American Welding Society
AWS D1.1: WPS, PQR, welder qualifications, and the 2025 code
AWS D1.1/D1.1M:2025-AMD1 is the current Structural Welding Code for Steel. It organizes the welding procedure, personnel qualification, workmanship, and inspection evidence used to accept structural welds. A WPS tells production what conditions to use; a PQR records procedure-test observations; a welder qualification records the person's demonstrated range. Those documents answer separate approval questions. The specified project edition and amendment status determine which qualification and material provisions govern.
Applies to
Fabricators, erectors, welding engineers, inspectors, and owners use D1.1 where structural-steel contracts and applicable construction requirements invoke it. The code governs welding execution and acceptance; the structural design still establishes the member, connection, loading, and required weld. Carry that design information into the welding package so a sound weld is not mistaken for evidence that the connection was correctly designed.
Key topics
Three qualification documents answer three different questions
AWS's public 2025 Annex J provides PQR Form J-1, WPS Form J-2, and single-process welder qualification Form J-4. Compare them by function during submittal review: the PQR retains actual test conditions and results, the WPS defines production conditions, and the welder record connects an individual to a qualified range. Identify the WPS as prequalified or supported by the applicable procedure testing. A prequalified WPS is still a written procedure; that route does not turn the welder's test certificate into the missing production instruction. AWS qualification and procedure forms
A913 Grade 80 changes the material review
AWS's May 2025 Welding Journal identifies ASTM A913 Grade 80 as a new prequalified base metal in D1.1:2025, with minimum strengths of 80 ksi in yield and 95 ksi in tension. That addition makes the steel grade and governing edition material to the procedure review. It does not make every weld involving that steel automatically prequalified. Confirm the complete proposed procedure against the applicable prequalification conditions before selecting that route. A material substitution needs a welding review even when the member still meets the structural design. AWS explanation of the 2025 change
Keep the weld-test observations behind the procedure
AWS's 2025 sample PQR Form J-1 records preheat temperature and interpass temperature separately. It also provides entries for travel speed and maximum heat input. Preserve those actual observations with the test results and laboratory identifiers. A qualified procedure cannot be reconstructed from a statement that the coupon passed while its welding conditions have disappeared. Where several processes are combined, identify which process deposited each layer instead of assigning one undifferentiated set of parameters to the entire joint. AWS 2025 Annex J sample forms
Actual test values and qualified ranges are different records
AWS's 2025 single-process welder qualification Form J-4 separates the actual test variables from the ranges qualified and asks for the D1.1 edition year in its certification. That distinction is useful when reviewing a qualification issued for a previous project. The test coupon thickness is an observation; the allowable production thickness range is a code-derived result. Check the recorded range against the assigned production weld rather than assuming that a familiar process name establishes coverage. Form J-4 qualification record
How it is used in the field
Use a welding register with a row for each weld family: joint detail, base-metal specification and grade, WPS revision and qualification route, assigned welder records, required examination, and governing code edition. Cross-reference the material test report to the actual member mark. This makes an unreviewed grade substitution visible before it reaches the welding station.
When a member changes to a higher-strength grade, trace the revision through the material test report, connection detail, procedure, consumable selection, and assigned personnel. Record the acceptance of the revised package before production resumes. Keeping the old procedure number while changing the base metal hides the very decision the record needs to explain.
Retain the original qualification evidence and identify any later review against a different edition as a separate action. Likewise, label repaired welds on the weld map and connect the repair instruction to the follow-up examination. An accepted final result should lead back to the work and decisions that produced it.
Edition history
AWS identifies the available publication as 2025-AMD1. Record the full designation when purchasing and issuing controlled copies; a cover labeled only 2025 leaves the amendment status unresolved. AWS publication designation
Fabricators scheduling plant-service outreach receive their building lists as CSV or Excel within 48 hours through PorchRocket Ground Control.
Frequently asked questions
Does the latest AWS edition automatically replace the contract edition?
A publisher release changes what is available to purchase. Identify the edition governing the job from its applicable requirements and contract documents, then document any accepted change. Do not silently apply a new material allowance to an older project specification.
Can an AWS sample form serve as proof of qualification?
A blank form is a recording aid. The completed record needs actual test information, results, qualified ranges where applicable, and certification. Retain the underlying evidence that allows those entries to be reviewed.
Does a CWI credential qualify a welder or a procedure?
An inspector's credential is not a PQR or a welder performance record. Review the qualification evidence for the procedure and assigned welder, then record the inspection performed on the production weld. A familiar inspector's name cannot fill an absent test record.