RTI
RTI, the Return Temperature Index, is calculated in DOE's air-management method as 100 x airflow-weighted cooling-unit temperature drop / airflow-weighted equipment temperature rise. A cooling drop of 11.2 C and equipment rise of 14 C give 80% RTI: under the room heat-balance model, equipment takes 80% of the cooling airflow. Use measurements from one operating boundary and interval, and retain the inlet map because equal room totals can conceal local mixing.
Return Temperature Index; above 100 percent is recirculation, below 100 percent is bypass
Build the numerator with airflow weights
DOE's Air-Management Tool Engineering Reference, version 1.03 (2009), weights each air handler's temperature drop by its share of total airflow. It applies the same principle to the equipment temperature rise. A simple average gives unequal units equal influence and changes the reported index.
Take two operating cooling units: one moves 6,000 cfm with an 8 C drop, and the other moves 4,000 cfm with a 16 C drop. Their weighted drop is (6,000 x 8 + 4,000 x 16) / 10,000 = 11.2 C. With a measured, airflow-weighted equipment rise of 14 C, RTI is 100 x 11.2 / 14 = 80%.
A plain average of the two unit drops gives 12 C and an RTI of 85.7%. The difference comes entirely from weighting. Preserve each unit's airflow and temperatures so the result can be recalculated after a fan change, rather than retaining only the final percentage.
Translate the index into an airflow balance
DOE's engineering reference also expresses RTI as 100 times total equipment airflow divided by total air-handler airflow under its room heat-balance model, which holds air density and specific heat approximately constant. In the 80% case, 10,000 cfm through the cooling units corresponds to 8,000 cfm through the equipment. The 2,000 cfm difference is net excess supply in that model.
That result directs the survey toward bypass paths, but it does not measure any one opening. Likewise, RTI of 120% means equipment airflow is 1.2 times cooling airflow; it does not mean 20% of every rack's inlet air is recirculated. The denominator of a local recirculation fraction is equipment-intake flow.
Keep liquid-cooling duty outside the air balance
DOE's tool sets equipment power equal to the heat removed by the air handlers. A hybrid hall needs the air-cooled portion of the IT load on that boundary. With 400 kW of IT heat, 300 kW removed by liquid and 100 kW left to air, substituting all 400 kW into an air-side airflow calculation overstates the required equipment airflow by a factor of four at the same temperature rise.
Why 100% can hide simultaneous mixing
Oak Ridge National Laboratory's DOE metering protocol (2010) defines RTI as a measure of net bypass or net recirculation. Equal totals can conceal both paths: 10,000 cfm supplied and 10,000 cfm drawn by equipment remain balanced when 2,000 cfm of supply bypasses the racks and 2,000 cfm of exhaust returns to their intakes.
The airflow totals still produce RTI of 100%, while the affected intakes receive warm air. Berkeley Lab's Self-benchmarking Guide pairs changes in air management with Rack Cooling Index checks for equipment thermal conditions. Retain the inlet map and RCI alongside RTI when documenting work from the airflow-management guide.
Distinctions
- Design delta-T
- The equipment rise in RTI is the operating rise used for the measured condition. Substituting a design temperature difference changes the calculation into a comparison with a design target.
- Related technical instruction
- RTI in an apprenticeship record refers to classroom instruction. It has no connection to the thermal index.
Frequently asked questions
Can I combine Celsius and Fahrenheit temperature differences?
Convert them to the same unit first. A ratio of two Celsius differences equals the ratio of the corresponding Fahrenheit differences; mixing the scales introduces a factor-of-1.8 error.
Should RTI be calculated during a chiller restart?
Use a stable operating interval for the airflow-balance interpretation. During a restart, stored heat and changing airflow disrupt the steady balance; the inlet time series remains the direct measure of equipment exposure.
Sources checked
- DOE, LBNL and ANCIS: Air-Management Tool Engineering Reference, version 1.03 (2009), pages 8 to 11 and 17 to 18
- Oak Ridge National Laboratory for DOE: High Performance Computing Data Center Metering Protocol (2010), page 23
- Lawrence Berkeley National Laboratory: Self-benchmarking Guide for Data Center Infrastructure (June 28, 2010), metrics B1 to B3
Also defined as
- Return Temperature Index, a measure of bypass and recirculation in the room airflow