ACI 355: anchor qualification limits and the reinforcing-bar distinction

ACI 355 is a family of product-qualification documents for connections to existing concrete. The 2024 editions distinguish mechanical anchors, adhesive anchors, and post-installed reinforcing-bar systems. Their tests establish the conditions and design data a qualified product supports; the connection design comes from ACI 318. A reinforcing bar used as an anchor and a bar developed as reinforcement require different qualification evidence, even when both are installed with adhesive.

Current edition: ACI CODE-355.2-24, CODE-355.4-24, and CODE-355.5-24 (2024)
Updated

Official publisher page

Applies to

Anchor manufacturers and independent testing agencies use these documents to establish product performance. Structural designers use the resulting data; submittal reviewers and inspectors verify that the specified system's qualification includes the proposed application.

A submittal reviewer needs the connection's design model, the product's tested conditions, and the installed configuration on the same schedule. Use the concrete anchor installation guide to connect that schedule to the crew's drilling and installation records.

Key topics

An anchor element and a developed reinforcing bar need different evidence

ACI CODE-355.5-24 qualifies post-installed bars for ACI 318 straight-bar development and splice-length design. ACI CODE-355.4-24 qualifies adhesive anchors, including systems using reinforcing bars as anchor elements. Identify whether the calculation develops reinforcement or designs an anchor connection before selecting the report. A bar's deformations and adhesive cartridge do not settle that distinction. The ACI publication for reinforcing-bar systems identifies its design pathway explicitly.

Qualification dimensions define the test framework

ACI CODE-355.2-24 covers mechanical anchors at least 1/4 inch in nominal diameter with at least 1-1/2 inches of effective embedment; screw-anchor embedment is limited to ten anchor diameters. ACI CODE-355.4-24 also starts at a 1/4-inch anchor diameter and bounds adhesive-anchor embedment by the greater of four diameters or 1-5/8 inches, up to twenty diameters. Apply the diameter and embedment checks separately. Within those boundaries, the product report still determines the recognized sizes, member thicknesses, and installation options.

Hole diameter is part of adhesive-system qualification

ACI CODE-355.4-24 limits the drilled-hole diameter in its scope to 1.5 times the anchor-element diameter. Its commentary explains that a thicker adhesive annulus changes how bond must be assessed. For a 1/2-inch rod, that scope boundary is a 3/4-inch hole. The approved product's required drill diameter still determines the actual hole; the scope calculation does not authorize enlarging it to that boundary.

Recognition follows the service condition, not the cartridge label

ACI 355.4-24 separates assessments for installation moisture, drilling methods, sustained loading, temperature, and installation direction. Recognition for saturated concrete does not establish recognition for a water-filled hole or submerged installation. Capture those conditions separately in the submittal comparison. The adhesive-anchor qualification preview shows why one general statement about wet service leaves material questions unanswered.

How it is used in the field

Build the anchor schedule around connection functions. Separate a railing post's anchor group from bars extending an existing wall, then attach the report that supports each calculation method. This prevents a single approved adhesive submittal from being treated as approval for every bonded connection on the site.

For a 3/8-inch adhesive anchor, four diameters equal 1-1/2 inches, so ACI 355.4's fixed 1-5/8-inch floor controls the qualification-scope minimum. For a 1/2-inch anchor, the calculated bounds are 2 and 10 inches. A 12-inch embedment is outside that anchor scope; determine the applicable design and qualification pathway before treating the extra depth as usable bond length.

For each substitution, compare recognized conditions before comparing capacities. A product with a higher catalog tension value still needs the required concrete condition, drilling system, installation orientation, and service-temperature recognition. Preserve the accepted comparison with the connection identifier so purchasing and inspection use the same product configuration.

Edition history

ACI's product pages identify CODE-355.2-24, CODE-355.4-24, and CODE-355.5-24 as the 2024 mechanical-anchor, adhesive-anchor, and reinforcing-bar qualification documents. Retain the decimal suffix in purchase and submittal records so a citation identifies the testing program actually used.

Adoption

The design connection is through ACI 318 and the building code that references it. The 2024 adhesive-anchor publication identifies ACI CODE-318-25 as its design basis. Match the qualification report to the project's accepted ACI 318 edition rather than assuming publication of a newer test code updates an existing report.

Frequently asked questions

Does a longer bonded bar always qualify as an adhesive anchor?

Length does not establish the design model. Determine whether the bar transfers force through anchor design or through reinforcement development and splicing. ACI 355.4 and ACI 355.5 qualify those different uses.

Does a proof-load result expand a product's approved uses?

A site test records the installed connection's response under that test. It does not supply the temperature, sustained-load, moisture, and seismic qualification evidence established by the applicable ACI 355 testing program.