True power factor is kW divided by kVA at the same measurement boundary: 100 kW over 125 kVA is PF 0.80. Displacement PF uses only fundamental-frequency voltage and current, so it can read near 1.00 while harmonic current still raises total kVA. Record both PF type and leading or lagging direction before estimating capacity or selecting correction equipment.

Ratio of kW to kVA; gensets are commonly rated at 0.8 lagging

Used across 5 Anvilfield field guides, most in Datacenter.
Updated

Quantify the distortion gap

Fluke’s 39/41B manual defines displacement PF using fundamental-frequency active and apparent power, and true PF using power quantities that include harmonics. The two displays therefore answer different measurement questions.

ABB Technical Note 174, revision B, relates true PF to displacement PF divided by sqrt(1 + THDI²), assuming nearly sinusoidal voltage. Here THDI is harmonic RMS current divided by fundamental RMS current. Fluke’s manual distinguishes that fundamental-referenced THD from THD expressed against total RMS current; select the matching display and enter 40% as 0.40.

For displacement PF 0.99 and current THD 40%, the approximation gives 0.99 / sqrt(1 + 0.40²) = 0.919 true PF. At 100 kW, that corresponds to about 108.8 kVA. Use that measured distortion gap when defining a power factor correction scope, because a fundamental-frequency target alone leaves the remaining current burden unexplained.

Calculate the ceiling on displacement-only correction

Using ABB’s relationship with displacement PF equal to 1.0 and THDI still at 40% gives an approximate true-PF ceiling of 0.928. Perfecting only the fundamental phase alignment cannot produce true PF 1.0 while that current distortion remains.

At fixed distortion under that voltage-waveform assumption, moving displacement PF from 0.99 to 1.00 raises calculated true PF from 0.919 to 0.928. Carry the measured THD and true PF through the correction record so both the phase alignment and the waveform result are visible.

Combine power components instead of averaging power factors

For sinusoidal power, ABB gives apparent power as sqrt(kW² + kVAR²). To combine sinusoidal loads at one boundary, sum their real powers and signed reactive powers before applying that relationship.

ABB’s fundamental-frequency power triangle makes kVAR/kVA equal to sqrt(1 - PF²), so PF 0.8 corresponds to 0.6 kVAR per kVA.

Two loads each consuming 100 kW at displacement PF 0.8 each carry 75 kVAR in magnitude. When one is inductive and the other capacitive, their reactive powers cancel at the common boundary: 200 kW and zero net kVAR produce aggregate displacement PF 1.0. The arithmetic average of the two 0.8 magnitudes would miss that result.

Keep total true-PF metering for loads with significant harmonics. Cancellation of the fundamental reactive components does not establish cancellation of every harmonic current at the shared supply.

Distinctions

Efficiency
PF concerns the relationship between real and apparent electrical power. Conversion efficiency compares useful output with real-power input.
PF direction and sign
A magnitude alone does not identify leading, lagging, import or export. Preserve the instrument’s sign convention and load-direction indication.

Frequently asked questions

Does PF 0.8 mean twenty percent of the kVA is kVAR?

No. For a sinusoidal load, kVAR/kVA is sqrt(1 - 0.8²) = 0.6. The power components do not divide arithmetically into eighty and twenty percent.

Can a perfect displacement PF prove good true PF?

No. Inspect the true-PF and harmonic measurements at the same point and operating state.

Sources checked

Also defined as

  • Electrical: Ratio of real power to apparent power, kW divided by kVA, a number from 0 to 1

Where this shows up

Next step: Build a factory service route