Field glossary · component

Brush grommet

A brush grommet controls air leakage at a cable opening while allowing the cables to remain accessible. Its outside dimensions, required panel cutout and usable cable passage are separate dimensions. Select the fitting around the opening geometry and the installed bundle, including whether the floor panel must lift away without disconnecting cables. Bristles close a leakage path; they do not make the opening a structural walking surface.

A sealed cable cutout fitting whose brush or gasket closes the floor opening around the cables

Used across 4 Anvilfield field guides, most in Datacenter.
Updated

Which dimension should the floor crew cut?

Upsite's KoldLok 1010/3030 installation guide lists an 8 by 4 inch usable cable passage, smaller than both the panel cutout and the fitting's outside frame. The dimensions below identify different boundaries; the frame overhang supports the fitting on the panel.

Use the row for the actual opening orientation when issuing the cut ticket. With the grommet's long side on the tile edge, fit the supplied underside foam strip. Pair the fitting drawing with the panel-support detail in the raised-floor installation record so the cut leaves the required bearing material.

Dimension for KoldLok 1010/3030Published size
Outside frame, including depth11 by 8.25 by 1.625 inches
Usable cable passage8 by 4 inches
Cutout within the panel9.25 by 6.75 inches
Cutout with the grommet's long side at the panel edge9.25 by 7.5 inches
Cutout with the grommet's short side at the panel edge6.75 by 10.25 inches

Integral or split: will the panel clear the cables?

Upsite identifies the KoldLok 3030 as a split integral grommet that allows the tile to move without capturing the cables. That is a service-access feature, separate from the brush's air-sealing performance.

Trace the actual removal path at a loaded cabinet. A one-piece frame surrounding a permanent bundle leaves the panel tethered even after it has been lifted from its supports. The split configuration separates around the bundle, but the panel still needs room to move past the rack feet, cable supports and neighboring fittings. Record the selected frame type on the cable-opening schedule.

Reading a brush seal performance claim

Upsite's Integral data sheet describes effective sealing at 0.10 inch water column with four half-inch cables through the grommet. That stated bundle and pressure are part of the claim; the sheet does not publish a zero-leakage acceptance value for every cable arrangement.

Observe where the bundle pushes the opposing filaments apart and where the flange meets the panel. A narrow opening along the frame needs a frame-seal correction, while a dense bundle that holds the brushes apart calls for a different opening arrangement. Separating those paths makes a follow-up airflow reading useful instead of replacing a sound fitting without fixing its surrounding gap.

Distinctions

Firestop
A cable-opening air seal and a tested firestop system serve different requirements. Upsite lists a UL 94 HB material rating for the Integral grommet; that designation does not establish an hourly rating for a penetrated floor assembly.

Sources checked

Also defined as

  • A sealed bristle insert for a floor cable cutout that passes cable while stopping bypass air
  • The sealing collar at a cable cutout that passes cable but blocks bypass airflow

Where this shows up