Thermal envelope

In data-center specifications, a thermal envelope combines an inlet-temperature band with moisture limits and permitted temperature changes. ASHRAE's fifth-edition guidance recommends 18 to 27°C for classes A1 through A4, while manufacturer-designated H1 equipment has an 18 to 22°C recommended band. The wider allowable limits answer a different operating question. Identify the equipment class before applying a setpoint, then check humidity, elevation and temperature excursions at the same inlet.

The temperature and humidity range allowed at the IT equipment intake, per ASHRAE TC 9.9

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Read the equipment class before choosing a setpoint

ASHRAE's Fifth Edition Revised and Expanded reference card gives H1 equipment a 15 to 25°C allowable inlet range. An H1 intake at 24°C is inside that allowable band but above its recommended 22°C ceiling. Label those two limits separately on the controls schedule; an A2 label on a neighboring server does not extend the H1 limit.

The equipment manufacturer's declared class and environmental specification determine which comparison belongs in its record. ASHRAE's recommended range is operating guidance, while a project acceptance requirement comes from the equipment and project specifications. A dashboard should identify the basis of its alarm rather than call every temperature outside the recommended band a failed equipment limit.

Apply dew-point and relative-humidity ceilings together

ASHRAE's Thermal Guidelines for Data Processing Environments, Fifth Edition Revised and Expanded, pairs a recommended upper dew point of 15°C with an RH ceiling determined by corrosion conditions. The published reference card permits 70% RH where silver and copper coupon corrosion rates remain below 200 and 300 angstroms per month, respectively; elevated corrosion calls for 50% RH or lower. Both moisture constraints apply.

At the upper moisture boundary, use whichever of the RH and dew-point limits permits less water vapor at the measured temperature. Both limits must be satisfied. Reaching the RH ceiling does not permit a higher dew point, and a dew point below its ceiling does not override excessive RH. Preserve both points in the control graphics and humidity-control record.

Derate the allowable temperature for elevation

ASHRAE's reference card reduces the maximum allowable dry-bulb temperature for classes A1 and A2 by 1°C for each 300 m above 900 m elevation. An A2 ceiling of 35°C therefore becomes 33°C at 1,500 m: the 600 m elevation increment removes 2°C. Compare that adjusted ceiling with the equipment's own published environmental specification.

The elevation adjustment belongs to the equipment class, so applying an A2 correction to every device in a mixed aisle loses information. Record class and elevation with the limit calculation. A setpoint copied from a sea-level site does not preserve the same allowable margin at a higher site.

Check temperature excursions with time windows

ASHRAE limits inlet-temperature change for non-tape IT equipment to 5°C within any 15-minute period and 20°C within an hour. The reference-card notes define change as the maximum inlet temperature minus the minimum within the specified window, rather than a fitted average slope.

An inlet rising from 22°C to 28°C in ten minutes spans 6°C and exceeds the 15-minute change limit even though both readings fit an A2 allowable temperature range at sea level. A report containing only hourly averages cannot demonstrate that the shorter window stayed within bounds. Retain sufficiently frequent inlet observations and evaluate rolling windows during a transfer or cooling-recovery event.

Distinctions

Building thermal envelope
In roofing and energy-code work, the thermal envelope is the building boundary controlling heat transfer. The data-center equipment envelope describes environmental conditions at IT intakes. It is not an insulation or air-barrier assembly.

Frequently asked questions

Why does an older H1 table show a 5°C lower allowable temperature?

ASHRAE's May 31, 2022 errata corrected the H1 allowable dry-bulb range from 5 to 25°C to 15 to 25°C. Use the corrected reference card when recording limits alongside the thermal-setpoint guide.