kW (real power)
Generator real power is signed electrical output in kilowatts, distinct from both engine shaft power and alternator kVA. A 1,000 kVA load at true PF 0.8 receives 800 kW. With export defined positive, a -100 kW reading indicates 100 kW flowing toward the set; verify the meter convention and connections before diagnosing motoring. Reverse-power protection uses a kW rating base, not kVA.
The power the engine produces and the load consumes, what the engine is sized for
Put the kW boundary at the electrical terminals
Cummins’ generator-ratings FAQ uses kWe to distinguish electrical kilowatts from mechanical engine power. Alternator losses separate the shaft input from the electrical output, so an engine power rating does not directly establish the kW available at the generator terminals.
For a generator acceptance record, label the metering location: generator terminals, downstream switchboard or load bank. Compare synchronized readings at the same operating point. Distribution loss and connected auxiliaries between those locations explain part of a difference without indicating missing engine output.
Understand why a paralleled machine can import kW
A generator connected to an energized bus can receive real power from the other sources if its mechanical input is insufficient. The machine then acts as a motor. Terminal voltage and frequency can remain close to the bus values while the direction of real-power transfer changes.
Cummins T-037 identifies ANSI function 32 as directional power protection for reverse kW. The protection watches the direction of active energy transfer; it is separate from reactive-power or excitation supervision. Keep the event’s signed kW trace with the breaker position and engine state.
Read the reverse-power percentage against its correct base
Cummins T-037 states that real-power protection percentages use the generator’s standby kW rating, and gives 10% as a typical default reverse-kW threshold. Cummins limits the threshold to the engine’s regenerative power capability.
For a 1,000 kW standby rating, a recorded 10% threshold represents 100 kW of reverse power. Dividing by a 1,250 kVA alternator nameplate instead would mix the units and misstate the protection basis. Record the installed threshold, time characteristic and the engine’s permitted regenerative power together.
Separate a real reversal from incorrect CT polarity
A negative reading on one phase of a consuming load can arise from a voltage-current channel mismatch or reversed CT polarity. Compare the meter’s phase mapping and total direction with independently established source and load states. Correct metering interpretation precedes any conclusion about motoring.
On a genuine event, several synchronized records should tell one story: real power changes direction, the paralleled breaker remains closed during the event and the protection responds on its configured characteristic. A lone negative number without its wiring convention and operating state does not establish that sequence.
Distinctions
- Reactive power
- kVAR describes reactive exchange. A reactive-power sign change is not proof of reverse real power.
- Exported energy
- kWh integrates real power over time. A short reversal can disappear inside a long interval total even though the instantaneous event matters to protection.
Frequently asked questions
Does falling frequency prove reverse power?
No. A machine paralleled to a strong energized bus follows bus frequency while its kW contribution changes. Use signed real-power measurement.
Is a negative generator kW reading always motoring?
Establish the meter’s import/export convention and verify phase mapping. Genuine motoring and an incorrectly connected meter require different corrections.
Sources checked
Also defined as
- The actual power the engine produces and a resistive load bank dissipates
- The power the engine produces and a resistive load bank dissipates