Sensible cooling

Size sensible cooling by the dry-bulb temperature drop and mass of air passing the coil. Colmac's air-side equation is 1.085 x SCFM x temperature drop in F, giving Btu/h; measured ACFM needs a density correction first. A dry coil moving 1,600 SCFM through a 20 F drop removes 34,720 Btu/h. Match that gross coil duty to any fan heat added downstream before comparing it with the unit's delivered sensible capacity.

Cooling that lowers air temperature without removing moisture, the mode an in-row unit runs when the coil stays above dew point

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Calculate sensible capacity from SCFM and temperature

Colmac Coil's sizing bulletin uses Q_sensible = 1.085 x SCFM x temperature drop in F to obtain Btu/h. The airflow in that equation is standard cubic feet per minute. Colmac converts actual flow by SCFM = ACFM x actual air density / 0.075 lb/ft3, making the density assumption explicit.

A coil moving 2,000 actual cfm through air with density 0.060 lb/ft3 moves the equivalent of 1,600 standard cfm. At a 20 F air-temperature drop, the calculated sensible duty is 1.085 x 1,600 x 20 = 34,720 Btu/h. Entering 2,000 directly gives 43,400 Btu/h, overstating capacity by 25%.

The correction matters when comparing a field traverse with a selection sheet at different elevation or air conditions. Record whether each airflow is actual or standard, and retain the density used. The psychrometric-chart guide supplies the air-state context for that comparison.

Subtract fan heat at the correct boundary

Trane's TRACE 3D Plus load-calculation documentation includes supply-fan heat in the cooling-coil duty and lowers the required coil-leaving temperature to offset it. A temperature drop measured across the coil therefore describes a different capacity boundary from the cooling delivered after a downstream fan.

With 35 kW of gross sensible coil duty and 3 kW of fan heat added to the supply airstream, the delivered sensible cooling is 32 kW. Compare gross with gross, or net with net. A performance sheet that already subtracts fan heat needs no second subtraction.

Place the temperature measurements around the component being evaluated. An entering-coil probe and a probe downstream of the fan include the fan's temperature rise; probes directly before and after the coil do not. This boundary should be identified in the in-row capacity record.

Use the water side to cross-check a dry coil

Colmac's water-side heat equation is Q = 500 x GPM x water-temperature rise in F, giving Btu/h for water. A 7 gpm stream warming by 10 F carries about 35,000 Btu/h, close to the 34,720 Btu/h air-side result above. The two results differ by 280 Btu/h, about 0.8% of the air-side value; retain both results rather than rounding them to the same capacity.

For a dry coil, the air and water measurements describe the same sensible heat transfer. Once moisture condenses, the water side carries sensible plus latent duty, so comparing it only with the air dry-bulb calculation leaves part of the load uncounted. Use the rear-door heat-exchanger guide and CDU commissioning guide for the associated flow and control checks.

Colmac's total air-side cooling equation uses 4.5 x SCFM x enthalpy drop in Btu/lb of dry air to obtain Btu/h. At 1,600 SCFM and a 6 Btu/lb enthalpy drop, total duty is 43,200 Btu/h. Subtracting the 34,720 Btu/h sensible duty leaves 8,480 Btu/h latent duty and a sensible heat ratio of about 0.80.

Distinctions

Sensible heat ratio
SHR divides sensible capacity by total capacity at a stated condition. It describes the split of the duty, not the unit's efficiency or the amount of cooling available after fan heat.
Latent cooling
In the 43,200 Btu/h total-duty case, the 8,480 Btu/h latent portion is 19.6% of the total. That moisture-removal duty sits outside the 34,720 Btu/h dry-bulb calculation; the two duties must be added when selecting a coil.

Frequently asked questions

Does the 500 water-side factor apply to a glycol loop?

Use the fluid's density and specific heat at its concentration and operating temperature. The factor for water does not account for the changed properties of a glycol mixture.

Why is measured sensible capacity below the catalog value?

First put both values on the same entering-air, airflow-density and fan-heat basis. Those differences change the comparison before coil fouling or insufficient water flow is considered.

Sources checked

Also defined as

  • Cooling that removes heat without condensing water, the mode the loop runs in when the coolant stays above dew point
  • Lowering air temperature without removing moisture; what a rear door does when it runs above dew point

Where this shows up