Field glossary · measurement
Step load
A step load is an abrupt increase or decrease in demand. For generator selection, describe the load before the change, the switched block and the resulting load, then specify permitted voltage and frequency excursions and recovery times. Adding 400 kW to a 1,000 kW set already carrying 300 kW is a 40 percent rated-load step from 30 to 70 percent loading. It is a different event from applying that block to an unloaded set.
A block of load applied at once, the transient that often governs the size
Write the initial load and the added block explicitly
A 1,000 kW set carrying 300 kW that receives a 400 kW block moves from 30 percent to 70 percent of rated power. The applied step is 40 percent of rating. Relative to the preceding 300 kW load, the increase is 133.3 percent. A submittal that says only 40-percent step leaves the starting condition unresolved.
Include kW, reactive loading or power factor, motor starting behavior and the switching order in the load schedule. The engine responds to the real-power change while the alternator and regulator also respond to the current and reactive demand. The generator sizing guide covers selection of the set; the step schedule defines the transient it must accept.
Put the voltage and frequency limits on the same event
Cummins' 2025 Transient Performance of Generating Sets paper describes a customer-specific 60-percent load application with diesel frequency dip limited to 7 percent, voltage dip limited to 15 percent, and recovery to the respective bands within three and four seconds. Its discussion uses the ISO 8528-5:2018 framework. ISO's current published Part 5 is the sixth edition, ISO 8528-5:2025, issued in May 2025.
At 60 Hz and 480 V, the cited dips correspond to 55.8 Hz and 408 V. Cummins' customer-limit example also uses 2 percent recovery bands for both quantities: 58.8 to 61.2 Hz within three seconds and 470.4 to 489.6 V within four seconds. Returning to those bands is a separate criterion from staying above the dip minima. These are the cited customer-example limits, not a claim that any 60-percent step establishes ISO G3 classification.
Capture acceptance and rejection with adequate time resolution
Cummins calls for an adequate power-quality analyzer for transient-test accuracy rather than relying only on controller recordings. Record the initial state, actual applied block, minimum and maximum excursions, recovery bands and event times on the same run. A slow trend can miss the deepest part of the dip.
Kohler's ISO 8528-5 transient-performance paper treats full rated-load rejection as a separate test and identifies G4 as a user-specific performance category. A successful pickup therefore does not establish successful rejection, and a generic class label should not replace the agreed project load steps and limits. Preserve those details with the equipment selection and acceptance report.
Distinctions
- Ramp load
- A ramp changes demand over a stated duration. Its ramp rate and final load are different test inputs from an abruptly switched block.
- Steady rating
- The rating describes sustained capability under specified conditions. Transient acceptance also depends on the initial operating state and applied load characteristics.
Frequently asked questions
Does a G3 label mean the set accepts any 60-percent block?
No. The class assessment has a defined test basis. Specify the actual initial load, block characteristics, allowable excursions and recovery bands required by the project.
Sources checked
Also defined as
- Electrical: A block of load brought onto the set at once, the moment that motor inrush makes a generator sag