Recirculation
At an inlet supplied with 20 C air, a 25 C reading can result from mixing 25% exhaust at 40 C with 75% supply. That is a local recirculation estimate from a steady heat balance, not a room-wide loss of cooling capacity. PG&E's airflow-based recirculation ratio instead needs recirculated flow divided by total intake flow; temperature and airflow indices coincide only when their mixing assumptions match.
Hot exhaust air pulled back into the equipment inlets, raising inlet temperature above supply
Estimate exhaust mixing from three temperatures
HP Laboratories' 2005 HPC User Forum presentation defines Supply Heat Index, SHI, as heat gained before equipment entry divided by the total heat rise from supply to equipment exhaust. For one intake and exhaust pair, its temperature form is SHI = (T_inlet - T_supply) / (T_exhaust - T_supply). Use readings from the same operating period.
With supply at 20 C, inlet at 25 C and contributing exhaust at 40 C, the calculation is (25 - 20) / (40 - 20) = 0.25. Under a steady two-stream mixing balance with equal specific heats and no other heat input, that also represents a 25% exhaust fraction at the inlet. The balance is a local estimate derived from the measured temperatures.
After closing the identified path, an inlet of 22 C with the same supply and exhaust temperatures gives 0.10. The estimated exhaust share has fallen from 25% to 10%. Record the temperatures alongside the fraction so a change in supply conditions cannot masquerade as a sealing improvement.
Keep a heat index separate from an airflow ratio
PG&E's Data Center Air Management Research report (2010) defines recirculation ratio as recirculated airflow divided by total equipment-intake airflow, with zero representing no recirculation. That is a flow fraction; SHI describes preheating. PG&E places SHI on a zero-to-one scale, with zero indicating that every measured intake equals the supply temperature. The two indices agree numerically for the simple mix above; room layouts with several air paths need separate heat and flow accounting.
HP Laboratories' SHI formulation weights heat transfer by mass flow, so combining racks requires their airflow contributions as well as temperatures. Averaging a small rack's index with a much larger rack's index gives the small rack too much influence. The airflow-management guide covers the physical sealing work; these distinctions make its before-and-after measurements comparable.
Take two racks with the same 20 C supply-to-exhaust span, mass flows of 1 and 4 kg/s, and SHI values of 0.40 and 0.10. Their combined SHI is (1 x 0.40 + 4 x 0.10) / 5 = 0.16. A plain average reports 0.25. Equal temperature spans make mass-flow weighting sufficient in this case; unequal spans require weighting the heat terms themselves.
Choose the supply measurement before tracing the leak
The supply reference must describe the cool stream that actually reaches the mixing point. Air warmed along its delivery path by another heat source raises the inlet-to-supply difference without proving server-exhaust recirculation. Move the reference downstream of that heat gain when isolating the exhaust contribution.
Likewise, several exhaust streams at different temperatures need a representative mixed-exhaust value. Pair the temperature survey with the observed path through the cabinet or aisle boundary. The containment acceptance guide identifies the locations to inspect once the affected inlet is known.
Distinctions
- Bypass air
- PG&E divides bypass airflow by total cooling supply, while its recirculation ratio divides recirculated exhaust by total equipment intake. The fractions have different denominators even when they describe the same room.
- Water recirculation
- A plumbing return or living-wall irrigation loop deliberately returns water for reuse. Its flow and heat-loss calculations do not use the air-mixing index above.
Frequently asked questions
Is an SHI of 0.25 a 25% loss of cooling capacity?
No. It describes preheating relative to the supply-to-exhaust heat rise. Chiller capacity, fan electricity and useful cooling at the rack are separate quantities.
What does SHI below zero or above one mean?
The two-stream calculation requires the inlet temperature to lie between the cool-supply and contributing-exhaust temperatures. A result outside zero to one breaks that ordering. Recheck the reference locations, timestamps and other heat inputs before treating the result as an exhaust fraction.
Sources checked
Also defined as
- Landscaping: Catching runoff at the base in a tank and pumping it back to the top, reusing the water and the feed
- Hot exhaust that loops back into the cold aisle and raises the server inlet temperature