Field glossary · measurement
Half-cell potential
Half-cell potential compares reinforcing-steel voltage with a reference electrode through an electrical circuit completed at the concrete surface. Establish the circuit before interpreting a map: FHWA uses a continuity criterion of 1 ohm or less after accounting for lead resistance. Report electrode chemistry and contact conditions with each survey, because those conditions govern whether its corrosion-probability bands apply.
Electrical potential of reinforcing steel against a reference electrode, used to estimate corrosion activity under ASTM C876-22b
Reading the copper-sulfate probability bands
Under FHWA's copper/copper-sulfate interpretation, a -410 mV reading lies below the -350 mV boundary associated with about 90% probability of active corrosion, while -150 mV lies above the -200 mV boundary associated with about 90% probability of no active corrosion. A -275 mV result remains in the uncertain band. Identify the electrode before applying those boundaries to a plotted value.
These are probability bands for the stated reference system, not a scale of percentage steel loss. A reading of -400 mV does not mean twice the corrosion rate of -200 mV. Preserve individual readings and their coordinates before generating contours, because interpolation can make a sparse grid look more definitive than its measurements.
When the electrical circuit changes the answer
ASTM C876-22b excludes reinforced concrete with epoxy-coated bars from this test method. It also excludes arrangements where a waterproofing membrane between the reinforcement and test surface interrupts the electrical path. Establish the reinforcement type and continuity before treating a surface voltage map as a corrosion survey.
ASTM C876-22b notes that cover deeper than 75 mm can average adjacent reinforcement potentials and reduce discrimination between locations with different corrosion activity. A smooth potential contour over thick cover can therefore conceal local differences rather than demonstrate uniform steel condition.
FHWA's field setup checks continuity between steel connection points against a limit of 1 ohm after accounting for test-lead resistance. It connects reinforcing steel to the positive meter terminal and the reference cell to the negative terminal. Record the connection points and polarity so an apparent reversal of corrosion condition is not simply reversed leads.
For repeat surveys, use the same coordinate system and document reference-cell condition, wetting, temperature, and steel connection. Changing the measurement conditions between visits can change the readings without establishing a corresponding change in metal loss.
Translate a potential map into the next investigation
Select verification locations from each mapped probability band, including areas without visible spalls. A high-probability location needs evidence of the corrosion mechanism and actual steel condition; the voltage supplies neither a metal-loss rate nor a remaining bar area. Chloride samples, cover measurements, and selected exposures provide those different parts of the investigation.
Overlay the potential map with the reinforcement-corrosion investigation and the repair assessment, keeping each test's findings identifiable. Corrosion probability, delamination extent, and measured bar-section loss remain separate results even when they share a location.
Distinctions
- Corrosion rate
- Rate describes how quickly metal is being consumed. Potential alone supplies no conversion to thickness loss per year.
- Concrete resistivity
- Resistivity describes opposition to electrical current through concrete. It helps explain environmental conditions and current paths but is a different measurement.
Frequently asked questions
Does -350 mV mean the reinforcing bar has failed?
No. The potential band indicates corrosion probability under the test conditions. Structural assessment uses the actual steel section, anchorage, concrete condition, and loads.
Can I apply copper-sulfate thresholds to any reference electrode?
No. Reference electrodes have different potentials. Identify the cell chemistry and use the interpretation or conversion appropriate to that reference.
Sources checked
Also defined as
- The reinforcing steel's electrical potential against a reference cell, read to estimate corrosion activity
- A voltage reading against a reference electrode that estimates the probability of active corrosion