ASHRAE 90.4: MLC, electrical losses, and the 2025 calculation basis
ASHRAE 90.4-2025 evaluates data center support systems using an annualized mechanical load component (MLC) and a design electrical loss component (ELC). Its mechanical calculation models 25, 50, 75, and 100 percent of IT design load; its UPS calculation includes redundant capacity. Engineers use these boundaries to document energy compliance for new facilities, additions, and equipment changes. A measured facility energy ratio does not supply the required design calculations or identify the applicable climate-zone limits.
Applies to
Mechanical designers assemble the annual cooling, heating, and ventilation model; electrical designers trace the UPS and IT distribution losses. Suppliers provide part-load performance data, reviewers reconcile the installation with those inputs, and owners retain the model when capacity changes. ASHRAE's published 2025 scope excludes telephone exchanges, essential facilities, and the IT equipment itself. Identify any exclusion at the start of the submission rather than treating every server installation as an identical application.
An economizer choice from the data center cooling selection guide becomes a set of weather-dependent operating hours in the compliance model. Keep the selected equipment, control states, and auxiliary loads together so the model represents the system being purchased.
Key topics
How the four MLC load cases combine
ASHRAE's Addendum g to 90.4-2022, incorporated into 90.4-2025, evaluates annual mechanical energy at four fixed IT loads: 25, 50, 75, and 100 percent of design. Add the cooling, heating, and ventilation energy from all four cases; divide that sum by design IT power multiplied by 2.5 and 8760 hours. For 1000 kW of IT design power, the denominator is 21,900,000 kWh. Four modeled mechanical-energy totals adding to 5,256,000 kWh produce an MLC of 0.24. Compare that result with the applicable climate-zone and capacity category, not with a measured PUE target.
Redundant UPS modules change the efficiency point
ASHRAE 90.4-2025 bases UPS efficiency on total available UPS capacity, including redundant capacity. A UPS with four operating 500 kW modules supplying 1200 kW operates at 60 percent of that installed capacity, rather than 80 percent of a three-module capacity. Select the manufacturer's efficiency data at the applicable loading point. Keep UPS output, IT design power, and supporting loads separately identified so the denominator does not change between drawings and calculations.
Generator heating and humidity equipment belong in the model
ASHRAE's Addendum g to 90.4-2022, incorporated into the 2025 edition, assigns standby-power temperature maintenance to the process-heating segment and humidity control and continuous ventilation to the process-ventilation segment. Those loads remain relevant when liquid cooling removes much of the white-space air load. Request heater ratings, controls, schedules, and ventilation assumptions alongside chiller and fan selections. Omitting small continuously operating devices understates annual support energy.
An equipment addition needs an explicit segment boundary
The public explanation of Addendum g describes mechanical segment allowances intended to support limited-scope equipment additions without automatically recalculating the entire facility's mechanical and electrical compliance. Identify the segment affected by a retrofit and the compliance provisions selected for it. A replacement-unit submittal needs to show the old and new calculation boundaries, especially when controls or shared pumps serve both retained and new equipment.
Electrical-loss paths extend beyond the UPS nameplate
ASHRAE's Addendum b to 90.4-2022 calculates design ELC from the UPS and IT distribution segments using the highest-loss parts of each segment. The incoming-service segment is outside that ELC calculation. Trace UPS output through distribution equipment to the IT connection boundary on the one-line diagram. A favorable UPS efficiency cannot compensate for omitting a downstream transformer from the submitted path, and ELC is not an inventory of every electrical loss at the property.
How it is used in the field
During procurement, compare the proposed UPS module arrangement with the arrangement modeled for compliance. An accepted substitution that changes installed capacity also changes the loading point used to obtain efficiency. Attach the applicable curve and identify the normal operating configuration rather than submitting a peak-efficiency headline.
During controls checkout, verify that the modeled operating assumptions have a corresponding installed sequence. Record heater enable conditions, humidity-control coordination, and equipment staging states. A model that assumes a device stops needs an actual control command and feedback showing that state.
At an economizer retrofit, carry the approved mechanical boundary into the revised calculation. The cooling equipment, controls, and associated auxiliaries should describe the same installation in the model, equipment schedule, and turnover documents.
Edition history
ASHRAE lists the 2025 publication as superseding 90.4-2022. Its published explanation of Addendum do to 90.1-2022 identifies 90.4-2022 Addenda a, b, c, and g as incorporated into 90.4-2025. The 2025 purpose statement also adds environmental considerations beyond direct energy consumption; that purpose statement alone does not create a numerical water-use or carbon limit.
Adoption
Standard 90.4 is written for use in energy codes, but its publication date and a jurisdiction's adoption date are separate. ASHRAE's 90.1-2022 Addendum do updates the normative reference to the revised data center provisions. Establish the adopted energy-code path and referenced 90.4 edition on the submission cover before applying a newer calculation method to an existing permit.
A heat-rejection service territory changes as plants expand; PorchRocket Asset Search monitoring reports new, removed, or altered visible cooling towers with dated views.
Frequently asked questions
Does redundancy disappear from the UPS efficiency calculation?
No. The 2025 clarification includes redundant capacity in total available UPS capacity. The resulting loading fraction determines which manufacturer efficiency data represents the installation.
Can I use measured PUE as the ASHRAE 90.4 calculation?
The 90.4 calculation needs the four modeled mechanical load cases and the defined electrical segments. A utility-to-IT meter ratio does not identify those inputs. Preserve the MLC and ELC worksheets alongside any operating energy report so reviewers can distinguish design compliance from measured facility performance.
Sources checked
- ASHRAE: Standard 90.4-2025 scope and publication status
- ASHRAE: 2025 edition changes, including redundant UPS capacity
- ASHRAE: Addendum b to 90.4-2022, UPS and distribution calculation boundaries
- ASHRAE: Addendum g to 90.4-2022, heating, ventilation, and mechanical segments
- ASHRAE: Addendum do to 90.1-2022, reference update and incorporation into 90.4-2025