Thickened edge

A thickened edge is the part of a concrete slab where the section gains depth toward a boundary: a 12-inch slab with a 15-inch edge contains 3 inches of additional depth at that edge. Width and underside shape determine the added quantity. Identify whether the detail serves a pavement joint or a building's integral footing before applying dimensions, because those sections carry different loads.

The slab run deeper along an edge or load line to carry the higher bending a wheel puts on an edge

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Measure the edge profile before placing concrete

Mark field thickness, total edge depth, transition width, and any flat-bottom width on the section. With finished surface elevation established, measure down to the prepared bearing surface at the edge and at the end of the taper. Record both depths and the horizontal distance between them; a correct edge depth with a shortened taper still produces the wrong section.

Separate a rectangular downstand, a triangular haunch, and a flat-bottom strip followed by a taper in the takeoff. Each has a different added cross-sectional area. Compare the detail reference in the driveway guide with the load and support assumptions covered by the slab design guide.

Airfield edge dimensions belong to the named joint detail

FAA AC 150/5320-6G, issued June 7, 2021 and listed as active, describes Type A thickened edges at airfield pavement isolation joints. Figure 3-4 sets total edge depth at 1.25 times field thickness, rounded to the nearest inch, subject to a minimum increase of 2 inches. These are dimensions for that airport pavement joint, rather than a sizing rule for residential driveways or building footings.

FAA Figure 3-4 carries the Type A taper to the nearest joint, at least 10 feet away. A takeoff must therefore use the actual joint distance: a 15-foot distance calls for a 15-foot transition, not a default 10-foot strip.

The Port Authority of New York and New Jersey's 2018 Civil Design Guidelines give a different airfield haunch rule: half the slab length, with a 10-foot minimum. The common minimum does not make the FAA and Port Authority details interchangeable. Name the selected detail and panel geometry on the quantity sheet.

Take off the added concrete below the field slab

Calculate ordinary slab volume over the full plan area, then add the cross-section below field thickness. For a linear taper, added area equals one-half × transition width × extra edge depth. A flat-bottom strip contributes its full width × extra depth in addition to the tapered portion. Multiply the combined area by edge length using consistent units.

At intersecting edges, account for the shared corner volume once. A perimeter-length shortcut counts overlapping strips twice unless its corner treatment matches the drawing. Footing sections with vertical sides or a flat bottom need their own cross-sectional shape; the foundation guide explains their bearing function.

Distinctions

Integral footing
A thickened edge becomes an integral footing when it is designed to transfer building loads to its bearing area. A pavement edge thickening is identified by its pavement section and joint detail.
Raised curb
A curb adds height above the pavement surface. Edge thickening adds depth to the slab section, so a visible curb height does not establish the concrete depth below it.

Field example

Using the Port Authority's 2018 haunch rule, two 20-foot panels provide a 40-foot edge with a 10-foot taper. With a 12-inch field slab and 15-inch edge depth, the added volume along that one edge is 0.5 × 10 × (3/12) × 40 = 50 cubic feet, or 1.85 cubic yards. Treating the taper as a rectangular strip would add 3.70 cubic yards instead. Both quantities are additions to the ordinary slab volume.

Frequently asked questions

Is edge depth the same as added thickness?

Edge depth is the total concrete depth at the perimeter. Added thickness is the difference between that depth and the ordinary slab thickness. Keep both labels on the section to prevent double-counting concrete.

Can I determine thickened-edge volume from linear feet alone?

Linear feet establish length. Volume also requires the added cross-section, including its depth, width, and shape, plus the treatment at corners and terminations.

Sources checked

Also defined as

  • Paving: A deepened slab perimeter, commonly 6 in or more, that beams the edge under wheel load

Where this shows up