ASHRAE Guideline 36 supplies detailed HVAC control sequences that designers adapt to the equipment and operating requirements of a project. As of November 5, 2026, the base edition is Guideline 36-2024, with published addenda that need explicit version control. A claim of 'G36 controls' is incomplete unless the submittal identifies the edition, applicable sequences, incorporated addenda, and project-specific settings.

ASHRAE's standardized high-performance control sequences for VAV systems and air handlers

Used across 2 Anvilfield field guides, most in HVAC.
Updated

Specify the edition and the actual control package

The ASHRAE Manitoba introduction to Guideline 36-2024 describes a package of hardwired point lists, operating sequences, and control diagrams. The design team must still select applicable systems and supply project settings. A controller library name does not establish that its points, alarms, modes, and reset logic match the approved design.

Create a sequence register with equipment identification, guideline section, edition, incorporated revisions, and approved departures. Connect that register to the VAV commissioning guide so a functional test can be traced to the exact sequence implemented. Keep downloaded controller code and the final narrative together at turnover.

Two 2026 revisions that change what gets tested

ASHRAE Addendum a to Guideline 36-2024, approved in February 2026, reduces the default fan-array stage delay from 15 minutes to 5 minutes. Its stated purpose includes avoiding long recovery times when arrays must climb through several stages. A test script built around the earlier delay would judge different behavior.

ASHRAE Addendum a also adds supply-fan staging when duct static pressure remains more than 10% below setpoint for 5 minutes. That condition supplements staging based on airflow demand. Test it with the relevant pressure and setpoint trends visible, rather than inferring successful staging from fan speed alone.

ASHRAE Addendum e to Guideline 36-2024, approved in September 2026, corrects fan-coil fault-condition equations FC#4 and FC#5 and clarifies which equipment configurations they cover. This is a diagnostic-logic revision, so merely checking that the fan coil changes modes will not verify its implementation.

A sequence library becomes a project obligation through adoption

California's 2025 Energy Code, Section 140.4(e)2D, invokes Guideline 36 for required DDC-controlled air economizers, but Section 100.1 identifies the incorporated edition as Guideline 36-2021. That code reference does not automatically incorporate the 2024 publication or its 2026 addenda. Identify the adopted-code edition and any additional owner-specified edition separately in the sequence register.

For each implemented sequence, identify the inputs that enable it, the controlled outputs, and the condition that ends it. Include transitions after overrides, loss of a required input, and recovery from shutdown. Resolve whether a controller's default value is a design selection or an unreviewed software setting before testing starts.

Keep acceptance evidence useful after handover

A trend demonstrates behavior only when its units, timestamps, sample interval, active mode, and relevant setpoints are known. Save the approved parameter values with each functional test. When an operator later changes a timer or reset limit, the sequence register should show which acceptance result needs to be repeated.

Request controls submittals that distinguish editable project parameters from fixed logic. That distinction lets an owner tune operation without accidentally removing the condition that enabled an alarm or changing the intended relationship between zone requests and central equipment response.

Distinctions

Building energy code
A code establishes enforceable requirements in its adopted scope. Guideline 36 supplies sequences that a code or project specification can incorporate.

Frequently asked questions

Does every published addendum automatically apply to an existing project?

Identify the contract edition and incorporated addenda first. Record later changes through the project revision process so software, narrative, and test expectations remain aligned.