Field glossary · code or standard

Class

On an NFPA 110 schedule, Class is the duration used to size stored energy for the emergency power supply system at rated load. A diesel calculation multiplies the engine's full-load fuel consumption by those hours. HCAI's hospital example requires 7,668 usable gallons for 72 hours at 106.5 gallons per hour, available below the low-fuel alarm. Fuel below the pickup and tank space above the permitted fill level contribute nothing to that reserve.

NFPA 110 class for runtime, the minimum hours at rated load without refueling

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Named classes and a project-specific Class X

Cummins' 2025 NFPA 110 training identifies the short-duration classes 0.083 and 0.25 with 5-minute and 15-minute supplies; the other numbered durations are 2, 6, and 48 hours. Class X supplies the duration specified for another application. A 72-hour schedule needs that number beside X so the fuel takeoff has a usable multiplier.

NFPA lists the current edition of NFPA 110 as 2025. Identify the project's governing edition on the fuel schedule, then distinguish its required runtime from the physical tank-capacity calculation. Keep the energy calculation with the operating configuration in the generator acceptance package.

Locate the runtime reserve below the low-fuel alarm

California HCAI's NPC 5 seismic FAQ uses a 1,500 kW generator consuming 106.5 gallons per hour at full output: 106.5 × 72 = 7,668 usable gallons. HCAI places the required 72-hour reserve between the fuel pickup and the low-fuel sensor. A runtime calculated only from maximum-fill inventory does not establish that the reserve remains when the alarm operates.

The same HCAI example has a nominal 12,000-gallon tank, 10,200 gallons available between pickup and maximum fill, and a 7,700-gallon low-fuel setting. Record all three quantities against the tank's level-to-volume data. The nominal label, maximum drawable inventory, and low-alarm reserve are different quantities, and fuel trapped below the pickup belongs to none of the usable-volume calculations.

For multiple engines, add the full-load consumption of the engines included in the required operating configuration before dividing usable inventory by consumption. Two engines each burning 106.5 gallons per hour consume 213 gallons per hour together; 7,668 gallons then supplies 36 hours. The generator sizing guide establishes the plant configuration that this fuel calculation must match.

What changed in the 2025 fuel-tank allowance?

Cummins' 2025 NFPA 110 update explains the minimum main-tank capacity as 1.33 times the fuel quantity at the low-fuel sensor setting for classes through 24 hours; longer classes use a factor of 1.00. The longer-duration factor replaces the 2022 edition's 1.33 basis. These provisions appear in sections 5.5.3.1 and 5.5.3.2 of the 2025 edition.

The sensor quantity is the basis for those percentages. Applying the percentage to a nominal tank label reverses the calculation. Establish the sensor's corresponding fuel quantity and usable levels first, then apply the governing edition's capacity provision. HCAI also notes that CMS and Joint Commission adoption of NFPA 110-2010 retains a 133 percent capacity requirement; a project's use of the 2025 provision does not remove a separately applicable requirement.

HCAI also identifies additional inventory above the low-fuel level for routine generator exercise and other permitted tank users in its hospital guidance. The full-load runtime quantity, normal operating inventory, and physical tank capacity therefore need separate lines on the fuel schedule.

Distinctions

Type
A plant can have sufficient stored fuel for its Class and still fail its Type requirement because power returns too slowly. Review the fuel calculation and the transfer timing as separate acceptance evidence.
Generator duty rating
Standby or prime rating describes the generating set's permitted duty. The EPSS Class specifies the required energy duration.
Low-fuel alarm
In the cited HCAI calculation, the alarm marks the remaining required runtime reserve. It is not an empty-tank indication or the engine shutdown level.

Frequently asked questions

Does a 48-hour fuel calculation require a 48-hour load-bank test?

The duration calculation establishes energy capacity. Installation acceptance testing has its own specified sequence and duration; the class number alone does not define that test.

Can average building load establish the NFPA 110 Class?

The class definition uses rated load. Keep an operating estimate based on average load separate from the rated-load duration calculation.