Field glossary · measurement
Corrosion coupon
Read a data center corrosion coupon as two laboratory results, not one room average: copper and silver each have a corrosion-film growth rate. Purafil's published G1 criteria are below 300 angstroms per 30 days for copper and below 200 for silver. A copper pass cannot cancel a silver failure. Identify the metal, exposure dates, normalized reporting period and inlet location before comparing reports or using them to support a humidity setting.
A clean strip of copper or silver placed in the space; the corrosion thickness on it sets the severity level
Read actual exposure and monthly rate as separate fields
Purafil's CCC bulletin describes a laboratory result normalized to 30 days from the measured film and actual exposure duration. Transcribe the exposure days and normalized rate into separate fields. A raw thickness from a shorter exposure is not yet the monthly result; a laboratory number already labeled per 30 days needs no further time conversion.
The film is corrosion product accumulated on the test metal, not circuit-board thickness lost. Purafil publishes separate copper and silver limits under ANSI/ISA-71.04-2013, the edition still listed by ISA as of November 2026. Keep both metal results in the work order rather than reporting an averaged G1 number. Use the contamination-control guide to plan gas-filtration and source-control work after an elevated result.
Locate coupons in the air reaching the equipment
IBM's conductive-contamination guidance puts routine monitoring about 5 cm ahead of the frame's intake face, at heights one-quarter and three-quarters of the frame height; it also identifies locations with much higher air velocity. For a 2 m frame, the two fractional heights are 0.5 m and 1.5 m above the floor. Record which placement was used so the next exposure samples the same air path.
A coupon above a cabinet and one facing its intake represent different sampling positions. Retain the location sketch when comparing results before and after filter work. Moving the coupon while changing the filtration makes it harder to separate the treatment effect from the location change.
Keep exposure time separate from the return deadline
Purafil's sampling procedure specifies a typical 30-day exposure and allows up to 90 days in very mild environments. It also permits earlier return when a coupon becomes visibly corroded. The same procedure requires return within 90 days of receipt to preserve the coupon warranty; that receipt clock is separate from the exposure clock.
Start the exposure record when the coupon leaves its packing bag. Enter the installation and removal dates, company details and room identifier on its label, retain the panel number, and return it in the saved bag. Purafil states that missing required identification or date information prevents a report. Changing a guessed installation date to make the monthly rate look reasonable destroys the basis of the comparison.
Use both metals when judging humidity headroom
ASHRAE's Thermal Guidelines, fifth edition, revised and expanded, tie the 70% RH recommendation to copper below 300 and silver below 200 angstroms per month; the 2024 reference card directs 50% RH or lower when corrosion exceeds those limits. These RH ceilings operate alongside the dew-point boundary, so a favorable coupon does not by itself authorize a 70% setting at every inlet temperature. See the humidity-control guide for the equipment envelope.
ASHRAE's 2023 Applications Handbook recommends testing both metals at least twice yearly, covering winter and summer, for the expanded recommended envelope. It also reports that chlorine or hydrogen sulfide produced significant corrosion even at 50% RH in the cited research. Lowering humidity is therefore a control response, not proof that the gas problem has cleared. Pair repeat coupon results with the room's relative-humidity trend.
Distinctions
- Corrosion-film thickness versus pollutant concentration
- A film-growth result measures the metals' response to the exposure. Laboratory interpretation can identify contaminant classes, but an angstrom result is not itself a gas concentration in parts per billion.
- Atmospheric coupon versus cooling-water coupon
- Cosasco's water-treatment bypass rack exposes coupons to system water for weight-loss and pitting analysis. That test answers a piping-corrosion question; the atmospheric copper and silver film limits above do not classify a cooling-water coupon.
Field example
A 15-day exposure returns laboratory-normalized results of 240 angstroms per 30 days for copper and 260 for silver. Those monthly results are already comparable with Purafil's published G1 criteria: copper is at 240 / 300 = 80% of its limit, while silver is at 260 / 200 = 130% and exceeds its limit by 60 angstroms per 30 days. Retain 15 days as the actual exposure duration; doubling the laboratory's normalized results again would misstate both rates.
Frequently asked questions
Can a coupon identify the day a contamination event occurred?
The exposed film accumulates over the sampling interval. Its final thickness alone does not timestamp an event; correlate it with dated operating records and any continuous monitoring available for that location.
Does dark tarnish tell me the corrosion rate?
Visible corrosion is a reason to return a Purafil coupon early under its sampling procedure. The laboratory result establishes the film thickness and normalized rate; appearance alone does not supply either number.
Sources checked
- Purafil: Corrosion Classification Coupon product bulletin, CCC-4, 2018
- Purafil: Corrosion Coupon Sampling Procedure
- ISA: current standards list, including ANSI/ISA-71.04-2013
- IBM: conductive contamination, equipment-inlet monitoring locations
- ASHRAE TC 9.9: Thermal Guidelines, fifth edition revised and expanded, 2024 reference card
- ASHRAE 2023 Applications Handbook, Chapter 20: Data Centers and Telecommunication Facilities
- Cosasco: water-treatment bypass racks and weight-loss coupon analysis
Also defined as
- A copper or silver strip used to measure air corrosivity over time