bypass options where fitted. A catalog family contains several combinations. The installed label, incoming protection, and study location must describe the same switch before the acceptance record is closed.

Surviving a fault does not establish continued serviceability

Cummins' UL 1008 training distinguishes the WCR test from a short-time rating that also requires a subsequent temperature-rise test. That additional test demonstrates the ability to carry rated current after the short circuit. A WCR label alone does not establish that a switch remains fit for service after an actual fault; the manufacturer's post-fault inspection and disposition belong in the repair scope.

Distinctions

ANSI/NETA ATS
In a testing specification, ATS also abbreviates Acceptance Testing Specifications. That document name does not identify a transfer-switch product or its UL rating.
Breaker interrupting rating
A breaker clears fault current. A transfer-switch WCR describes surviving and closing onto fault current under its stated protection conditions.

Frequently asked questions

Does a high WCR make an ATS a protective device?

A withstand rating does not add an overcurrent trip function. Identify any integral breaker separately and preserve its actual protection settings.

What does "any breaker" mean on an old schedule?

Cummins explains that the phrase commonly refers to a time-based rating. Recover the actual duration and current qualification from the switch documentation.

Sources checked

Also defined as

  • Datacenter: Automatic transfer switch, operating a specified sequence between sources
  • Datacenter: Automatic transfer switch, the device that moves the load between sources

Where this shows up

Next step: Track transfer switch bids