Field glossary · component
Containment
In data halls, containment identifies which air stream is enclosed: cold-aisle systems put the server intake zone inside the barrier, while hot-aisle systems collect exhaust for the cooling-unit returns. That choice determines conditions outside the enclosure. Trace the complete air path and measure inlet temperatures, then compare cooling power at matched IT load; completing the enclosure alone does not demonstrate an energy reduction.
Doors and a roof that seal a cold or hot aisle so the two air streams cannot mix
Follow supply air and exhaust across the barrier
Upsite's Containment Best Practices presentation distinguishes the two arrangements by the environment left outside the barrier. Cold-aisle containment leaves the surrounding room on the exhaust side; hot-aisle containment keeps that room on the supply side. Include network cabinets and other equipment outside the main rows when choosing the arrangement.
| Arrangement | Enclosed path | What the survey must trace |
|---|---|---|
| Cold-aisle containment | Cooling supply into rack intake faces | Supply delivery into the enclosure and exhaust movement through the surrounding room |
| Hot-aisle containment | Rack exhaust toward cooling returns | Return path from the enclosure and supply conditions around the remaining equipment |
Why the doors can work while the energy meter stays flat
Lawrence Berkeley National Laboratory's 2016 Air Management in Small Data Centers report distinguishes enabling energy savings through air separation from realizing them by increasing supply temperature or reducing supply airflow. Closing the mixing paths creates an opportunity; operating the cooling plant differently captures it.
A before-and-after record should therefore pair inlet temperatures with cooling-unit airflow or fan speed and electrical input. Also record IT load. A lower cooling reading during a quieter computing period does not isolate the containment improvement. After correcting bypass and recirculation, compare fan input at matched IT load to quantify the operating improvement.
How a fan calculation changes the savings estimate
Upsite's Containment Best Practices presentation uses fan affinity laws to relate speed, flow, pressure and power. For the same fan at comparable efficiency and corresponding operating points, 80% speed gives flow, pressure and power ratios of 0.80, 0.64 and 0.512. These are fan ratios; whole-system energy also includes runtime and the other cooling equipment.
LBNL's 2016 modeling instead uses a fan exponent of 2.8 to represent non-ideal operation. Using that model, reducing airflow to 80% gives 0.80 raised to 2.8, or about 0.535 of the original fan power. A 4 kW fan input becomes a calculated 2.14 kW. Meter the actual result with the operating point; the calculation explains the expected scale of the opportunity.
A closed aisle still needs an operating return path
Upsite identifies a contained return-air path from the hot aisle back to the cooling equipment as a requirement of hot-aisle containment. An enclosure that ends below an open ceiling can leave that transport path unfinished even when every aisle door latches.
Trace where air goes after leaving the enclosure and when a cooling unit changes state. Include equipment outside the cabinet rows in the inlet-temperature survey. A successful improvement keeps those loads within their operating conditions while fan demand falls; it does not simply transfer a hot spot from the main row to an unmeasured corner.
Distinctions
- Dust or liquid containment
- The same word describes remediation barriers and spill-retention structures elsewhere in Anvilfield. Here the contained medium is the data hall's cooling air, and the result is judged through airflow and operating measurements.
Sources checked
Also defined as
- HVAC: A sealed work area, usually poly sheeting, that keeps spores from spreading to clean space