American Society of Mechanical Engineers
ASME B31: select the piping code and define package test boundaries
A pressure-piping purchase order needs a complete ASME B31 code and edition assigned to each circuit. B31.1-2026 includes power and district heating or cooling applications; B31.3-2024 includes process piping inside packaged assemblies; B31.9-2025 reaches building-service piping within property limits. Neither a factory skid frame nor an exterior wall establishes the code boundary. The designer's selection must connect the service and design conditions to the required fabrication, examination, and testing records.
Applies to
Owners and designers establish the applicable piping basis; fabricators, installers, examination personnel, and inspectors produce the evidence for that basis. Distinct circuits in one facility can use different codes. Mark their limits at identifiable equipment connections or drawing locations so procurement and field work use the same division.
The process piping guide explains fabrication and fluid-service rigor. The additions here address packaged-system interfaces, the breadth of power-piping service, and the quality records that a code designation must lead to.
Key topics
A packaged assembly does not end the piping review
ASME B31.3-2024 includes piping interconnecting pieces or stages within a packaged equipment assembly. A factory skid therefore needs an identified piping basis rather than an unexplained boundary at its shipping frame. Obtain the vendor's circuit diagram, code declaration, and included examination and test records. Show how field connections join that package's documented limits, especially where facility water and technology coolant remain separate circuits.
Power piping also includes district heating and cooling
ASME's B31.1 scope includes central and district heating and cooling systems as well as power-generation and specified boiler-external piping. Thus chilled water alone does not select B31.9, and steam alone does not establish the complete B31.1 boundary. The plant and distribution application belong in the code-selection record. Reconcile the campus designer's code basis with the building connection before dividing the work into purchasing packages.
Boiler-external scope has stated pressure and temperature thresholds
ASME's B31.1-2026 scope includes boiler-external piping for steam or vapor boilers operating above 15 psig. Its high-temperature water-boiler scope uses pressure above 160 psig or temperature above 250 F. Either water condition reaches that stated threshold: a boiler generating 240 F water at 180 psig exceeds the pressure threshold even though its temperature is below 250 F. These figures describe that boiler-external application; they are not a rule assigning every low-pressure campus line to B31.9.
Covered power piping has quality-program and record appendixes
ASME's B31.1 publication highlights identify Mandatory Appendix Q for quality-management programs and Mandatory Appendix R for documentation, records, and reports for covered metallic nonboiler-external piping systems. Determine whether the project's system falls in that covered scope before setting the record schedule. A pressure-test sheet alone does not describe the quality program or the complete construction record identified by those appendixes. ASME's revision highlights also identify paragraph 137.2.1's requirement for uncoated joints during pressure testing unless the owner allows otherwise. Set the coating release point in the inspection plan before shop finishing conceals the joints.
Building-service scope can extend outside the building
ASME B31.9-2025 includes building-services piping within buildings or their property limits. Crossing the exterior wall therefore does not by itself change a service circuit into a different B31 application. Identify the service, operating design basis, and agreed boundary on the site drawing. Use the complete code designation when coordinating outdoor heat-rejection connections with the interior building-services package.
How it is used in the field
On a CDU package, assign separate circuit identifiers to the facility-water connection and technology-coolant connection. Request the vendor's code and test declarations for each, including which components are inside the tested assembly. A single factory test certificate should identify its actual circuit and exclusions before it is attached to both systems.
At a campus interface, place the code boundary on the piping and instrumentation diagram and the construction drawing. Identify the exact flange or connection and who supplies the closure joint and its records. An unresolved interface can leave the final joint outside both contractors' examination and test packages.
Build the test-package register around circuit ID, governing edition, design conditions, test medium, specified test pressure and duration, isolated components, examination records, and witness responsibility. Link each factory or field report to that register. A hydrostatic multiplier copied from another circuit does not establish the pressure for a package with a different code basis or component limit.
At turnover, reconcile field and factory boundaries against the as-built circuit. Include the closure work and any excluded items resolved on site. A test performed on a skid before shipment does not establish the condition of field joints added after delivery.
Edition history
The three code publications listed here have different current years: B31.1-2026, B31.3-2024, and B31.9-2025. ASME's B31.9 publisher page identifies updated stainless-steel allowable stresses and normative references among its changes. An older adopted or contracted edition remains an identifiable project basis rather than becoming a generic B31 requirement.
Adoption
Jurisdictional rules and project specifications select the controlling code and edition. Record that selection by circuit, including any equipment-package declaration, rather than assuming that every pipe on a data center or industrial site follows one code. Product standards for pipe, fittings, or joining components provide separate evidence from the governing system construction code.
Tank-farm piping contractors track facility expansions through PorchRocket Asset Search, whose monitoring reports new or altered visible tanks with dated views.
Frequently asked questions
Does a factory skid's piping fall outside ASME B31.3?
B31.3's scope includes piping interconnecting pieces or stages within a packaged assembly. Identify the package's actual application and declared code basis, then connect its records to the field-piping boundary.
Does an outdoor chilled-water pipe automatically use B31.1?
Location alone does not select the code. B31.9 includes building-service piping within property limits, while B31.1 includes central and district cooling applications. The documented service and system boundary determine the selection.