ANVILFIELD Try FieldOS

Field glossary · property

Ride-through

Ride-through is the interval a load continues operating while its normal power or cooling supply is interrupted or recovering. State the supported load, disturbance and acceptable operating limits with the duration. Electrical transfer time, battery runtime and stored-cooling duration are different measurements. For chilled water, usable thermal energy divided by the heat load gives an initial duration; the field test must also demonstrate circulation and acceptable temperatures until cooling capacity returns.

The window between a power or cooling loss and full recovery, during which the critical load and room temperature must hold

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Calculate the cooling minutes available from stored water

DOE's Thermal Energy Storage fact sheet uses a water heat capacity of 1 Btu per pound per degree F. A usable cold-water mass of 100,000 lb working through a 10 F temperature difference stores 1,000,000 Btu. Against a 10,000,000 Btu/h heat load, that energy supports 0.1 hour, or six minutes of cooling.

Use the water mass that can be discharged while meeting the required outlet temperature. DOE describes stratified storage with cold water leaving the bottom while warmer return water enters above it. Mixing and the moving temperature boundary affect how much cold water remains deliverable; the tank's gross volume alone does not establish that quantity. Record tank outlet temperature and flow during discharge.

Read voltage depth and duration together

The Information Technology Industry Council's ITI curve, revised in 2000, describes typical tolerance for 120 V, 60 Hz equipment: a complete interruption up to 20 milliseconds, a sag to 70 percent for up to 0.5 seconds, or a sag to 80 percent for up to 10 seconds. These are separate disturbance cases. The document presents an equipment-tolerance envelope, not a facility design specification.

At 120 V nominal, those sag levels are 84 V and 96 V. Retained voltage and event duration belong together on the event record. Use the selected equipment's specified behavior for the project acceptance criterion.

Distinguish a transfer interruption from stored-energy duration

Eaton's SU2200RTXL2UN data specifies zero transfer time in online double-conversion mode. That mode-specific statement concerns continuity when the supply changes. It does not specify how long the batteries will support a particular load, or the behavior of a maintenance bypass.

A 2 MW load carried for 45 seconds requires 2,000 x 45 / 3,600 = 25 kWh delivered at the load boundary. Select a discharge capability that supplies both that energy and the required instantaneous power at the specified battery condition. The energy arithmetic establishes the load requirement; the manufacturer discharge data establishes which battery configuration delivers it.

Measure recovery at the load rather than at the start signal

Time the interval from the disturbance to a stable acceptable supply at the protected load. A generator start indication, a breaker-close command and an acceptable voltage waveform occur at different instants. Capture them on a common time base so the restoration point is evident.

The ITI application note assumes separate transients begin from nominal conditions and allows recovery to equilibrium between them. A repeated disturbance sequence should therefore retain every event and its recovery state, rather than treating each event as an isolated curve point.

If the six-minute cooling store above serves a plant that restores the required heat removal after five minutes, the calculated duration margin is one minute. Confirm that margin from outlet and rack-inlet temperature trends during the integrated systems test. The recovery endpoint is sufficient delivered cooling at the load, not merely a chiller start command.

Distinctions

Autonomy
Autonomy is the duration supplied from stored energy at the specified load and condition. Transfer time is the supply interruption during a change of source.
Grid ride-through
For interconnected generation, the term also describes remaining connected through specified grid disturbances. That behavior is separate from keeping an isolated IT load powered.

Frequently asked questions

Does an online UPS prove the cooling will ride through?

It establishes only the supplied electrical function and supported loads. Cooling continuity depends on which pumps, fans and controls remain operating and how the heat-removal system recovers.

Sources checked

Also defined as

  • The minutes of cooling the tank carries while the chillers restart or generators load

Where this shows up

Next step: Locate campus tank owners

Back to the full field glossary