Field glossary · component

Pedestal

A raised-floor pedestal must hold the selected panel elevation and transfer loads into its slab attachment. Check its adjustable head, base connection and restraint separately: an intact adhesive bond does not prove the height lock works, and a high compression rating does not establish lateral capacity. Identify which connection moved before prescribing a repair, then compare its condition with the tested support assembly.

The adjustable column, base plate plus threaded tube and head, carrying axial load from the panels to the slab

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Why a 6,000 lb axial test is not a lateral rating

Tate's February 2026 ConCore 1500 PosiLock specification requires a pedestal axial test load of at least 6,000 lb without permanent deformation. That load acts down the support axis. It is not a lateral force rating and does not establish a rack's allowable load on a panel.

The same Tate specification requires an average overturning test moment of 1,000 inch-pounds for the pedestal bonded to clean, sound, uncoated concrete. Moment combines force and lever arm. At a 20-inch lever arm, a 50 lb sideways force produces 1,000 inch-pounds; at 25 inches, the same force produces 1,250 inch-pounds. These calculations compare demands, while the project design establishes the resistance required for the floor.

Read the failure location, not just the leaning head

A disturbed pedestal can rotate at its height adjustment, separate from its adhesive, or move with a failed surface layer beneath the adhesive. Those observations describe different repairs. Photograph the base, slab surface and head orientation before the evidence disappears beneath a replacement panel.

For finished floors at least 6 inches high, Tate's PosiLock specification requires the threaded head to resist free rotation through its anti-rotation device. A pedestal that remains bonded to the slab but loses its level when panels are lifted therefore needs attention at the head and lock, not another bead of adhesive around the base.

Keep stringer torque separate from pedestal attachment

Tate's September 2025 installation manual specifies 30 inch-pounds for attaching stringers to pedestal heads with a torque-limiting screw gun. That is 2.5 foot-pounds, not 30 foot-pounds. The number belongs to those stringer screws, not to an anchor or an adjustable locking nut.

Identify the fastener being checked on the inspection record. A torque value without a component name can send the next crew to the wrong connection. Attach the support model and tested floor height to the raised-floor installation record so a later repair can recover the original configuration.

Frequently asked questions

Can a taller pedestal use the same lateral-force allowance?

Its taller lever arm creates more overturning moment for the same horizontal force. Match the support height, base attachment and bracing configuration to the approved assembly; carrying over a compression rating does not answer the lateral question.