ASHRAE 62.1: ventilation editions, density and changed occupancies

Ventilation compliance with ASHRAE 62.1 requires a documented calculation method and an installed system that delivers the resulting outdoor-air requirement. The 2025 edition covers mechanical and natural ventilation, air cleaning, controls, commissioning and operation for its covered spaces. New density-adjustment requirements and the 2026 supermarket revision make edition control especially consequential. Identify the occupancy category, operating assumptions and incorporated updates before carrying an older ventilation schedule into a new project.

Current edition: ANSI/ASHRAE Standard 62.1-2025 (2025), with August 27, 2026 errata and Addendum a approved June 30, 2026
Updated

Official publisher page

Applies to

ASHRAE 62.1-2025 excludes spaces within dwelling units occupied by nontransient residents; Standard 62.2 addresses those residential units. That boundary is based on the space and occupancy, not simply the building's height. Common areas and dwelling units within one building can therefore require different ventilation references. ASHRAE 62.1 scope

Designers establish the method and inputs; controls contractors implement the intended modes; TAB providers measure delivery; operators preserve the operating conditions. The published scope does not prescribe rates for hazardous-material laboratories, unlisted patient-care areas, or smoking spaces and spaces lacking the required separation from smoking. Identify their specialized requirements separately in the ventilation schedule.

Key topics

Supermarket area ventilation changed in June 2026

ASHRAE 62.1-2025 Addendum a increases the supermarket area outdoor-air rate from 0.06 to 0.12 cfm per square foot. The publisher attributes the change to evidence of contaminants associated with expanded supermarket activities, including food preparation. Where the addendum governs, update the occupancy calculation instead of carrying forward the earlier retail assumption. ASHRAE supermarket addendum

Density correction belongs in the intake calculation

ASHRAE's August 27, 2026 consolidated erratum retains the corrected outdoor-air-intake equation: divide the uncorrected requirement by system ventilation efficiency, then multiply by the air-density correction factor. The correction first appeared in January 2026. Retain the factor and its project basis in the schedule so design and field measurements use the same volume basis. A standard-density volume and the corrected site volume represent different numerical flow rates for the same mass flow. Current outdoor-air-intake equation erratum

Control sequences now deserve their own ventilation review

ASHRAE identifies demand-control sequences and ventilation emergency controls among the 2025 changes. Review their intended operating modes with the ventilation calculation rather than treating every mode as a fixed damper command. State which requirement applies during occupancy changes and during an emergency-control state, then make the functional test demonstrate that behavior. ASHRAE 62.1-2025 changes

IAQ Procedure designs need a two-year change review

ASHRAE 62.1-2025 Table 8-1, reproduced in the August 2026 erratum, assigns a two-year review for Indoor Air Quality Procedure systems to identify changes in occupancy, space use, procedures, components and renovations. The erratum corrects its contaminant-table reference to Table 6-6. This is a method-specific operational task, not an instruction to wait two years after a known change. Record which calculation method each system uses so its maintenance calendar includes the right review. IAQP review interval and corrected reference

How it is used in the field

For a 10,000-square-foot supermarket, Addendum a increases the area contribution from 600 to 1,200 cfm. Its people rate remains 7.5 cfm per person, so a project design occupancy of 80 adds 600 cfm, producing 1,800 cfm of breathing-zone outdoor air before the applicable distribution, system and density adjustments. The same occupancy under the former area rate would produce 1,200 cfm. That 600 cfm increase belongs in replacement-unit and conditioning-load calculations.

For an uncorrected outdoor-air requirement of 600 cfm, a system ventilation efficiency of 0.80 and a project density factor of 1.20, the corrected intake calculation gives 900 cfm: 600 divided by 0.80, then multiplied by 1.20. Omitting density would produce 750 cfm. Label both the factor and the airflow basis on the test sheet so the TAB comparison uses the design's corrected quantity.

Before accepting a changed occupancy, reconcile the room schedule, ventilation calculation and controls points. Record which rooms changed category, which system serves them and which setpoints were revised. This is more useful than an unqualified statement that the air handler passed balance, because the acceptance question is whether it delivered the requirement for the current space use.

Edition history

The base edition is 62.1-2025. The August 27, 2026 errata sheet supersedes the January sheet, retaining its density-equation correction and adding the IAQP table-reference correction. Addendum a, approved June 30, 2026, changes the supermarket area rate. Record which addenda are adopted or specified alongside the corrected edition on the calculation cover sheet.

Frequently asked questions

Does the 2025 residential MERV 11 change apply automatically to 62.1?

No. ASHRAE's shared bookstore page describes the MERV 6-to-11 revision under Standard 62.2-2025. Identify the standard, space and actual filtration provision before transferring that statement to a commercial ventilation specification.

Does publishing a new ventilation edition change every existing permit?

Publication and adoption are separate. Record the edition incorporated into the permit or contract and the specific addenda included. A revised calculation should show its governing basis so plan review and field acceptance use the same requirement.