How to scope corroded post-tension tendons in a parking structure

Identify the PT system, connect investigation findings to structural decisions, and measure tendon repairs with defined acceptance evidence.

Post-tensioningParking structuresTendon corrosionRepair scopeStructural assessment

Direct answer

Scope corroded post-tension tendons by identifying the installed system, mapping tendon distress and water entry, and commissioning tests that distinguish protection defects, broken steel, and lost prestress. Use PTI DC80.3-24/ICRI 320.6-2024 for single-strand unbonded systems, then turn the findings into an engineered load-management plan, measured repair quantities, and acceptance records for each tendon. Include drainage, joints, and anchorage protection in the scope so the repair addresses the route that admitted water.

On this pageWhat belongs in a tendon corrosion repair scope?Which post-tensioning system is installed?What does unbonded tendon corrosion look like?Which investigation tests answer the tendon question?How many tendons and anchorages should be investigated?What must the engineered load-management plan control?Repair, replace or strengthen: which decision does the evidence support?How should sheathing, anchorages and water entry be repaired?How do you price and phase a parking garage tendon repair scope?Worked examples from published parking structure repairsWhat evidence closes the repair scope?What should the owner inspect after tendon repairs?

What belongs in a tendon corrosion repair scope?

A tendon repair scope identifies affected tendons, evidence supporting each repair decision, permitted temporary conditions and records needed to release completed work.

Use the parking structure restoration and repair guide for the wider garage program. Here, keep tendon investigation and repair quantities distinct from ordinary concrete patching.

Define the deliverables before commissioning tests

Require a system schedule, condition maps, test plan, load-management drawings, repair quantities and inspection hold points. Carry one stable tendon ID through the plan, photographs, opening records, tests, repair detail and closeout. Mark each condition as verified, suspected or inaccessible; these are Anvilfield record conventions.

The owner supplies history and access; the investigating engineer selects the investigation and evaluates structural consequences; the repair designer specifies permanent repairs and temporary conditions; the PT specialist executes the specified work; the testing agency supplies traceable results. The Chester Street 2024 project manual shows how these responsibilities become submittals, measured items and acceptance records.

Include top and soffit access, occupied rooms, utilities, opening reinstatement and temporary water exclusion. State who authorizes supplemental testing, changed quantities and redesign after concealed conditions appear.

Which post-tensioning system is installed?

Identify tendon construction, corrosion protection and hardware separately. In an unbonded tendon, coated steel can move relative to its sheath and transfers force through anchorages; in a bonded tendon, cementitious grout bonds the steel within its duct. That distinction changes how a local defect affects the investigation and repair. PTI DC80.3-24/ICRI 320.6-2024 addresses evaluation and repair of single-strand unbonded post-tensioned structures; a cement-grouted multistrand or bar system requires the grouted-system investigation branch described by ACI PRC-423.8-21.

Match structural and PT placing drawings, shop drawings, material certificates and previous repair records to controlled observations of the installed details. Confirm that the member is post-tensioned before assigning a repair branch: a precast member can be pretensioned, post-tensioned or conventionally reinforced. Use its fabrication and connection records to establish which system is present.

Schedule mixed construction and successive repair generations by location. ACI PRC-423.4-14 is the separate unbonded single-strand corrosion and repair report.

Table 1. System identification and scope consequences
Installed systemEvidence to obtainProtection to verifyInvestigation/repair consequenceSource
Plastic-sheathed unbonded seven-wire strandStrand and PT drawings; observed sheath and wedge anchorage; steel recordsPT coating, sheath continuity, end caps and transitionsTrace the continuous tendon and both ends; distinguish steel condition from protection conditionS1, S2, S6
Older paper-wrapped or loose-sheathed unbonded strandOriginal detail and observed wrapping/seam; historical hardwareActual remaining barrier and water pathsTest selection and replacement feasibility must match the old sheath; do not assume modern encapsulationS2, S3
Button-headed parallel-wire tendonWire bundle and end-bearing/button-head detailWrapping, anchorage enclosure, water entrySeparate hardware and strengthening design from seven-wire monostrand repairS2, S7
Cement-grouted multistrand or bar tendonDuct, grout and anchorage records; observed constructionGrout continuity/condition, ducts and anchor protectionUse grouted-system investigation, including void/grout evidence; use ACI PRC-423.8-21 rather than applying the unbonded guide wholesaleS10, S15
Mixed or previously modified systemLocation-linked records for every system and repair generationEach old-to-new interfaceSchedule separate details and acceptance records; unresolved identity stays open in the design registerS6; Anvilfield synthesis

Identify the steel as well as the sheath

PTI FAQ 18, July 2026 distinguishes 250 ksi and 270 ksi strand and normal-relaxation and low-relaxation steel; repair design needs both strength and relaxation type. Confirm diameter and net steel area from records or authorized testing. A newer replacement or one capped anchorage does not establish the identity or encapsulation of every tendon on the floor.

Record identity as observed-and-documented, records only, or unresolved. Account for sampling in the structural assessment. The post-tension slab stressing guide explains original system terminology and stressing records; retain those records as evidence for the repair-specific design.

What does unbonded tendon corrosion look like?

Protruding strand, displaced anchorage hardware, fresh anchor-zone spalls and a reported tendon release require immediate area control and structural assessment. PTI Journal’s July 2006 repair paper describes distress and legacy-system problems that warrant investigation; crack width alone does not establish permission to continue garage operations.

Map rust or grease stains, leaking pockets, tendon-line cracks and soffit damage as investigation evidence. Separate concrete delamination from observations of the strand, wires and anchorages. An intact-looking surface cannot establish the condition of embedded steel.

Trace water from deck surfaces, joints and drains to anchor pockets, tendon low points and repair transitions. Water can travel along a sheath, separating the visible entry point from the damaged steel. The potentially affected length follows the tendon route and water pathway rather than the edge of a visible patch.

Check competing causes: rust from conventional reinforcement, cracking away from tendon lines, damaged anchorage concrete and recent drilling. Visible rust extent does not establish residual strength; use fracture or material examination where the mechanism changes the repair decision [S2, S3].

Table 2. Distress mapping register
Evidence categoryLocation and measurement fieldsWhat the finding supportsNext scope itemSource
Broken wire, protruding strand or displaced hardwareLevel, grid, tendon ID, observed break/displacement, photoA visible break confirms local discontinuity; displaced hardware needs its mechanism resolvedImmediate area control; engineering assessment of affected tendon/load pathS2, S6
Anchor pocket rust/leakageEnd ID, wet/dry state, stain/defect extent, photoSuspected water access or hardware deteriorationSpecified pocket investigation and adjacent-water-path reviewS2, S5
Grease staining/tendon-line crackingAlignment, length in ft, width in in or mm, dated photoPossible protection defect or tendon distressTargeted investigation correlated with tendon layoutS2
Spall/delaminationTop/soffit, measured sq ft and depth in in, steel encounteredConcrete deterioration footprintApproved removal limits plus separate PT assessment where encounteredS6
Failed joint/drain or pondingJoint/drain ID, wet-weather photos, affected routeSource or concentration of waterDrainage/joint/waterproofing repair packageS4, S6
Inaccessible zoneExact boundary, reason, next access opportunityUnassessed extentAccess allowance and investigation return pointAnvilfield record convention

Use the crack monitoring guide for repeatable measurements. Tie each observation to the mapped tendon, date and prior repair boundary.

Which investigation tests answer the tendon question?

Choose each test for a specific question and decision: location, concrete distress, exposure, steel condition or force.

The 2017 NCHRP Research Report 848 describes differing NDE methods for bridge PT and stay-cable systems. Applying a method in a garage requires validation for its tendon construction and access. A GPR location scan alone cannot certify remaining tendon cross-section, effective prestress or structural capacity.

Use embedded-feature locating before designed openings to coordinate access and conflicts. The diagnostic test selection guide separates concrete material questions from tendon questions. Measurable tension can coexist with local steel damage.

Table 3. Specialist investigation matrix
InvestigationQuestion answeredEvidence deliveredLimitation carried into the scopeDesign/bid decision it supportsSource
Records reconciliationWhat was installed and altered?System, tendon routing, steel/hardware records, gapsRecords require correlation with actual constructionWhich investigation and hardware package to specifyS1, S2, S6
GPR/embedded-feature locatingWhere are tendons/rebar and proposed opening conflicts?Marked plan, depth interpretation, coverage limitsCongestion and depth affect interpretation; no direct strength/force certificateEngineer's opening locations and access planS8
Visual survey and concrete soundingWhere is visible distress or delamination?Location-linked photos and concrete distress mapCannot expose hidden steel conditionSurvey quantities and target locationsS2, S6
Designed inspection opening/pocket examinationWhat are local protection, water and hardware conditions?Local images, steel/anchor observations, sample IDsLocal evidence; opening/restoration must be engineeredProtection-only work versus further steel/force investigationS1, S2, S6
Steel-condition examination and authorized laboratory testingIs the exposed/sample steel pitted, fractured or of uncertain identity?Measured condition, sample provenance, material/fracture resultsRemoved sample and accessible face are not the whole tendon populationReuse, replacement, supplementation and investigation expansionS2, S3
Engineer-specified in-place force/lift-off testingWhat force does the specified test infer at this location and stage?Test method, calibration, location, load/displacement record, limitationsFeasibility depends on accessible compatible hardware; not residual strength or whole-length corrosion clearanceAnalysis input and repair dispositionS1, S2; decision logic is Anvilfield synthesis
Half-cell survey of suitable rebarWhere does rebar potential indicate corrosion activity?Electrode, continuity/circuit checks, conditions and potentialsNo transfer of rebar probability bands to sheathed strandConventional reinforcement corrosion programS9
Concrete or grout chloride testingWhat contamination is present at the sampled depth/material?Method, depth, units, material/binder basisConcrete, grout and tendon environments differWater-source control and material-specific durability interpretationS11, S15

Why rebar tests do not become tendon acceptance tests

ASTM C876-22b estimates corrosion potential in uncoated reinforcing steel and expressly excludes using its results to estimate structural properties, so a rebar potential map does not establish the residual capacity of a sheathed tendon.

Read the half-cell potential definition and survey interpretation guide when specifying the separate rebar program. ASTM C1152/C1152M-20 measures acid-soluble chloride, generally total chloride, in mortar and concrete; record depth, sampled material and reporting basis. Chemistry describes exposure at the sample location, not tendon force.

FHWA-HRT-14-040, March 2014 studies chloride thresholds in cementitious tendon grout. Interpret a grout sample within that system; its thresholds do not transfer to grease-filled unbonded tendons.

How many tendons and anchorages should be investigated?

The Chester Street March 21, 2024 bid package allows 125 slab openings and 250 grout-pocket openings for its investigation. Use these as project-specific bid allowances; the initial count for another garage follows its systems, exposure, known failures, variability, access and structural consequences.

Group locations by system generation, level, tendon direction or band, anchorage type, repair history and water exposure. Include apparently unaffected comparison locations. Count distinct tendons separately from openings because several openings can examine the same tendon; a distress-only sample cannot establish garage-wide damage prevalence.

For every group, record the population, selected tendon IDs, selection reason, method, result and expansion authorization. Classify the outcome as accepted evidence supporting a stated disposition, adverse evidence requiring redesign or expansion, or inconclusive evidence requiring different access or testing. An inaccessible location stays unassessed.

Define what makes the investigation expand

Expand when damage extends beyond the assumed boundary, adjacent tendons share the same water entry, installed steel or hardware differs from records, or force/material findings change the structural model. The engineer identifies the next group and the decision it will settle. Price supplemental access, openings, laboratory work and reinstatement with that decision path.

Report findings by sampling group; deliberately selected wet pockets cannot represent all garage tendons.

End each investigation stage with a decision for every group: enough evidence for the specified repair, additional locations needed, or a changed investigation method. Keep wet and apparently dry groups separate when reviewing results. A satisfactory exposed segment does not clear an unexamined anchorage or an inaccessible portion of the same tendon.

What must the engineered load-management plan control?

The phase plan must control occupancy, affected levels, construction loads, removal limits, temporary supports, observation triggers and release conditions. Assess the full anchor-to-anchor tendon route and affected members before limiting restrictions to the visibly damaged bay. Include the temporary loss of tendon contribution during investigation and repair.

The structural review addresses flexure, shear and punching where applicable, anchorage-zone condition, serviceability and redistribution assumptions. Trace temporary supports through underlying floors to the final supporting structure. Closing parking stalls does not establish the capacity of that temporary load path.

ACI CODE-562, Assessment, Repair, and Rehabilitation of Existing Concrete Structures supplies an assessment and repair framework; the adopted edition, permit requirements and contract determine its project application. Put the applicable basis on the design documents.

Table 4. Engineered load-management register
Condition/phaseDecision to recordResponsible decisionEvidence before work/occupancy changesRelease requirementBasis
Known tendon failure or unknown structural effectDefined restricted area and assessment extentStructural assessment engineerCondition map and affected tendon/load-path reviewWritten disposition for specified useS1, S2
Investigation openingLocation, depth/extent limits and temporary support requirementInvestigation/repair designerLocated embedded features and authorized opening detailOpening inspected and restored as specifiedS6, S8
Concrete removal/PT repairPermitted concurrent work and support sequenceRepair and temporary-works designersApproved phase drawing and verified supportsRequired repair strength and PT records acceptedS6
Equipment/material/debris stagingWeights, wheel/contact loads, routes and allowed locationsEmployer, using information from a person qualified in structural designEquipment data and load evaluationLoad removed or next stage approvedS12(a)
Tendon stressing work zoneBarricade and access arrangementEmployer implementing design and safety planSigns, barriers and controlled accessWork zone released under the project planS12(c)
Adjacent occupied areas and lower levelsParking/egress/debris separation and support implicationsDesigner plus owner/operator for accessPhase-specific access and protection planApproved phase transitionS6
Return to serviceApproved vehicle use and remaining restrictionsRepair designer; owner implementsAccepted repair package, specified strength and temporary-support dispositionWritten authorization identifying area and useS6

Separate operating restrictions from repair operations

Under 29 CFR 1926.701(a), the employer must determine that the affected concrete structure can support proposed construction loads, using information from a person qualified in structural design. Record equipment weights, wheel/contact loads, debris accumulations, material staging and permitted travel routes on the phase drawing.

Under 29 CFR 1926.701(c), employees behind the jack during tensioning must be essential to the post-tensioning operation, and signs and barriers must limit employee access to the post-tensioning area. Coordinate these work zones with parking, egress and protection of adjacent occupied areas.

The shoring and reshoring guide supports temporary-load-path coordination. Keep the repair designer’s authorization, temporary-works design and owner’s access arrangement under the same phase ID.

Repair, replace or strengthen: which decision does the evidence support?

Select the intervention from steel and hardware condition, remaining force, continuous tendon route, available access, compatible components and repair-stage capacity. Protection restoration and structural restoration have different evidence requirements. Renewing sheathing does not replace lost steel section or establish effective prestress.

Table 5. Repair decision table
Scope alternativeEvidence neededWhat the design must establishMeasured scope itemBasis
Protection restorationLocal steel/hardware condition accepted for reuseRequired barrier and acceptable retained structural roleSheathing ft; pocket/anchor treatment eachS4, S6
Local steel/splice repairDamage extent and sound connection zones; compatible steel/hardwareTransfer of required force and repair-stage capacityStrand ft; couplers each; stressing locations eachS1, S2, S6
Complete tendon replacementExisting tendon route, sheath usability and access feasibilityNew tendon force, anchor zones, profile and transitionsTendon/strand ft plus separate anchor/stressing itemsS1, S2
Supplemental strengtheningExisting system contribution and available attachment/load pathForce transfer, anchorage capacity, clearance, protection and temporary statesDesigned system quantitiesS2, S7
Leave tendon out of serviceVerified system condition and analysis of required strength/serviceabilityAcceptable defined use without crediting that tendonAnalysis/disposition plus any protection workS2
Member/slab replacementExtent and lifecycle comparison of alternativesPermanent replacement and temporary load pathArea/volume and associated systems by designS16

Compare future access and protection continuity alongside initial constructability. The published cases below show how system identity and damage extent change the repair choice.

Why repair force differs from new-construction force

PTI FAQ 18, July 2026 assigns repair jacking force to the licensed design professional because existing steel identity and the difference between original and post-repair losses determine the force needed to restore effective prestress.

For its 0.5 in, seven-wire, 270 ksi strand example with no new long-term losses, PTI FAQ 18, July 2026 reduces the original 33 kip jacking value by 1.9 kip for low-relaxation steel or 4.1 kip for normal-relaxation steel, giving rounded repair examples of 31 kip and 29 kip respectively. These values explain the loss calculation; the approved repair schedule supplies the project force.

New strand and substantial replacement concrete change long-term losses; degraded coating and paper wrapping change friction. PTI FAQ 18 permits the designer to retain the original jacking force when the resulting effective force is acceptable. The repair schedule must identify the steel, loss assumptions and selected force, rather than applying one reduced value to every tendon.

Set reuse criteria before exposed steel is accepted. Record broken wires, pitting, hardware damage and the extent actually examined; average visible section loss alone cannot establish the strength of a locally pitted strand. Require a written tendon disposition that reconciles steel condition, attainable force and structural analysis, as the 2006 PTI repair paper and 2026 repair-force FAQ frame those decisions.

How should sheathing, anchorages and water entry be repaired?

Specify continuous protection across old-to-new sheathing, couplers and anchorages, with inspection before concealment. PTI FAQ 16, July 2017 treats sheathing continuity and restored PT coating as corrosion defenses and explains that the repair also preserves the strand’s unbonded behavior. A painted pocket cannot replace the specified tendon protection assembly.

Which dimensions and manufacturer details belong in the specification?

The M10.3-16 Appendix C detail reproduced in PTI FAQ 16, July 2017 uses separate tubing and tape extension datums, as the comparison below records; the FAQ separately specifies tape at least 2 in wide.

Resolve the FAQ narrative and Chester specification against the approved detail before procurement. Distinguish access exposure, tubing overlap and tape extension in the takeoff.

Table 6. Standards, project and manufacturer differences
IssueVerified instruction or product scopeDifference that mattersWhich document governs the decision?Source/version
Existing unbonded systemJoint evaluation guide is DC80.3-24/ICRI 320.6-2024Use the specified edition for existing single-strand unbonded PTProject's specified/adopted documents plus identified current guidanceS1, S19
Manual and specification editionsPTI lists field manual M10.3-26 and tendon specification M10.2-24FAQ 16 reproduces a detail from M10.3-16Approved project detail referencing the specified manual editionS4, S19
Sheath repair access versus overlapChester §3.6.A requires at least 6 in exposure beyond damage; FAQ 16's reproduced 2016 appendix shows tubing 3 in past damage and tape 3 in past tubingExposure, tubing overlap and tape extension have different datums; Chester §3.6.D describes tape 3 in onto existing sheathingDimension each interface in the approved project detail and resolve conflicting wording with the designerS4 pp. 1 to 3; S6 §3.6
Waterproof tapeFAQ 16 calls for compatible waterproof tape; ordinary duct tape is unsuitablePTI's FAQ index retracts the old December 2002 tape qualification documentCurrent product technical data/testing and approved detail, not the retracted listS4, S20
Pocket fillFAQ 11 specifies premixed cementitious chloride-free non-shrink repair grout, with manufacturer preparation, mixing and curePocket fill and underlying anchor protection need separate acceptanceApproved pocket material and manufacturer's instructionsS5, revised July 2010
GTI Zero Void intermediate coupler0.5 in product intended for construction-joint continuity or future extensionCatalog application is not approval as a corrosion-repair spliceSupplier's approved repair-specific assembly and engineer's designS17, undated product page, checked 2026-11-05
VSL unbonded monostrandProduct family lists 0.5 and 0.6 in systems and distinct anchor/coupler componentsSame nominal strand diameter does not establish compatibility with legacy hardware or another manufacturer's sealsSelected system's submittal and approved interfacesS18, undated product page, checked 2026-11-05

Congested bands, support bars, old wrapping and inaccessible undersides affect whether the specified transition can be sealed. Require interface details and clearances in the submittal. Coordinate the joint sealant work and traffic deck waterproofing with anchorages and repair edges so the water-entry correction reaches the actual source.

How do you price and phase a parking garage tendon repair scope?

Price a defined package with current project quotations for its access arrangement and PT system. Separate fixed investigation and temporary-work costs from remeasured concrete, sheathing, strand and hardware quantities. Put inclusions, separately paid work, measurement rules and authority for quantity changes beside each item.

The Chester Street 2024 bid form, items 32 through 40 provides published estimated bidding quantities and payment units. Use its work breakdown with explicit measurement rules and payment inclusions.

Table 7. A real owner's PT bid schedule
ItemDescription, paraphrasedEstimated bid quantityPayment unit
32Slab investigation opening125each
33Grout pocket investigation opening250each
34Tendon sheath repair1,000lin ft
35New seven-wire strand2,500lin ft
36Strand coupler100each
37Central stressing coupler, including restressing50each
38New fixed-end anchorage15each
39Reseat tendon in existing end anchor5each
40Reseat tendon in existing stressing-end anchor, including restressing10each

Chester’s Section 01 22 00 includes locating and restoration in slab-opening item 32. Sheath-repair item 34 measures length while concrete work is separately measured; new-strand item 35 includes old-to-new sheath transitions; coupler item 36 includes coupler protection and exposed-sheath repair.

Central-stressing-coupler item 37 includes shoring, phasing and restressing, while concrete work and new strand are paid separately. New fixed-end item 38 also includes shoring; reseating items 39 and 40 include pocket restoration. Use those boundaries to check the project payment schedule before extending quantities. Separate shared temporary works from work already included in an individual repair item.

What cost and time should the estimate carry?

Build the budget from investigation and engineering, access, temporary works, measured tendon repairs, concrete reinstatement, testing and water exclusion. Obtain current quotations for the identified system and hardware. Include additional investigation locations and a review allowance for concealed conditions; keep owner closure costs separate from contractor work.

Anvilfield estimates 25 to 38 working days for 375 investigation openings if one crew completes an assumed 10 to 15 openings per working day, including local restoration. This planning calculation uses the Chester quantities and an estimator-selected production allowance. Divide openings by daily output and round up; replace the allowance with the specialist's proposed crew output for the actual access and repair details.

Schedule engineering reviews, material procurement, temporary supports, tendon repairs and cure holds as separate activities. Keep slow soffit access and pocket work as distinct production items when preparing the contractor schedule. Reopening follows specified strength, accepted PT records, temporary-support release and the surfacing manufacturer's traffic-release conditions.

Municipal owners can procure investigation separately to resolve concealed conditions before bidding repairs. Bid history helps an estimator identify the owner's purchasing pattern: PorchRocket Bid Control shows who won past public garage repair bids and for how much.

Worked examples from published parking structure repairs

Turn an investigation allowance into access quantities

Anvilfield estimates 375 scheduled openings and an allowance of 84 pocket-access locations from Chester Street’s March 21, 2024 quantities and pricing assumption.

Table 8. Chester Street investigation and access takeoff
Input or calculated resultQuantityBasis and estimating use
Slab investigation openings125 eachS6, bid item 32; includes locating and opening restoration
Grout-pocket investigation openings250 eachS6, bid item 33; includes cap and pocket restoration
Total scheduled openings375 eachAnvilfield estimate: sum the two distinct opening categories
Pocket openings per access locationAverage 3S6, Section 01 22 00, item 33 pricing assumption
Pocket access-location allowance84 locationsAnvilfield estimate: divide 250 by 3 and round up
Access allowance at 2 pockets per location125 locationsAnvilfield estimate: changed grouping assumption for access sensitivity
Additional locations in that access case41 locationsAnvilfield estimate: 125 minus 84

Method: add the two opening categories, then divide pocket openings by the specified average grouping and round up. In symbols, 125 + 250 = 375 openings; ceiling(250 / 3) = 84 pocket-access locations. Changing to two pockets per location gives 125 locations, or 41 additional setups. Price those extra setups only where separately payable.

Associate every opening with a tendon and investigation decision. Access setups and distinct tendons need separate counts: moving a lift does not necessarily reach another tendon, and an opening allowance does not establish a replacement quantity.

Different members can require different repairs

The July/August 2001 ICRI Alexandria case found that almost all elevated-slab tendons needed replacement, while approximately 10% of the mat-foundation tendons needed repair. The selected scope replaced the elevated PT slab with conventionally reinforced concrete and repaired the mat slab and tendons.

The published case reports three weeks to remove the 37,000 sq ft elevated slab. That duration belongs to slab removal; procurement, reconstruction and reopening are separate schedule activities. Compare the affected members independently, including usable access, required capacity, protection restoration and continuing maintenance.

Why a wire count does not establish remaining structural capacity

PTI’s 2024 O’Hare presentation reports a column with three 42-wire tendons, at least ten failed wires and unknown condition of the remaining wires, followed by external PT strengthening. Anvilfield estimates a minimum observed failed-wire share of 7.94%: divide failed wires by the original wire count and express it as a percentage, 10 / (3 × 42) × 100 = 7.94%.

Carry that observed damage and the unresolved condition into analysis. The reusable case record is system identity, observations, unknowns, structural evaluation, selected strengthening and protection details.

What evidence closes the repair scope?

Accept the tendon record, protection assembly, concrete repair and operating state separately. The Chester Street 2024 specification, Section 03 01 24 §3.9 connects strength, stressing and as-built evidence to completion.

Set hold points before mobilization and assign a reviewer to each. Specify the required concrete strength, force and elongation acceptance ranges in the repair documents. Retain access until discrepancies are resolved, and inspect hardware, sheath transitions and anchorage protection while visible.

Table 9. Repair acceptance evidence
Hold pointRequired evidenceWho reviews/releasesWhat keeps the item openBasis
System/design before mobilizationVerified steel/system schedule, repair details, approved temporary conditionsRepair designerUnresolved material identity or load-path assumptionsS3, S6
Exposed tendon before dispositionPhotos, measured condition, sample/test results, location IDInvestigating/repair engineerUnassessed pitting, fracture or hardware conditionS1, S6
Hardware/material before installationProduct data, certificates, steel size/area/grade and approved compatibilityRepair designer under submittal processUnapproved substitutions or missing interface detailS6
Stressing readinessSpecified versus actual concrete strength; approved loss calculations; matched jack/gauge calibrationDesignated inspector and repair designerStrength, equipment or calculation not acceptedS6 §3.9
Force/elongation recordTendon ID, force/pressure, calculated and measured elongation, conditions and dispositionRepair designerOut-of-range or unexplained result under project criteriaS6 §3.9
Protection before concealmentSheath, coupler and anchorage continuity; caps; accepted transitions; photosEngineer/testing agency as specifiedGaps, incompatible protection or incomplete inspectionS4, S6
Concrete/material repairPlacement, curing, specified strength; pull-off result and failure mode where requiredSpecified testing agency/designerFailed criterion or unclassified failure modeS6, S13
Waterproofing/closureJoint/drain details and accepted deck protection; operating restrictionsDesigner and owner for their respective scopeUnfinished water-entry correction or restricted phaseS6
Return to service/turnoverAs-built repair map; released supports and restrictions; maintenance scheduleRepair designer; owner implementsMissing release or incomplete structural evidenceS6

Keep concrete test results separate from tendon acceptance

ASTM C1583/C1583M-25 requires a failure mode for every pull-off result and permits averaging only results with the same failure mode; a repair-bond result does not establish restored tendon force. Locate embedded steel and approve test sites before drilling pull-off specimens in PT concrete.

Use the pull-off testing guide for that concrete evidence and the concrete repair and restoration guide for substrate, placement and curing scope after PT-specific details are established. Record every discrepancy and its written resolution.

The written service release identifies the area, permitted use and remaining access obligations.

What should the owner inspect after tendon repairs?

The University of Missouri System’s Parking Garage Evaluations and Maintenance Guidelines call for annual in-house visual inspections and suggest late winter or early spring. Use that owner-program example to establish a dated calendar for leaks, drains, sealants, pockets and repair interfaces; the repair engineer specifies closer tendon monitoring where findings require it.

Use closeout photographs and the repaired tendon map as the baseline. Salt, persistent leaks and legacy protection increase exposure; prior failures and active movement increase urgency. Record the observer, next review date and reason for any shortened interval.

New York City’s parking-structure program requires a condition assessment and filed report at least once every six years for covered structures, performed by a New York State licensed and registered professional engineer who is also a Qualified Parking Structure Inspector (QPSI). Keep that local statutory cycle separate from repair monitoring and prompt response to new distress. A new release or displaced hardware requires immediate area control and structural assessment.

Field checklist from investigation to turnover

  • Identify every system and mark unresolved steel/hardware identity.
  • Collect PT drawings, prior repairs and material certificates.
  • Trace tendons, ends, intermediate anchors and inspection locations.
  • Map distress, water routes and inaccessible zones with dated photographs.
  • Assign each test a question, location, limitation and decision.
  • Record sample groups, comparison locations and expansion triggers.
  • Obtain engineered opening, removal and temporary-support requirements.
  • Record equipment, debris and material loads and approved locations.
  • Put area controls, public separation and egress on the phase plan.
  • Give each tendon a written repair, replacement, strengthening or reuse disposition.
  • Approve steel, hardware and protection interfaces before procurement.
  • Define investigation, sheath, strand, hardware and stressing payment boundaries.
  • Inspect and photograph exposed work before concealment.
  • Accept strength, stressing and protection evidence; resolve deviations.
  • Complete joint, drainage and waterproofing repairs.
  • Issue the as-built register, service release and observation schedule.

Sources checked and how to cite this page

Anvilfield. Reviewed 2026-11-05. Update log: publication and article review, 2026-11-05. References below include PTI technical guidance, publisher descriptions, agency requirements and published project evidence.

Evidence tables are Anvilfield syntheses of the cited references.

How to cite this page: Anvilfield, How to scope corroded post-tension tendons in a parking structure, 2026, https://anvilfield.com/field-guides/concrete/post-tension-tendon-corrosion-repair/

Related tools

Next step: Find garage repair bids

FAQ

How do you investigate tendon corrosion in a parking garage?

Identify the system, map distress and water entry, then use designed openings and selected tests to answer steel-condition and force questions.

How do I identify the PT system in an existing garage?

Match structural and PT shop drawings to observed sheath, strand or wire, and anchorage details. Record protection and steel identity separately; one encapsulated repaired end does not establish the protection of the whole tendon.

What are signs of unbonded tendon corrosion?

Rust or grease staining, wet pockets, tendon-line cracking, anchor distress and released strand warrant location-linked investigation. A visible wire break establishes local discontinuity; staining alone does not establish fracture.

Can GPR prove a tendon is unbroken?

A location scan does not establish whole-tendon integrity, force or residual capacity. Use it to coordinate embedded-feature locations and engineered access, then obtain the condition and force evidence required by the investigation.

Can half-cell testing measure PT tendon corrosion?

ASTM C876-22b addresses uncoated reinforcing steel. Its rebar potential bands are not acceptance criteria for grease-filled sheathed tendons; keep rebar corrosion mapping separate from tendon-condition evidence.

How many tendons need testing?

Chester Street’s 2024 bid package allows 125 slab openings and 250 pocket openings. A project sampling plan sets its own count from system, exposure, failure history and structural consequences. Count distinct tendons separately, include comparison locations and define investigation expansion triggers.

Must a corroded tendon always be replaced?

The disposition follows steel and hardware condition plus structural analysis. Protection repair, local steel repair, replacement, supplemental strengthening and leaving a tendon out of service require different evidence and design checks.

Can a garage stay open during tendon repairs?

Operation is limited to the areas, loads and uses authorized by the engineered phase and support plan. Carry lower-level support implications, construction loads, public separation and egress into the same phase record.

Should an old tendon be restressed to the original jacking force?

PTI FAQ 18, July 2026, assigns a repair-specific force decision to the licensed design professional using existing steel identity, effective prestress and changed losses. Use the approved repair schedule for the project force.

What does parking garage tendon repair cost?

Build a current estimate from separate investigation, access, engineering, temporary works, tendon repairs, concrete reinstatement and waterproofing quantities. Obtain system-specific contractor quotations and define payment inclusions so sheath transitions, shoring and restressing are counted once.

How long does parking garage tendon repair take?

For 375 investigation openings, Anvilfield estimates 25 to 38 working days at an assumed crew output of 10 to 15 openings per day including local restoration. Add engineering review, procurement, tendon repairs and cure holds as separate scheduled activities; their durations follow the actual repair package.

What proves a tendon repair is complete?

The closeout package links each tendon to accepted material and hardware records, approved stressing results, inspected protection, concrete-strength evidence and an as-built repair map. Resolve deviations before concealment and obtain the written release for the specified use and area.