Rain load is the structural demand from water retained on a roof under its design drainage condition. ASCE 7-22 explicitly includes ponding head from structural deflection alongside static and hydraulic head. In inch-pound units, multiply their combined depth in inches by 5.2 to obtain pounds per square foot. Establish the storm, overflow performance, and loaded roof shape together because each contributes to the resulting demand.

The structural load from ponded water plus hydraulic head, per ASCE 7, about 5.2 lb/sq ft per inch

Used across 2 Anvilfield field guides, most in Roofing.
Updated

The ASCE 7-22 calculation includes three heads

ICC's 2024 IBC training presents the ASCE 7-22 rain-load relationship as R = 5.2 × (ds + dh + dp), with depths in inches and R in psf. The added dp is ponding head: water depth attributable to roof deflection under unfactored dead and rain loading. Retain that term when updating an older two-head calculation.

Establish one elevation datum for the undeformed roof and overflow inlet to obtain static head, ds. For hydraulic head, dh, read the overflow's test data or flow calculation at the design discharge. The structural analysis supplies dp. Keep these three inputs beside the drainage layout so the overflow detail and framing calculation refer to the same water surface.

Storm duration and building risk category

The 2024 IBC Section 1611.1, explained in ICC's training, bases the structural secondary-drainage calculation on a 15-minute-duration storm. Table 1611.1 assigns 100-year return periods to Risk Categories I and II, 200 years to III, and 500 years to IV. Those are storm durations and recurrence bases; the resulting intensity is still expressed in inches per hour.

ICC's 2024 example routes rainfall from 5,000 square feet at 8.71 inches per hour to the secondary system with the primary drainage blocked. Using Q = 0.0104 × area × intensity gives about 453 gallons per minute. The overflow's hydraulic data must supply the head at that flow; its nominal diameter alone does not supply dh.

A 27.3-psf roof-location calculation

With static head 3.00 inches, hydraulic head 1.50 inches, and calculated ponding head 0.75 inch, the combined depth is 5.25 inches. Applying the ASCE 7-22 relationship gives 5.2 × 5.25 = 27.3 psf. Leaving out the deflection contribution gives 23.4 psf, a shortfall of 3.9 psf at that analyzed location.

Keep the three depths visible in the calculation record. Raising the overflow changes ds; changing its opening or flow demand changes dh; changing member stiffness changes dp. The numerical result alone cannot show which design change caused the load to increase. On a controlled-flow blue roof, connect the detention operating levels to these same water elevations so the accumulated depth is accounted for once.

Hand off water elevations with the load

Carry the reference elevation, overflow inlet and opening geometry, storm duration and return period, flow demand, hydraulic head, and structural ponding result into the coordinated record. State whether each depth is referenced to the undeformed roof or the calculated deflected shape. That lets a later drain replacement or reroof detail be compared with the original loading basis. Explicitly identify the blocked-primary design case so a later calculation does not credit normal drain flow toward the required overflow capacity.

Distinctions

Rainfall intensity
An intensity in inches per hour sets incoming water flow. A retained depth in inches sets water weight at a roof location. Equal rainfall intensities can produce different roof loads through different outlet and structural conditions.

Frequently asked questions

Is ponding head the same as hydraulic head?

Hydraulic head drives flow through the overflow. Ponding head represents water depth added by structural deflection. Their separate origins are why ASCE 7-22 carries both terms.

Does a 15-minute design storm mean using one quarter of its intensity?

No. An intensity stated as 8.71 inches per hour remains 8.71 in the flow-rate equation even when it represents a 15-minute storm. Multiplying by 0.25 hour calculates rainfall depth over that interval, not the discharge rate used to size the overflow.

Sources checked

Also defined as

  • The roof load from ponded water, about 5.2 psf per inch of depth