Rolling load

Rolling load is the force a moving wheel places on the access-floor system. Its published rating applies to a specified wheel, number of passes and deformation limit, not to the gross weight of a rack. Tate's ConCore 1500 PosiLock supports a published 900 lbf rolling test for 10,000 passes with a 6 in by 2 in wheel. Compare the actual caster reactions and dimensions with that complete test condition.

Dynamic load from a wheel rolled across the panel for a set number of passes, the data-hall case that usually governs

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Read the wheel and pass count beside the published load

Tate's ConCore 3000 bare bolted-stringer assembly has a published 2,400 lbf repeated-traffic rating with a 10 in diameter, 4 in wide wheel. That larger wheel is part of the rating. Keep the wheel conditions attached to the selected product data when comparing it with the ConCore 1500 PosiLock:

The ConCore 1500 ratings come from separate test panels, so the 1,250 lbf trial does not precede the 900 lbf trial on the same specimen. Tate's published results therefore describe two wheel-and-traffic conditions. Keep both with a movement plan that includes equipment delivery and recurring service traffic.

Tate floor assemblyWheel diameter and widthWheel loadPasses
ConCore 1500 PosiLock3 in by 1-13/16 in1,250 lbf10
ConCore 1500 PosiLock6 in by 2 in900 lbf10,000
ConCore 3000 bare bolted stringer10 in by 4 in2,400 lbf10,000

Calculate reactions before judging the move

A 2,700 lb loaded cart averages 675 lbf per wheel when four contacts share its weight equally. Equal sharing across only three contacts raises that average to 900 lbf. Neither average establishes the maximum reaction: an off-center load or uneven transition can put more on one wheel. Compare the highest expected caster reaction, not the arithmetic average, with the applicable test load.

Obtain the equipment mass in its transported condition, caster layout, wheel dimensions and expected reactions. Packing, batteries, fluids and handling equipment belong in that transported condition when present. A rack weight divided by its footprint produces a distributed pressure and does not answer the per-wheel comparison.

Keep deformation criteria and system identity attached

Tate specifies a maximum 0.040 in surface deformation, accounting for local and overall deformation, in both cited rolling-load specifications. That converts to 1.016 mm. The result belongs to the tested panel and supporting understructure; a replacement support arrangement needs its own assembly evidence.

Preserve the panel finish, understructure, pedestal configuration and any cut-panel details in the route approval. Inspect the actual path for supported transitions and complete assembly before moving equipment. Use the raised-floor acceptance packet to retain that identity with the published test evidence and movement restrictions.

Distinctions

Rack rolling rating
The cabinet manufacturer rates its own frame and casters. That rating does not establish the capacity of the floor below them.
Ultimate load
Ultimate load describes an overload failure test. It is not an allowable rolling-traffic value.

Frequently asked questions

Does a higher concentrated rating guarantee a better rolling route?

No. Compare the wheel, load, pass count and complete assembly. The two Tate specifications show why the rolling-test wheel itself must remain visible in the comparison.

Sources checked

Also defined as

  • The dynamic load of a wheeled rack moved across the floor, often more severe than the static load that follows
  • Dynamic load from a wheel rolled across the panel, reported at 10 passes and 10,000 passes

Where this shows up