Equipment class (A1-A4)

ASHRAE A1 through A4 labels identify tested operating environments for air-cooled IT hardware. The 2024 revised fifth-edition reference card sets allowable inlet temperatures at 15°C to 32°C for A1, 10°C to 35°C for A2, 5°C to 40°C for A3, and 5°C to 45°C for A4 before altitude derating. A usable equipment schedule also records moisture limits, approved hardware options, and temperature-change limits; a class label alone leaves those operating checks incomplete.

ASHRAE rating that sets a device's allowable temperature and humidity band

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Check the hardware behind an A3 or A4 claim

Lenovo's ThinkSystem SD530 maintenance manual makes A3 and A4 support conditional on supported processors and PCIe adapters, two redundant power supplies, and exclusion of 1100-watt supplies. Those conditions attach the environmental claim to an actual build, rather than to every configuration sharing the SD530 name.

Match the equipment schedule to the installed processor, adapter, power-supply, and cooling options. Lenovo specifically excludes PCIe SSDs and GPGPU cards from the SD530's A3/A4 configurations. A supported chassis with an excluded adapter therefore loses that environmental claim even if its model name stays the same.

ASHRAE's allowable air-cooling envelope establishes equipment functionality and permits power or thermal management within that envelope. It does not promise unchanged compute throughput at the upper limit. Carry the actual configuration's limit into the thermal-envelope operating schedule along with any manufacturer performance restriction.

How altitude changes the allowed inlet temperature

Lenovo's SD530 manual reduces the A2 upper inlet limit by 1°C per 300 m above 900 m, the A3 limit by 1°C per 175 m, and the A4 limit by 1°C per 125 m. The corresponding low-altitude upper limits are 35°C, 40°C, and 45°C. These published model limits make the altitude adjustment directly calculable.

At 1,800 m, the elevation above the 900 m threshold is 900 m. The A2 reduction is 900/300 = 3°C, leaving a 32°C maximum. The A4 reduction is 900/125 = 7.2°C, leaving 37.8°C. Enter the adjusted result in the operating limit schedule instead of carrying the low-altitude value into the alarm settings.

ASHRAE applies the same 1°C per 300 m altitude derating to A1, so its 32°C ceiling becomes 29°C at 1,800 m. The site elevation belongs next to every class-based alarm ceiling, not just those for extended-temperature hardware.

Check the dew-point cap and RH cap together

ASHRAE's 2024 reference card limits allowable upper moisture to both the dew-point and relative-humidity caps: A1 uses 17°C dew point and 80 percent RH, A2 uses 21°C and 80 percent, A3 uses 24°C and 85 percent, and A4 uses 24°C and 90 percent. Passing either reading alone does not establish compliance with the moisture envelope.

Record a lower-limit violation whenever inlet RH falls below 8 percent or dew point falls below -12°C; ASHRAE's lower boundary requires both tests to pass. Log inlet temperature, RH, and calculated dew point together in the humidity-control record so a change in dry-bulb temperature does not hide a crossed moisture boundary.

Read both temperature-change time windows

The 2024 revision of ASHRAE's fifth-edition Thermal Guidelines limits non-tape IT equipment temperature change to 5°C within 15 minutes and 20°C within an hour. The windows describe the difference between maximum and minimum inlet temperatures during each period, rather than an instantaneous slope inferred from two adjacent samples.

An inlet rising from 20°C to 26°C within ten minutes changes by 6°C. Both readings lie within ASHRAE's 18°C to 27°C recommended dry-bulb band, but the swing exceeds its 15-minute change limit. An hourly average conceals the event. Preserve sufficient trend detail to recover both the temperature extremes and the time window.

Distinctions

Shipping or powered-off specification
A storage temperature range describes another equipment state. It does not establish the environment supported while the server is operating.
Performance rating
An A4 rating does not guarantee equal throughput at 27°C and 45°C. ASHRAE permits thermal-management responses within the allowable air-cooling range; the hardware specification establishes the performance consequence.

Frequently asked questions

Can a server's supported ASHRAE class change after an upgrade?

Review the resulting configuration against the manufacturer's restrictions. Processor, adapter, and cooling-option changes affect which environmental claim applies.

Is the inlet's highest temperature enough to establish compliance?

Include altitude-adjusted limits, moisture conditions, and temperature-change windows. One peak value leaves those separate requirements unanswered.