Field glossary · equipment
STS
A static transfer switch (STS) selects an AC supply electronically and provides no battery runtime. Its interruption rating belongs to a specified operating case: Vertiv's STS2 Revision 17 manual gives less than 1 ms for synchronized manual transfers on units without Optimized Transfer. Excessive downstream current normally inhibits transfer on that device. A synchronized manual test therefore does not establish emergency-transfer performance or prove how the switch responds to a load fault.
Static transfer switch, which moves load between two sources fast enough to avoid an interruption
Which transfer time does the STS specification describe?
IEC 62310-3:2008, the current published performance and test part of the static-transfer-system series, covers controlled transfers with or without interruption. The equipment name therefore does not define one interruption limit. A purchase specification needs the triggering condition and the permitted load-voltage interruption as well as the switch rating.
Vertiv's Liebert STS2 100-1000A manual, SL-20620 Revision 17, specifies less than 1 ms of interruption for a manually initiated transfer on units without the Optimized Transfer option, when both sources are available and synchronized within the configured phase window. Its emergency-transfer description permits a transfer to an acceptable alternate voltage regardless of phase difference. These are different operating cases. A successful synchronized manual transfer does not establish the waveform during an emergency source loss.
Include manual transfer and source loss as separate cases in the UPS and STS commissioning hold-point record. Label each capture with its transfer algorithm, source phase relationship and trigger so results from different cases remain distinguishable.
Why an STS can block a transfer during low voltage
A falling bus voltage can originate upstream, or it can accompany a downstream fault drawing excessive current. Moving the latter event to another supply risks disturbing that supply as well. Inspect the current record alongside the voltage event before calling a blocked transfer a switch failure.
Vertiv's STS2 manual identifies an I-Peak condition that inhibits ordinary manual and automatic transfers when load current exceeds the configured inrush-or-fault threshold. It separately describes an open-SCR exception. The inhibit is protective logic, not evidence that the alternate source was unavailable.
The STS2 also has a repeat-transfer safeguard: Vertiv disables automatic retransfer after five preferred-to-alternate transfers within five minutes. Repeatedly unstable preferred power can therefore leave the load on the alternate even after the preferred-source indication recovers. Preserve the alarm sequence and settings before interpreting that state as a failed return command.
An event history is not a transfer waveform
Vertiv's STS2 history log contains 64 status frames spaced 4 ms apart. Those frames explain source selection, breaker state and surrounding alarms, but their spacing cannot establish a sub-millisecond interruption. Use the time-resolved load-voltage capture for the interruption measurement and the history log for the switch's reported state.
Retain both input-source voltage traces, the output voltage and load current on a common time base. Mark when the source disturbance began and when the output recovered; do not substitute a controller timestamp for either waveform boundary. If a log says 'transfer complete' while the load restarted, the load trace and equipment ride-through limit decide whether the transfer met the acceptance requirement.
Distinctions
- UPS static bypass
- A UPS bypass alarm identifies an event in that UPS's inverter and bypass paths. Trace the reporting device and its output circuit before assigning that event to a downstream standalone STS; the alarm does not establish which STS input was selected.
- Transfer inhibit versus source unavailable
- Vertiv's I-Peak inhibit identifies current-based blocking, while source availability depends on the input conditions and configured limits. A healthy alternate-source indication can coexist with an inhibited transfer. Preserve both states in the event record.
Frequently asked questions
Will an STS keep equipment running if both sources fail?
It has no stored-energy reserve to supply the load. Continued operation depends on upstream storage or another available power path. Two connected inputs alone do not provide autonomy.
Sources checked
Also defined as
- Concrete: Standard threshold shift, a 10 dB average worsening at 2000, 3000, and 4000 Hz from baseline
- Static transfer switch, a solid-state switch that moves the load between two sources sub-cycle