ASHRAE Technical Committee 9.9
ASHRAE TC 9.9: humidity conditions, temperature excursions, and altitude
A project citing ASHRAE's TC 9.9 committee needs the actual publication, revision, and equipment class to identify its environmental criteria. Its revised Thermal Guidelines reference card makes the recommended upper moisture boundary conditional on corrosion measurements and a 15 C dew-point ceiling. Operators also need excursion duration and altitude, not just an instantaneous temperature. Cite the actual publication and revision: the Datacom Encyclopedia introduced in 2024 is an evolving reference platform, while a retained printed chart has a fixed edition.
Applies to
IT manufacturers declare equipment capabilities; facility designers coordinate environmental conditions; operators compare measurements with the selected equipment limits. A committee name in a submittal does not identify a particular chart or requirement. Cite the document supporting each condition and preserve its associated notes with the engineering record.
The thermal-envelope guide organizes operating measurements. Use the publication distinctions below when reconciling its equipment basis with a vendor document or an older project chart.
Key topics
The recommended RH ceiling still has a dew-point limit
ASHRAE's revised fifth-edition reference card couples the recommended upper moisture limit to a 15 C dew-point ceiling and a corrosion-dependent RH ceiling. The 70 percent RH option is tied to silver and copper corrosion rates below 200 and 300 angstroms per month, respectively; the note calls for 50 percent RH or lower when corrosion exceeds those thresholds. Both moisture constraints apply. These values describe the recommended envelope, not every equipment class's allowable humidity range. A passing coupon result does not authorize exceeding the dew-point ceiling.
A short excursion can fail even when the hourly trend looks steady
For non-tape IT equipment, ASHRAE's revised reference card limits the inlet temperature span to 5 C within any 15-minute window and 20 C within an hour. Calculate each span from the highest and lowest readings in the window, not from its first and last values. A trend moving from 20 C to 26 C and back to 20 C within 15 minutes has a 6 C excursion. Identical endpoint readings do not make that excursion disappear.
Powered-off limits describe unpacked installed equipment
The ASHRAE reference card defines its product-power-off condition as equipment removed from its original shipping container and installed but not operating, including repair or upgrade periods. That condition differs from packaged transport and storage. Label a received shipment, an installed de-energized rack, and an operating rack as different environmental states in the receiving record. An operating-range chart should not silently become a shipping acceptance specification.
The 2022 corrections also affect Classes B and C
ASHRAE's May 31, 2022 errata adds Classes B and C to the fifth-edition reference material and extends the stated altitude derating note to those classes. In that corrected guidance, their maximum allowable dry-bulb temperature decreases by 1 C per 300 m above 900 m. This matters for telecommunications and factory equipment spaces beyond the main data hall. Identify the equipment's declared class before carrying a data-hall chart into an edge installation.
A corrected printed chart and a live encyclopedia need dated citations
ASHRAE's public Datacom page identifies a frequently updated encyclopedia and historical PDFs of every edition of the 14-book Datacom Series. Retrieve the topic currently being specified, then retain the document title and revision or access date in the submittal. The May 2022 errata explicitly says its corrections were incorporated into the revised and expanded fifth edition. A 2021 cover date alone therefore does not establish whether a chart contains those corrections.
How it is used in the field
A rack inlet at 24 C with a measured dew point of 17 C is outside the recommended moisture envelope even if RH is below 70 percent and coupons report 180 angstroms per month for silver and 280 for copper. Record all three quantities with the coupon evidence. A copper result of 340 instead invokes the reference card's lower RH guidance. Neither coupon outcome converts recommended limits into an equipment warranty.
At 1500 m, the corrected B/C altitude rule removes 2 C from the sea-level allowable maximum: the 600 m elevation above 900 m contains two 300 m increments. Class B's 35 C ceiling becomes 33 C, while Class C's 40 C ceiling becomes 38 C. Record the class and adjusted allowable ceiling separately from the site's chosen operating setpoint.
When two submissions disagree, compare publication title, edition, corrections, environmental state, and measuring boundary before comparing their numbers. Preserve the resolved source in the acceptance package. A screenshot containing only the chart body leaves later operators unable to reconstruct those conditions.
Edition history
Thermal Guidelines for Data Processing Environments appeared in its fifth edition in 2021. ASHRAE's May 2022 correction sheet states that its changes were incorporated into the revised and expanded edition published in 2022. The public supplemental reference card carries 2021 and 2024 copyright dates. ASHRAE introduced the Datacom Encyclopedia in 2024 as the successor platform for the book series.
Adoption
A specification must identify which TC 9.9 publication and environmental class it incorporates. Preserve recommended targets, allowable limits, manufacturer restrictions, and acceptance thresholds as separate fields in the operating basis. The committee name alone supplies neither a contract edition nor an automatic change to installed-equipment limits.
Frequently asked questions
Does passing the corrosion test mean 70 percent RH is always acceptable?
The recommended envelope still has its 15 C dew-point ceiling and noncondensation condition. Record temperature, RH, and dew point together; then apply the coupon-dependent RH ceiling. The equipment-class allowable envelope is a different comparison and needs the actual class declaration.
Where is the current TC 9.9 reference material?
ASHRAE's Data Center Resources page links the Datacom Encyclopedia and related publications. Use the named topic and its revision in the project record; historical book editions remain identifiable references for an existing design basis.