In-row / close-coupled

In-row cooling serves nearby racks with units installed in the row; verify its useful duty at the selected air and water conditions. Schneider's ACRC301S selection gives 18.2 kW net sensible capacity at the conditions below, leaving 36.4 kW when one of three units is unavailable. Compare that surviving duty with rack heat load, and verify temperatures at the actual cabinet inlets.

A cooling unit set in the row between cabinets, drawing hot-aisle return and supplying the cold aisle over a short air path

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Read the sensible-capacity column at the selected condition

Schneider Electric's InRow technical specification 990-5792A-001 lists 18.2 kW net sensible capacity for an ACRC301S at 26.7°C dry-bulb/17.1°C wet-bulb entering air, 7.2°C entering water, and 5.5°C water rise. The same selection lists 18.4 kW total net capacity. The difference is latent cooling, which does not remove the rack's sensible heat load.

Three units at that selected sensible duty provide 54.6 kW. With one unavailable, the remaining pair provides 36.4 kW; a 40 kW row is short by 3.6 kW at those conditions. Carry the air condition, water condition, flow, and available fan operation into the schedule used to allocate row load.

A zero flow display can be a measurement-range problem

Schneider's ACRC301S performance notes warn that flow below 3.0 GPM can display as zero, and that 3.0 to 5.0 GPM can increase error in displayed flow and calculated power. A displayed zero at low duty is therefore not sufficient evidence of zero hydraulic flow.

Compare the indicated value with an independent measurement suited to that operating range and with entering/leaving water temperatures. During in-row functional testing, retain the controller's measurement limitations beside its calculated cooling output. This keeps low-load trends from being mistaken for calibrated capacity tests.

Budget the ports for rack sensors and leak detectors together

Schneider's ACRC301S/ACRC301H operation manual provides four combined ports for rack-inlet temperature sensors and leak detectors. Its allowance of up to four of either type is not an allowance for four of each simultaneously. The selected monitoring arrangement must fit the shared port count.

With three rack-inlet sensors connected, one port remains for a leak detector. Mark which cabinets the sensors represent, how group control uses them, and which areas the leak detector covers. A sensor near the easiest cable route can miss the hottest rack. Relate a high-temperature alarm to that physical location before changing the row setpoint or replacing a cooling component.

Distinctions

Net sensible versus total net capacity
Net sensible capacity addresses dry-bulb cooling after the stated fan-heat treatment. Total net capacity also includes moisture removal under the published selection conditions.

A row-cooling replacement needs a selection at the actual water and entering-air conditions; PorchRocket Bid Control tracks public HVAC solicitations and early capital-plan signals for this indoor work.

Frequently asked questions

Does a cold aisle temperature prove every rack is cooled?

It establishes the temperature only where measured. Match the sensor map to cabinet inlet locations and load distribution, including the cabinets farthest from the operating cooling units.

Sources checked

Also defined as

  • Cooling units placed between the racks to shorten the air path for higher density

Where this shows up

Next step: Find server-room HVAC bids

Back to the full field glossary