ASHRAE Guideline 36: the 2024 sequences and 2026 controls changes

Guideline 36-2024 supplies HVAC sequences of operation and functional tests for confirming their implementation. Its published 2026 addenda change fan-array staging, fan-coil fault detection, dual-duct ventilation logic, alarm testing, and laboratory controls. Engineers, programmers, and commissioning providers need an identified base edition and addendum set. A controller library labeled Guideline 36 does not establish which of those changes its installed application contains.

Current edition: ASHRAE Guideline 36-2024 with published 2026 Addenda a, e, f, h, and k
Updated

Official publisher page

Applies to

A controls estimate needs the equipment configuration, application parameters, base edition, and accepted addenda beside each controller program. Designers assign those inputs; programmers implement them; commissioning providers retain the trend evidence for each selected sequence. Record project modifications in the submitted logic and controller revision history so a later software replacement preserves the intended operation.

The VAV commissioning guide explains terminal and reset behavior. The edition-specific additions below concern logic changes that an older program can miss even when its normal occupied operation looks correct.

Key topics

Fan-array staging now uses a shorter default delay

ASHRAE's February 2026 Addendum a to Guideline 36-2024 changes the default fan-array staging delay from 15 minutes to 5 minutes for supply and return arrays. Addendum a also adds a supply-fan stage-up condition when duct pressure stays more than 10 percent below its setpoint for 5 minutes. Test the additional capacity request as well as the airflow-based staging logic; a program containing only the original airflow trigger misses that response. The supply-airflow staging input is the sum of enabled VAV airflow setpoints divided by design AHU airflow, not the sum of measured terminal airflows. Trend the commanded setpoints as well as the pressure response.

Alarm Test Mode changes suppression during commissioning

ASHRAE's September 2026 Addendum h introduces Alarm Test Mode, which disables post-exit, hierarchical, and time-based alarm suppression for the selected device or system. This provides a deliberate test state instead of repeatedly waiting for normal suppression periods. Include enabling and restoring that state in the test record. Capture the alarm input, controller event, and operator display so an accelerated test still demonstrates the complete notification path. The addendum forces the associated SystemOK points true during this mode, so an alarm demonstrated there does not prove normal hierarchical suppression.

Dual-duct DCV must account for both air streams

ASHRAE's September 2026 Addendum f corrects demand-controlled ventilation logic for dual-duct boxes using cold-deck-minimum control because hot- and cold-deck airflows add at the diffuser. Verify the installed terminal type and the combined airflow in that mode. A test limited to the cold-deck reading can miss excess delivered supply air while the controller appears to satisfy its individual minimum.

Fan-coil fault rules need the actual coil configuration

Addendum e, published in September 2026, corrects fan-coil fault-condition equations and clarifies which tests apply to the installed fan-coil configuration. Retain the relevant inputs and omit tests for components that are absent. Match the FDD configuration to the equipment schedule before treating repeated alarms as mechanical faults. A controller running an inapplicable diagnostic can produce a persistent finding on equipment that is operating as designed.

Laboratory sequences are a separate 2026 extension

ASHRAE's July 2026 Addendum k adds sequences for four-pipe and two-pipe VAV laboratory systems. Its public explanation describes both air valves with onboard airflow controllers and arrangements controlled by a laboratory-room controller. Identify that architecture before assigning points and test responsibilities. The location of the airflow control loop changes which controller evidence proves the command and which proves the measured response.

How it is used in the field

With a duct-pressure setpoint of 250 Pa, Addendum a's more-than-10-percent deficit condition means pressure below 225 Pa continuously for five minutes. A steady 220 Pa meets that deficit condition; exactly 225 Pa does not. Record the setpoint, pressure, timer, and available next fan stage together. Trend the enabled VAV setpoint total separately to distinguish the pressure trigger from airflow-demand staging.

For Addendum h acceptance, first demonstrate the alarm in Alarm Test Mode, then disable that mode and test the normal suppression behavior separately. Record restoration of SystemOK logic and suppression timers. An accelerated test proves the alarm input and notification path while those suppressions are bypassed.

A software substitution needs the same review as a sequence change. Obtain the vendor's implementation revision and compare its supported addenda with the approved set before scheduling functional tests. This prevents testing a newer written sequence against an older executable application.

Edition history

The 2024 edition supersedes Guideline 36-2021. As of November 5, 2026, ASHRAE's public addenda index lists a, e, f, h, and k for the 2024 edition. Their separate publication dates belong in the implementation record; they are not a newly numbered 2026 base edition.

Adoption

The acceptance record should name each controller application and the specific Guideline 36 revisions incorporated into it. A reference to the 2024 edition alone does not identify the 2026 addenda used here. List each incorporated addendum, adjustable parameter, and project override so the executable controller application and the commissioning test use the same logic.

Controls contractors following school retrofits see early signals in board meetings, budgets, and capital plans through PorchRocket Bid Control.

Frequently asked questions

Which fan delay applies to a Guideline 36 array?

Addendum a to the 2024 edition changes the default staging delay to five minutes. Establish whether the project incorporates that addendum and which adjustable values the approved application uses.

Why can an alarm fail to repeat during a functional test?

Normal suppression logic can prevent immediate retriggering. Addendum h provides an explicit Alarm Test Mode for that testing condition; identify the active mode and restore normal operation when the test is complete.