ANVILFIELD Try FieldOS

Roofing

Roof drainage: sizing primary drains, overflow drains, and scuppers

How to size primary and secondary roof drainage, the design rainfall rate, the required overflow set 2 in above the low point, scuppers as weirs, and the rain load.

Roof DrainageRoof DrainsOverflow DrainsScuppersRain LoadRoofing

Direct answer

Roof drainage is the system that moves rainwater off a roof: primary drains or scuppers for normal rain, plus an independent secondary overflow set about 2 in above the low point in case the primary clogs. Size both for the design rainfall over the drained area. The adopted plumbing code and a structural rain-load check control the numbers.

Key takeaways

  • Low-slope roofs need two independent drainage systems: a primary sized for the design storm and a secondary overflow set about 2 in above the low point.
  • Roof drain flow Q in gpm equals 0.0104 times drainage area (sq ft) times design rainfall rate (in/hr); pick leader size from IPC tables.
  • Rain load R equals 5.2 times (static head plus hydraulic head) in psf; one inch of water weighs about 5.2 psf.
  • Use the 100-year design rainfall in in/hr; pull NOAA Atlas 14 and design to the higher of it and the code map.
  • Overflow scuppers are sized larger, commonly 3x the roof drains, with a minimum 4 in opening height, and must discharge separately above grade.

Roof drainage, and why it is two systems

Roof drainage is the system that gets rainwater off the roof, and on a low-slope roof it is two systems, not one. The primary drains or scuppers carry the normal rain. The secondary, or overflow, drains carry the storm the primary cannot, or the water that backs up when a primary drain clogs. Leave out the second one and you have designed half a roof.

The reason this is a structural problem and not just a plumbing one is weight. Water is heavy, about 5.2 lb per square foot for every inch of depth, and a flat roof that cannot shed it stacks that load in the low spots. The deck deflects, which lets more water collect, which deflects it further. That is ponding, and at its worst it runs away on the structure.

So roof drainage sits across two trades. The plumbing code sizes the pipes and the openings. The structural engineer sets how deep the water is allowed to get before the overflow takes over. Get those two coordinated and the roof drains. Miss the handoff and you get the leak, the ponding callback, or in the bad case the collapse.

Why roof drainage is a structural problem, not just a leak problem

Standing water does two kinds of damage, and the slower one is the one people underrate. The fast damage is the leak. Water sitting on a membrane finds every lap and seam, and most manufacturers condition the warranty on positive drainage, so a roof that ponds can lose its warranty before it ever leaks. That side of the story lives in the companion guide on roof crickets and tapered insulation, which covers the slope that feeds these drains.

The slow damage is load. A few inches of water over a wide roof is tons of dead load the deck may not have been designed to carry, and it lands exactly where the deck is weakest, the low spot it already sags toward. The drainage system is what keeps that load bounded. Primary drains hold the normal water depth low. The overflow caps the worst case. The structural rain-load calculation, covered later, depends entirely on where you set that overflow.

The membrane and the structure are drained by the same water. Size the drainage for the membrane and you protect the warranty. Size it for the structure and you protect the building. They are the same calculation looked at from two ends.

What does the code require for roof drainage?

The code requires two independent drainage paths sized for a design rainfall, and on most low-slope roofs that is not optional. The framework lives in the International Plumbing Code, Chapter 11 on storm drainage, with the roof-assembly side in the International Building Code and the residential equivalent in the IRC. The IPC sizes the drains, leaders, conductors, gutters, and scuppers from the roof area and the design rainfall rate. The IBC and ASCE 7 handle the structural rain load.

The parts you do not skip are these. Primary drainage sized for the design storm. A secondary or overflow system, independent of the primary, wherever the roof construction can trap water if the primary backs up, which on a parapet-ringed roof is always. The structure designed for the maximum ponded depth with the primary assumed blocked.

Section numbers move between code cycles, so confirm the article against the edition the jurisdiction actually adopted and any local amendments before you put it on a submittal. The principle does not move: two paths, sized for the storm, with the structure checked for the worst case.

What rainfall rate do you use to size roof drainage?

You use the design rainfall rate for the location, in inches per hour, from the rainfall maps in the plumbing code or from updated NOAA data. The code maps give a 100-year return-period rainfall at a 60-minute (one-hour) duration. That rate is the input to every drain, leader, and scupper calculation.

Here is the catch the old hands know. The rainfall maps printed in the IPC trace back to NOAA precipitation data from the 1970s, and the rates have not been refreshed across code cycles even as the storms have gotten heavier. The code allows approved data, and the current source is NOAA Atlas 14, the point-precipitation frequency atlas. On a building you actually care about, pull the Atlas 14 value for the site and compare it to the code map. Where Atlas 14 is higher, the conservative move is to design to it.

Primary and secondary can use different rates. Some methods size the primary for the 100-year 60-minute rate and the secondary for the shorter, heavier 15-minute burst, on the logic that the backup has to swallow the cloudburst. Confirm which rate pairs with which system in the adopted code.

Drainage area per drain or scupper

Sizing starts by dividing the roof into the area each drain has to carry, because the flow to a drain is just that area times the rainfall rate. On a flat field with drains laid out on a grid, each drain owns the area that slopes to it, which is roughly the area closest to it. The tapered insulation layout is what actually directs that area to the drain, so the drainage area and the slope design are the same drawing, covered in the cricket and tapered insulation guide.

Two things have to be in the area you assign. The roof itself, and any vertical wall that sheds onto it. A parapet or a higher wall draining onto the roof adds projected area, and the code has a method for adding a fraction of the vertical wall area to the horizontal roof area. Miss the wall contribution and the drain is undersized for the water that actually reaches it.

Do not average the roof and call it even. The low corner with two walls and the nearest drain forty feet away carries more than its share, and that is the drain that floods. Assign the area honestly, drain by drain, to the spot water actually runs to.

How do you size a roof drain?

You size a roof drain by computing the flow from its drainage area and the design rainfall, then picking the drain and leader size that carries that flow from the code table. The flow formula the trade and the IPC use is Q in gallons per minute equals 0.0104 times the drainage area in square feet times the rainfall rate in inches per hour. The 0.0104 is the unit conversion: one inch of rain per hour on one square foot is 0.0104 gpm.

Run the number, then go to the IPC sizing tables. Vertical conductors and leaders are sized for the flow in Table 1106.2, horizontal storm drains by flow and slope, and the table values change with pipe slope, so a horizontal run at 1/8 in per ft carries less than the same pipe at 1/4 in per ft. Pick the size that carries your flow at the slope you can actually build.

The drain body and the leader are two separate checks. A drain bowl rated for the flow still chokes if the leader below it is undersized, and the strainer dome over it reduces the open area, which the rated drain capacity already accounts for. Size the whole path, not just the bowl.

What is a secondary (overflow) drain and why is it required?

A secondary, or overflow, drain is the independent backup that carries water off the roof when the primary drainage clogs or is overwhelmed, and on most low-slope roofs the code requires it. The rule sits in the IPC and the IBC roof-assembly provisions: wherever the roof construction can entrap water if the primary drains back up, you provide secondary overflow drains or scuppers.

The detail is specific and worth carrying in your head. Overflow drains are the same size as the primary roof drains, set with the inlet flow line about 2 in above the low point of the roof. That 2 in is a dam. It lets the primary do its job in normal rain, and it only starts passing water once the level rises, which it does when the primary is blocked. Overflow scuppers are sized larger, commonly three times the size of the roof drains with a minimum opening height of 4 in, and the inlet is set the same 2 in above the low point. Confirm these figures against the adopted code edition.

The independence is the whole point, and it is the part that gets violated. The overflow must discharge separately from the primary, not tie into the primary lines, and it must discharge above grade somewhere people see it. A stream of water pouring off a parapet scupper in a storm is the warning that the primary is plugged. Pipe the overflow into the primary and you have thrown that warning away, and the two systems clog together.

How do you size a roof scupper?

You size a scupper as a weir, because a scupper is an opening that water flows over or through, and the flow depends on the width of the opening and the depth of water over it. The underlying physics is the Francis weir formula: Q in cubic feet per second equals 3.33 times the weir length in feet times the head in feet to the 1.5 power. The contracted form, Q equals 3.33 times the quantity L minus 0.2H, times H to the 1.5, accounts for the water pulling in at the ends of the opening.

The head is the lever. Flow climbs with the 1.5 power of the depth over the scupper, so a little more allowable water depth buys a lot more flow, which is exactly why the structural water-depth limit and the scupper size are one decision. The IPC gives scupper sizing tables so you do not run the weir formula by hand on every job, but the formula is what the table is built from.

Two scupper rules come straight from the code. A scupper opening is at least 4 in high. The opening width is at least the circumference of a roof drain sized for the same area, so the scupper is never narrower than the round drain it replaces. An open scupper is a notch in the parapet with no top; a closed scupper is a rectangular hole through the wall, and the closed one acts as a weir only until the water rises to its top, then it behaves like an orifice and the flow assumption changes. Size the closed scupper so the design flow stays in the weir range, below the top of the opening.

Leaders, conductors, and the horizontal storm drain

The drain is only the inlet. Below it the water runs down a leader, also called a conductor, and then out through a horizontal storm drain to the site system, and each of those is sized from the same flow. A leader is the vertical pipe outside, a conductor is the same pipe inside the building, and the horizontal storm drain is the sloped run that carries the combined flow from several drains.

Vertical pipe carries more than horizontal pipe of the same diameter, because gravity does the work in the vertical and the horizontal relies on slope. The IPC sizes vertical conductors by flow alone and horizontal storm drains by flow and slope together. A horizontal storm drain at 1/4 in per ft carries more than the same pipe at 1/8 in per ft, so the slope you can fit under the structure affects the pipe size you need.

The combining run is where it adds up. A horizontal main collecting four drains carries the sum of the four flows, not one, and it has to be sized for that total at its slope. Size each branch for its drain and the main for everything downstream of the last connection, the same logic as sanitary drainage but driven by roof area and rainfall instead of fixtures.

Rain load, ponding, and the structural check

The structural side of roof drainage is the rain load, and it is set by where the water is allowed to stand, which is set by the overflow. The IBC and ASCE 7 give the rain load as R equals 5.2 times the quantity ds plus dh, in pounds per square foot. ds is the static head, the depth of water up to the overflow inlet with the primary assumed blocked. dh is the hydraulic head, the extra depth above that inlet needed to push the design flow through the overflow. The 5.2 is the weight of one inch of water per square foot.

That formula is why the overflow inlet height and the overflow size both feed the structure. Set the overflow inlet high and ds grows. Undersize the overflow and dh grows, because it takes more depth to force the flow out. Either one raises the rain load the deck has to carry.

Then there is ponding instability, the runaway case. Water deflects the deck, the deflection holds more water, and on a roof too flat and too flexible it does not stop. ASCE 7 evaluates susceptible bays for ponding instability in its structural-loads chapters, and a roof sloped at least 1/4 in per ft toward drainage generally falls outside that check. This is the same 1/4 in per ft minimum the cricket and tapered guide is built around, and it is one more reason the slope is not negotiable. Confirm the rain load and the ponding analysis with the structural engineer and the adopted edition of ASCE 7, which reworked the rain-load provisions in its 2022 edition to handle the ponding head explicitly.

Putting drains at the low points

A drain only works where water goes, so drains belong at the low points, and on a tapered roof the low points are something you build, not something you find. The tapered insulation layout slopes the field to the drains and drops a sump in at each one, a recessed area in the last few feet that gets the membrane below the surrounding field so water reaches the bowl instead of ringing around it. That sump and the slope to it are covered in the cricket and tapered insulation guide.

Put a drain where the structure deflects and you let the deck help. Put it at a structural high point and the tapered package fights the deck the whole way. Interior drains generally sit in from the edge in the field of the roof, away from the perimeter high points, so the field slopes inward to them. Scupper drainage runs the other way, sloping the field out to the parapet openings.

The pairing at the low point gets crowded. The primary drain, its sump, and the overflow all stack at or near the same low spot, with the overflow inlet 2 in up. That is a busy detail that deserves a real section drawing, not a note, because the sump depth, the drain, and the overflow height all have to coexist there.

The drain assembly: bowl, clamping ring, strainer, and sump

A roof drain is an assembly, and each part has a job. The drain bowl is the cast or formed body that collects the water and connects to the leader. The clamping ring bolts down over the membrane and compresses it against the bowl to make the watertight seal, and it doubles as the gravel guard. The strainer, or dome, is the cage over the inlet that keeps leaves and debris out of the leader. The sump is the recess in the deck and insulation that the bowl sits in. How you flash the membrane to the bowl under that clamping ring is covered in the roof penetration flashing guide.

The strainer is where capacity and clogging fight. The dome has to pass the design flow while blocking debris, and the rated capacity of a drain already accounts for the dome being in place, so do not size off the open bowl. Pull a dome to clear a clog and forget to replace it and the next storm sends debris straight into the leader, where it clogs somewhere you cannot see.

On a retrofit, the assembly changes. A retrofit drain is a smaller bowl that slips inside the existing drain to reconnect a re-roofed surface to the old leader, and the ANSI/SPRI RD-1 performance standard covers those. The retrofit always has a smaller throat than the original, so check that the smaller drain still carries the design flow before you trust it.

Controlled-flow, blue roofs, and siphonic drainage

Three approaches change the basic gravity-drain model, and each shows up on specific jobs. Controlled-flow drainage, sometimes the basis of a blue roof, uses restricting drains that meter water off the roof slowly and let the roof hold a shallow, planned pond during a storm. It cuts the peak flow into the site storm system, which is a stormwater-management win in dense areas, but it deliberately loads the roof with water, so the structure has to be designed for that ponded depth and the membrane has to tolerate the standing water. This is not a way around the rain-load calculation. It is a way to trade peak flow for held load on purpose.

Siphonic drainage is the high-flow approach for large roofs. Special outlets with baffle plates exclude air so the pipe runs full-bore, and the full pipe creates negative pressure that pulls water out far faster than gravity, with smaller pipe and fewer downspouts. It suits big flat roofs, warehouses, and distribution centers, and it is engineered as a system by the supplier, not sized off the standard tables. The horizontal mains run nearly level instead of sloped.

Both are specialty designs. Use them where the roof area or the stormwater rules justify the engineering, and keep the secondary overflow requirement in mind, because a siphonic or controlled-flow primary still needs a backup for the case it fails or clogs.

Gutters and downspouts on the edge-drained roof

Not every roof drains to interior drains. Many low-slope and most steep-slope roofs drain to the edge, into gutters that carry the water to downspouts. The gutter is sized for the flow from the area that drains to it, the same area-times-rainfall flow as an interior drain, and the IPC gives gutter sizing tables by flow and gutter slope. A gutter run too flat or too small overtops in the storm and dumps water down the wall it was meant to protect.

The downspout is the leader for an edge system, and it is sized for the flow the gutter delivers. Space downspouts so no single one carries more than its share, and remember the gutter between two downspouts has a high point in the middle the same way a roof field does between two drains.

Two standards sit on external gutters. ANSI/SPRI GT-1 is the test standard for how an external gutter holds up structurally, the wind and load side, and the companion GD-1 covers structural design. Neither sizes the gutter for water flow, so use the plumbing code tables for capacity and the SPRI standards for the structural attachment. Confirm both against the adopted code and the project.

How often should roof drains be inspected?

Roof drains should be checked on a schedule and after every major storm, because the failure that floods a roof is almost never the design. It is a blocked drain. A strainer packed with leaves, a ball of debris in the sump, a plastic bag over the dome in a windstorm, and the primary stops draining while the rain keeps coming. Then the overflow is the only thing between the roof and the rain load, and if nobody verified the overflow, the roof is on its own.

Walk the drains in spring and fall at a minimum, more in a leaf-heavy or industrial setting, and clear the strainers and the sumps. Confirm the dome is in place and intact on every drain, because a missing dome turns the next clog into a leader blockage. Check that the clamping ring bolts are tight, since a loose ring leaks under a perfectly good membrane.

Test the overflow at least once. Plug the primary, run water, and watch the overflow take over at the right level and discharge where it should, visibly and above grade. That test is the only proof the backup actually works, and it is worth doing at closeout and periodically after. The drain you never inspect is the one that floods the roof.

Large flat roofs and the data center case

On a big flat roof the stakes scale with the area, and the data center is the sharp case. The roof is enormous, dead flat, and sits directly over equipment that a single leak can take down, so the drainage gets designed with margin the warehouse next door does not get. More drains, generous overflow, and often a higher design rainfall than the code minimum, because the cost of the storm that overwhelms a code-minimum design is measured in downtime, not in roof repair.

The stakes change the redundancy thinking. A blocked primary on a data center roof cannot be allowed to become a leak over a server hall, so the secondary is sized and placed as a true equal backup, the overflow discharge is watched, and the inspection cadence is tight. Some owners add leak detection at the deck so a breach is found before it reaches the equipment.

The same physics governs as any roof. The difference is the margin and the consequence. Size a small commercial roof to the code and you are fine. Size a data center roof to the code minimum and you have ignored what is under it. Match the drainage redundancy to what a flooded roof would cost, and on the critical building that cost is the whole reason the building exists.

Field example: sizing drains for a 12,000 ft² roof

Take a 12,000 ft² flat roof section in a location with a design rainfall of 4 in per hour, drained by four interior drains laid out on a grid so each carries about 3,000 ft².

Flow per drain: 0.0104 times 3,000 ft² times 4 in per hour gives 124.8 gpm at each drain. Total roof flow is four times that, about 499 gpm, which is the number the horizontal main collecting all four has to carry at its slope. From the IPC vertical conductor table, a flow near 125 gpm falls within a 4 in conductor, so each drain gets a 4 in leader; confirm the size against the adopted table and the actual head.

Now the overflow. The secondary carries the same flow, sized the same way, with its inlet set 2 in above the low point. If it is scuppers instead, size each as a weir for the flow at the allowable head above the 2 in inlet.

Then the structure. With the overflow inlet at 2 in, the static head ds is 2 in, and say the overflow needs another 1 in of hydraulic head dh to pass its flow. Rain load R equals 5.2 times the quantity 2 plus 1, about 15.6 psf, the load the deck carries at the worst case with the primary blocked. Change one input, the rainfall rate, the drain count, or the overflow height, and every number downstream moves.

Flow from area (gpm)Qgpm = 0.0104 × Aft² × iin/hr
Scupper weir flow, Francis (cfs)Qcfs = 3.33 × L × H1.5
Rain load (psf)Rpsf = 5.2 × (ds + dh)
A
Drainage area in square feet, the roof area plus any wall area that sheds onto it
i
Design rainfall rate in inches per hour, from the code map or NOAA Atlas 14
L, H
Scupper weir length and the head of water over it, in feet
ds, dh
Static and hydraulic head in inches, set by the overflow inlet height and its design flow
InputValue
Roof section area12,000 ft²
Design rainfall4 in/hr
Drains4, each ~3,000 ft²
Flow per drain (0.0104 x A x i)124.8 gpm
Total roof flow~499 gpm
Leader per drain (IPC table)4 in, confirm vs head
Overflow inlet height2 in above low point
Rain load R = 5.2(2+1)~15.6 psf

What to document

The drainage record is what answers the question when a roof floods and someone asks whether it was ever sized right. The flows, the rainfall rate, the drain and overflow sizes, and the rain load are the evidence that the design met the storm, and they are what the structural engineer, the plumber, and the next re-roofer all need.

Capture the design rainfall rate and its source, the drainage area assigned to each drain, the flow per drain, the primary drain and leader sizes, the overflow type, size, and inlet height, the calculated rain load, and the overflow test result. Note whether you designed to the code map or to a higher NOAA Atlas 14 rate, because the next person needs to know which storm the roof was built for.

Field to recordWhy it matters
Design rainfall rate and sourceSets every flow; says which storm the roof meets
Drainage area per drainThe flow each drain must carry
Flow per drain (gpm)The basis for the drain and leader size
Primary drain and leader sizeWhat carries the normal storm
Overflow type, size, inlet heightThe backup, and the structural water depth
Calculated rain load (psf)Ties drainage to the structural design
Overflow test resultProof the backup actually works

Common mistakes

  • Leaving out the secondary or overflow drainage entirely, so a clogged primary has nowhere to send the water.
  • Setting the overflow inlet at the same level as the primary, so both pass water together and there is no warning the primary failed.
  • Tying the overflow discharge into the primary lines, so the two systems clog together and the visible warning is lost.
  • Sizing the drains for an old or low rainfall rate when the site's NOAA Atlas 14 value is higher.
  • Assigning an even average area to each drain instead of the real area, so the low-corner drain is undersized for the water that reaches it.
  • Forgetting the wall area that sheds onto the roof when computing the drainage area.
  • Sizing the drain bowl but undersizing the leader or the horizontal main below it.
  • Accepting ponding as normal instead of treating it as a drainage or slope failure.
  • Leaving a strainer dome off after clearing a clog, sending debris into the leader.
  • Setting the overflow without coordinating its height and size with the structural rain-load limit.

Field checklist

0 of 11 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

The plumbing code is where the sizing lives. The International Plumbing Code, Chapter 11 on storm drainage, sizes the roof drains, leaders, conductors, horizontal storm drains, gutters, and scuppers from the roof area and the design rainfall, with the conductor and storm-drain tables in Section 1106 and the scupper and secondary-drainage provisions in Sections 1106 and 1108. The International Building Code carries the roof-assembly and secondary-drainage requirements, and the IRC carries the residential equivalent in its roof-assembly chapter. Section numbers shift between code cycles, so confirm them against the adopted edition and any local amendments before citing them on a submittal.

The structural side is ASCE 7, which gives the rain load R equals 5.2 times the sum of the static and hydraulic head, and the ponding-instability evaluation for susceptible bays, in its rain-load and structural-loads chapters. The 2022 edition reworked the rain-load provisions to handle the ponding head explicitly. The design rainfall itself comes from the code rainfall maps or, better, from NOAA Atlas 14 point-precipitation frequency data, which the code allows as approved data.

The trade and product standards round it out. The NRCA Roofing Manual is the practical reference for roof drainage, slope, and ponding. ANSI/SPRI RD-1 covers retrofit roof drains and ANSI/SPRI GT-1 the testing of external gutter systems, with GD-1 on gutter structural design. FM Global data sheets carry their own drainage and rain-load requirements on insured roofs, sometimes stricter than the base code. Above all of it, the membrane manufacturer's warranty conditions on positive drainage decide whether your drainage keeps the warranty in force.

Units, terms, and conversions

Roof drainage spans the plumbing and structural worlds, so the same quantity shows up in different units across a storm-drainage plan, a structural calc, and a product sheet.

Flow is in gallons per minute on the plumbing side and sometimes cubic feet per second on the weir side, where 1 cfs is about 449 gpm. Rainfall rate is in inches per hour. Roof area is in square feet. Rain load is in pounds per square foot, and one inch of water depth weighs about 5.2 psf. A leader is the vertical drain pipe and a conductor is the same pipe inside the building. A scupper is an opening through a parapet; a primary drain carries the normal storm and a secondary or overflow drain is the backup set above the low point.

Primary drainage
The drains or scuppers that carry the normal design storm off the roof
Secondary / overflow drainage
The independent backup, inlet set about 2 in above the low point, for a blocked or overwhelmed primary
Scupper
An opening through a parapet that drains water off the roof edge, sized as a weir
Leader / conductor
The vertical drain pipe; a leader outside, a conductor inside the building
Design rainfall rate
The 100-year rainfall in inches per hour for the site, from the code map or NOAA Atlas 14
Static head (ds)
Water depth up to the overflow inlet with the primary assumed blocked
Hydraulic head (dh)
Extra depth above the overflow inlet needed to pass the design flow
Rain load
The roof load from ponded water, about 5.2 psf per inch of depth

Related tools

Calculators and readiness checks for this work

Compare your options

FAQ

How do you size a roof drain?

Size a roof drain from its flow: 0.0104 times the drainage area in square feet times the design rainfall in inches per hour gives the gpm. Then pick the drain and leader size that carries that flow from the IPC storm-drainage tables at the slope you can build. Confirm against the adopted code edition.

What is an overflow drain on a roof?

An overflow, or secondary, drain is the independent backup that drains the roof when the primary clogs or is overwhelmed. Its inlet sits about 2 in above the low point, so it only flows once water backs up, and it discharges separately and above grade where the stream warns you the primary failed.

How do you size a roof scupper?

Size a scupper as a weir, where flow rises with the 1.5 power of the water depth over the opening. The Francis formula, Q equals 3.33 times length times head to the 1.5, is the basis, and the IPC scupper tables apply it. The opening is at least 4 in high and as wide as a drain's circumference.

What rainfall rate do you use to size roof drainage?

Use the 100-year design rainfall in inches per hour for the site. The code prints rainfall maps, but they trace to 1970s NOAA data, so pull the current NOAA Atlas 14 value and design to the higher of the two. Some methods size the primary at a 60-minute rate and the secondary at a heavier 15-minute rate.

Is a secondary overflow drain required by code?

On most low-slope roofs, yes. The IPC and IBC require secondary overflow drains or scuppers wherever the roof construction can trap water if the primary backs up, such as any parapet-ringed roof. The overflow must be independent of the primary and discharge separately. Confirm the requirement against the adopted code edition and local amendments.

Why does the overflow inlet sit 2 in above the low point?

The 2 in acts as a dam. It keeps the overflow dry in normal rain so the primary does the work, and it only starts passing water once the level rises, which happens when the primary is blocked. That height also sets the static head in the structural rain-load calculation, so it is coordinated with the engineer.

How do you calculate the rain load on a flat roof?

Rain load is R equals 5.2 times the sum of the static head and the hydraulic head, in pounds per square foot, where 5.2 is the weight of one inch of water. Static head is the depth to the overflow inlet with the primary blocked; hydraulic head is the extra depth to push the flow through. ASCE 7 governs.

What size pipe do I need for a roof drain leader?

Size the leader for the flow the drain collects, 0.0104 times the drainage area times the rainfall rate in gpm, from the IPC vertical conductor table. Vertical pipe carries more than horizontal of the same size, and a 4 in leader handles a few hundred gpm. Size the horizontal main for the sum of the drains it collects.

What happens if a roof drain gets blocked?

A blocked primary drain stops draining while rain keeps falling, so water rises until the secondary overflow takes over. If there is no overflow, or it was never tested, the water keeps stacking and loads the deck toward ponding and possible collapse. Inspect and clear drains on a schedule and after every major storm.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.