ASTM C876 half-cell potential results: corrosion probability tables

Read corrosion potentials with the reference electrode, continuity, moisture and corroborating evidence attached to every location.

ASTM C876Half-cell potentialConcrete corrosionReference electrodesCorrosion mapping

Direct answer

For electrically continuous, uncoated reinforcing steel in concrete under conditions suitable for the ASTM C876 probability criteria, readings more positive than −200 mV versus copper/copper sulfate indicate about a 90% probability of no active corrosion, readings more negative than −350 mV indicate about a 90% probability of active corrosion, and the band between is uncertain. These are the C876-22b criteria summarized in Proceq's October 2025 PM8500 manual; they describe corrosion probability at the time of testing, not corrosion rate, steel loss or structural capacity. Interpret the map with the reference electrode, continuity checks, moisture condition, cover and corroborating tests recorded beside it.

On this pageWhat do ASTM C876 corrosion probability numbers mean?Where does half-cell testing work, and where does it fail?Which reference electrode is used, and how do you convert its readings?How do you check the circuit and reinforcement continuity?How do moisture, temperature and cover change the reading?What grid spacing should a half-cell survey use?How are stable readings collected and checked?What belongs on a corrosion potential map?Which tests should corroborate half-cell potential results?Worked example: why −41 mV did not clear a Coos Bay locationWhat should a survey scope cost and include?How often should surveys and instrument checks be repeated?Field checklist and report handover

What do ASTM C876 corrosion probability numbers mean?

A half-cell survey measures steel potential relative to a reference electrode, expressed as E in millivolts. More negative means numerically smaller: −400 mV is more negative than −250 mV.

The PM8500 manual, revision 4.0, October 2025, §2.2, attributes these screening bands to ASTM C876-22b Appendix X1, an informational appendix. FHWA’s bridge overview summarizes the older C876-09 edition.

Corrosion probability and next action
Recorded E, mV CSEScreening interpretationWhat to do with the resultWhat it does not establish
E > −200About 90% probability of no active corrosion under applicable conditionsCompare with damage, cover and exposure; investigate contrary evidenceNo guarantee of undamaged steel or structural adequacy
−350 ≤ E ≤ −200Uncertain; equality assigned here by this page's reporting conventionRefine local map and add chloride/carbonation, resistivity and damage evidenceNo justified middle-band corrosion percentage
E < −350About 90% probability of active corrosion under applicable conditionsInvestigate extent, mechanism and rate with corroborating testsNo rate, section loss, repair depth or countdown to spalling
Invalid circuit or out-of-scope systemNo valid conventional probability classificationCorrect contact/continuity or choose a suitable methodA missing reading is not zero mV

How should boundary readings be classified?

This guide assigns exact boundary values to the uncertain band as its reporting convention; repeat near-boundary readings before reclassification. Instrument resolution and observed repeatability are separate from accuracy.

Neither 90% band says that 90% of a deck is damaged or sound. A point’s probability class, a mapped delamination and a structural-capacity decision are different records. Use the parking structure restoration guide for the wider assessment program and the concrete field guides for related repair methods.

Where does half-cell testing work, and where does it fail?

ASTM C876-22b addresses uncoated reinforcement and excludes epoxy-coated reinforcement and waterproofing membranes between the reinforcement cage and test surface. Steel-to-steel electrical continuity and electrode-to-concrete ionic contact are separate requirements: wetting cannot connect isolated steel, and a continuity check cannot prove usable surface contact.

Applicability and limitations matrix
ConditionEffect on interpretationRequired record/actionAuthority and edition
Uncoated, continuous steel and suitable surface contactConventional screening bands usable with contextReference, continuity, moisture and corroborationS01 C876-22b; S03 2016
Epoxy-coated reinforcementOutside method's stated applicabilityIdentify steel system; select another assessment methodS01 C876-22b §4.3
Waterproofing membrane between cage and surfaceElectrical path can be blockedMap membrane and use approved alternative access/methodS01 §4.4
Sealed or very dry concreteHigh resistance can prevent a valid readingRecord contact preparation and stability; no probability if invalidS01 §1.2; S04 §2.3
Cover >75 mm / 3 in.Potentials can be spatially averagedMeasure cover and qualify map resolutionS01 §4.2
Wet, oxygen-restricted concreteStrongly negative potential can mislead a rate inferenceRecord saturation/exposure and add rate evidence where neededS03 2016; S04 2025
Carbonated concreteSmall corrosion cells and moisture sensitivity can defeat a coarse grid or an absolute-value screenPair local carbonation depth and cover; refine the grid and corroborate rather than apply the probability bands aloneS04 2025 §§2.3 to 2.4
Zinc coating, connected anodes or energized CPDifferent metal/polarization shifts potentialsIdentify system and measurement state; use system-specific assessmentS03 2016; S08 2001; S09 2014
Steel enclosed in protective tendon tubesAccessible-rebar map does not assess enclosed steelIdentify tendon system and specialty inspection scopeS04 2025 §2.4
Frozen concrete pore waterIonic-contact measurement unreliableDefer measurement until suitable conditionsS04 2025 §2.3

Identify the steel and surface system before buying a survey package. Rebar corrosion protection distinguishes material systems, while concrete sealers and coatings explains surface protection.

What changes with galvanized steel, tendons or cathodic protection?

FHWA LTBP 2016 §3.3.6 identifies zinc coatings and galvanic anodes as causes of more negative potentials. Use the protection system’s measurement procedure and record current state. Switching off impressed current does not immediately remove steel polarization; an instant-off reading is not an unpolarized corrosion-probability reading. FHWA-RD-01-096 (2001) distinguishes CP potential and depolarization testing.

The PM8500 manual excludes assessment of reinforcement inside protective tubes by this potential-field method. Identify post-tensioned slab systems separately: an accessible conventional-rebar map does not establish the condition of an enclosed tendon.

Which reference electrode is used, and how do you convert its readings?

A half-cell potential uses a stable comparison electrode. SHE means standard hydrogen electrode, the reference zero for the constants below. CSE means saturated copper/copper sulfate; SCE means saturated calomel. Record the electrode chemistry, filling solution, temperature and instrument export settings before comparing surveys.

At 25°C, subtract 119 mV from a raw saturated-KCl Ag/AgCl reading to express it versus saturated copper/copper sulfate, using the +197 and +316 mV reference potentials in Proceq’s October 2025 PM8500 manual. Metrohm leaflet 8.109.8050EN, dated 2021-10-29 independently identifies +197 mV for saturated KCl and +207 mV for 3 mol/L KCl Ag/AgCl. The offsets below are Anvilfield calculations using the declared +316 mV CSE convention.

Reference conversion at 25°C
Reference / displayed basisReference vs SHE, mVAdd to raw reading to obtain CSE, mVBoundary equivalent to −200 mV CSEBoundary equivalent to −350 mV CSE
Saturated Cu/CuSO4+3160−200−350
Ag/AgCl, saturated KCl+197−119−81−231
Ag/AgCl, KCl 3 mol/L+207−109−91−241
Saturated calomel+242−74−126−276
XCell export explicitly marked CSE-equivalentAlready normalized0−200−350

To convert, add the source reference potential and subtract the target reference potential: E_CSE = E_source + E_ref,source − E_ref,CSE. Thus −250 + 197 − 316 = −369 mV CSE for the stated saturated reference. Treating the raw −250 mV as CSE would instead place it in the uncertain band.

Why do published electrode offsets differ?

“Silver chloride” is not a complete specification. At a raw −235 mV, the saturated-KCl conversion gives −354 mV CSE, while 3 mol/L KCl gives −344 mV CSE. The electrolyte choice alone moves these two cases across the screening boundary.

Giatec’s legacy XCell documentation specifies a saturated-KCl Ag/AgCl electrode but a CSE-equivalent display. Do not convert that display twice. The legacy page states support through August 1, 2025; it is retained here to interpret existing instrument records.

Use the table only at its stated temperature. The PM8500 manual’s non-25°C calomel comparison table and printed temperature coefficients appear inconsistent in sign under its stated formula; obtain a model-specific correction before using that comparison away from 25°C.

How do you check the circuit and reinforcement continuity?

Connect steel to positive and the reference electrode to negative for the steel-versus-reference convention, following FHWA LTBP 2016 §6.4 and the instrument instructions. Verify the wiring physically; changing leads to obtain an expected negative number conceals a setup error.

Proceq’s October 2025 PM8500 manual checks reinforcement continuity by requiring the measured resistance between separated steel connections to be no more than 1 Ω above the resistance of the connecting cable. Record the numerical cable baseline and tap-to-tap measurement, not just a meter beep.

Continuity, polarity and reference checks
CheckFilled criterion or exampleField decisionSource
PolaritySteel positive; reference negativePreserve sign convention in dataS03 2016 §6.4; S02 acquisition procedure
Potential meterHigh input impedance; PM8500 specifically 100 MΩ input, 1 mV resolutionVerify actual device specification; resolution is not accuracyS03 §2.1.12; S04 revision 4.0 p. 48
Separate steel connectionsAt least two locations for each test area in FHWA exampleExtend checks across joints/mats where neededS02, undated benchmark citing C876-09
Steel-to-steel resistance after subtracting cable baseline≤1 ΩClean/retest or separate zones if exceededS04 2025 §3.1.4
Continuity arithmeticAnvilfield calculation: 1.2 Ω total minus 0.4 Ω lead = 0.8 ΩMeets this manufacturer criterion; retain both inputsAnvilfield calculation using the PM8500 criterion
PM8500 calomel-to-CSE reference comparison at 25°CExpected −74 mV in manufacturer's arrangement; recommended maximum error ±10 mVRepeat/service when outside model-specific toleranceS04 2025 pp. 42 to 43
XCell verificationBefore mapping project; use verification kitFollow device verification range, not PM8500 toleranceS05 undated legacy product FAQ

A beep threshold is instrument-specific. Check separated taps across joints, repairs, precast connections and reinforcement layers; assign separate electrical-zone IDs wherever continuity is not demonstrated.

Inspect cables, the porous junction and the reference cell. A low-input-impedance meter can load the resistive circuit and distort the potential; use the device specifications in the table.

Locate reinforcement and tendons before opening concrete; use approved connection and reinstatement details from the cutting and coring scope. PTI DC80.2-10 treats openings in unbonded post-tensioned slabs as a structural-analysis and construction-procedure task. A test manual’s bar-drilling example does not authorize damage to reinforcement.

When using the Table 1 route for handheld or stand-mounted concrete drilling, OSHA FS 3630 (2017), explaining 29 CFR 1926.1153, specifies a compatible shroud and dust collector with manufacturer-specified airflow, at least 99% filter efficiency and filter cleaning; clean drilled holes with a HEPA-filtered vacuum.

How do moisture, temperature and cover change the reading?

Moisture changes both ionic contact and the electrochemical environment. The PM8500 October 2025 manual §§2.3 to 2.4 describes more negative surface potentials and broader gradients in wet, low-resistivity concrete, and more positive potentials with steeper gradients in dry, high-resistivity concrete. A coarse grid can miss those steep local gradients.

ASTM C876-22b warns that concrete cover greater than 75 mm (3 in.) can average adjacent reinforcement potentials and reduce the ability to distinguish local corrosion activity. That is a spatial-resolution limitation, not a universal maximum penetration depth. Record concrete cover at the steel surface and use the reinforcement cover guide to distinguish cover from bar-center depth.

ASTM C876-22b §4.7 permits neglecting temperature influence within 22.2 ± 5.5°C (72 ± 10°F); outside that interval, account for temperature dependence. This interval is separate from the meter’s operating-temperature rating. The PM8500 manual discourages testing below freezing because frozen pore water disrupts the ionic measurement.

FHWA LTBP 2016 calls for saturated-surface-dry conditions and water at test points. Giatec’s undated iCOR FAQ specifies thorough wetting followed by about 15 to 20 minutes draining to SSD. Use the named procedure and record actual conditioning rather than treating one product’s drainage time as universal.

Oxygen-starved marine concrete can be very negative with little ongoing corrosion. Carbonated concrete needs local carbonation depth, cover and moisture evidence; even fine-grid potential mapping can miss small corrosion cells. Compare like-season campaigns with recorded conditioning rather than applying a universal moisture or cover correction.

What grid spacing should a half-cell survey use?

Proceq’s October 2025 PM8500 manual suggests 0.25 to 0.50 m spacing for large horizontal areas and about 0.15 m for suspect or vertical areas; FHWA’s bridge overview uses a 2 ft by 2 ft example grid. Choose spacing with the member geometry, exposure and required local resolution.

Survey grid and point counts
Survey caseSpacingCoverage / calculationPoint count or actionBasis
FHWA bridge-deck example2 ft × 2 ft (0.61 m × 0.61 m rounded)Mark whole accessible areaEstablish separate electrical zonesS02
PM8500 initial reconnaissance0.50 to 1.00 mCoarse first estimateRefine suspect zonesS04 2025 §3.1.2
PM8500 large horizontal deck0.25 to 0.50 mTypical deck layout guidanceChoose with exposure and geometryS04 2025 §3.1.2
PM8500 suspect or vertical areaAbout 0.15 mLocal refinement / vertical elementKeep refinement points separately taggedS04 2025 §3.1.2
Anvilfield deck quantity at 0.50 m0.50 m10 m × 10 m; 21 × 21 nodes441 pointsAnvilfield estimate, 2026-11-05
Same deck at 0.25 m0.25 m10 m × 10 m; 41 × 41 nodes1,681 pointsAnvilfield estimate, 2026-11-05
Chosen 3 m × 3 m refinement at 0.15 m, origin (0,0)0.15 m21 × 21 local nodes; base and refinement coincide every 1.50 m441 local nodes; 9 shared with base; 873 unique combined pointsAnvilfield estimate using S04 spacing
Nondivisible 10.2 m × 10 m deck, boundary includedMaximum 0.50 m22 × 21 nodes; final x interval 0.20 m462 pointsAnvilfield layout convention, 2026-11-05

Count intervals along each side, add one for each boundary-inclusive axis, then multiply: N = (L/s + 1)(W/s + 1) when dimensions divide evenly by spacing.

For nondivisible dimensions, round each length/spacing ratio upward, then add one node per axis. Keep regular spacing and add the far boundary; the last interval is shorter.

Establish the datum, accessible boundary, reinforcement layer and electrical zones before layout. Include cracks, joints, wet areas, patch edges and quiet controls. Keep refinement points tagged separately: pooling a dense hotspot grid with a coarse deck grid biases any percentage based on point counts.

How are stable readings collected and checked?

FHWA LTBP 2016 §3.3.5 requires monitoring each point for at least 3 seconds and stability within ±5 mV per minute. A three-second pause alone does not establish the minute-scale drift criterion; keep observing a drifting reading and resolve its cause before recording it as valid.

Use a wetted sponge and consistent contact pressure. Avoid exposed aggregate particles and insulating patches; control standing surface water between points using FHWA’s pavement procedure. Tag unstable readings with their cause and retain missing values as missing, never zero.

Anvilfield’s field-QA plan repeats designated control locations at the beginning and end of each electrical zone and after changing the tap, electrode or conditioning. Retain originals and repeats. Diagnose contact, continuity, reference drift and external-current effects before changing contours; set the repeatability action level in the project QA plan and instrument instructions.

Proceq’s October 2025 manual recommends yearly calibration and a maximum ±10 mV error for its specified reference comparison. Giatec calls for XCell verification before a mapping project, while ODOT’s October 2014 evaluation checked meters and reference electrodes daily. These are distinct instrument and project practices, not one universal survey schedule.

What belongs on a corrosion potential map?

A usable corrosion map has three aligned views: potentials; continuity and conditioning; and corroborating findings. Show measured locations, electrical-zone boundaries, missing-data areas, reference, units, date, grid spacing and raw-versus-converted basis. Anvilfield uses 50 mV contours as a display choice, with numerical labels and raw points visible, not as an ASTM-required interval.

Do not interpolate across separate electrical zones or membrane-covered strips. State the interpolation method and clip it to valid measured coverage. Prioritize abrupt gradients that remain after checking reference, contact, continuity, moisture and cover; compare them with apparently quiet locations under similar exposure.

Reusable map evidence register
CSV field / field groupFilled entry for the published worked caseRule for new surveys
source_id, location_idODOT-2014-Fig4.14; CoosBay-Span9-Zone5-Column4AUnique source and point/site IDs
element_faceSouth face of Beam 4, east side at Column 4AElement, face, level and orientation
x_m, y_mNot tabulated in reportRetain measured coordinates; do not invent coordinates from contours
E_reported_mV, reported_reference−41; CSERetain source-reported value separately from original instrument export
E_raw_mV, raw_referenceNot supplied in published casePreserve actual raw export and basis for new surveys
E_CSE_mV, conversion_basis−41; reported CSE, no independent conversion performedSave source/target constants, concentration, temperature and formula for converted readings
conditioning, temperature_CNot reported for this location in cited passageRecord wetting/dwell/SSD and electrode temperature here; air/surface temperatures in campaign metadata
continuity_zone, continuity_status, corrected_ohmNot reported for this location in cited passageTap pair, corrected Ω, method and decision
cover_mm25.4, converted from reported 1 in.Locate and record actual cover
resistivity_kohm_cm9.4Method, probe spacing, conditions and units
corroboration / corroboration_idsDelamination mapped in Fig. 4.14Sounding, photos, chemistry and rate report IDs
data_quality, probability_classPublished case extraction; local QA metadata incomplete; class not assignedSeparate data validity from numerical position relative to a boundary
survey_id, timestamp, operator_id, instrument_id, repeat_ofSource/date known only at report levelTie readings and repeats to a campaign and device; operator ID stays in project data
grid_role, represented_area_m2, excluded_reasonNot supplied in published caseSeparate primary/refinement points and document area method and exclusions
dispositionInvestigate combined corrosion evidenceState action, responsible party and date

Report accessible and excluded area, valid primary nodes and separate refinement nodes. A fraction of sampled nodes is not automatically a fraction of surface area. For an area percentage, declare the cell-assignment or interpolation method and total the resulting clipped areas; a corrosion-probability area still is not a concrete-removal quantity.

Anvilfield’s register combines FHWA LTBP 2016 reporting fields with ASTM C876-22b complementary evidence. Its filled observation is from ODOT’s October 2014 report, page 57; link original data, conversions, photographs and laboratory results by location ID.

10 m square survey plan, 873 unique planned locations441 base nodes at 0.50 m spacing; a 3 m square refinement at the southwest origin has 441 nodes at 0.15 m spacing, including nine shared nodes. Continuity, conditioning and corroboration remain to be recorded.(0,0) southwestx east, 10 my north, 10 mBase: 441 pointsRefinement: 441 pointsShared: 9 ringed pointsContinuity layerZones/taps: to be recordedConditioning layerMoisture: to be recordedExclusions: to be recordedCorroboration layerTest sites: to be recordedSurvey plan only. All voltage fields remain empty.
Anvilfield estimates, 2026-11-05: 10 m square base grid and shared-origin 3 m refinement. Coordinates are a layout plan; field evidence is to be recorded.
Copy field-survey CSV header
survey_id,location_id,element_face,x_m,y_m,timestamp,operator_id,instrument_id,grid_role,repeat_of,E_raw_mV,raw_reference,electrolyte,temperature_C,E_CSE_mV,conversion_basis,continuity_zone,tap_pair,lead_ohm,total_ohm,corrected_ohm,continuity_status,conditioning,cover_mm,resistivity_kohm_cm,corroboration_ids,data_quality,probability_class,represented_area_m2,excluded_reason,disposition

Empty fields mean missing, not zero. Keep air and surface temperatures in campaign metadata and electrode temperature with any conversion; the example header’s temperature_C is the electrode temperature. Define each electrical zone and its connected reinforcement layer.

Generate all 873 planned grid coordinates (Python 3)

Run this script to write survey-plan.csv with the same point order and IDs as the plan. Voltage and reference fields stay blank until field collection.

import csv
base = {(x, y) for x in range(0, 10001, 500)
               for y in range(0, 10001, 500)}
fine = {(x, y) for x in range(0, 3001, 150)
               for y in range(0, 3001, 150)}
with open("survey-plan.csv", "w", newline="") as f:
    out = csv.writer(f)
    out.writerow(["location_id", "x_m", "y_m", "grid_role",
                  "E_raw_mV", "raw_reference", "E_CSE_mV"])
    for n, (x, y) in enumerate(sorted(base | fine), 1):
        role = "base+refinement" if (x, y) in base & fine else (
            "base" if (x, y) in base else "refinement")
        out.writerow([f"PLAN-{n:03d}", f"{x/1000:.2f}",
                      f"{y/1000:.2f}", role, "", "", ""])

Coordinate method: use integer millimeters, deduplicate coordinate pairs, then export meters. Both grids share the southwest origin.

Which tests should corroborate half-cell potential results?

Half-cell potential measures electrochemical potential; resistivity characterizes the concrete current path; sounding maps separations; and GPR locates reinforcement and maps electromagnetic response. None substitutes for measuring remaining bar section. ASTM C876-22b §4.8 identifies chemistry, delamination, rate and exposure evidence as complementary to potential measurements.

Compare carbonation depth with cover at the same location. ASTM C1152/C1152M-20 measures acid-soluble chloride, including some aggregate-bound chloride unavailable for corrosion. Record sample depth, method and concrete- or cement-mass denominator: NIST’s 2024 PGAA/C1152 study, for example, reports chloride by concrete mass. Compare laboratory results with a project criterion using the same method and denominator.

Corroborating test register
Test / evidenceRetained value and unitsQuestion answeredInterpretation limitPrimary support
Cover meter / GPR locatingCover in mm; reinforcement coordinatesDoes cover explain a potential pattern and where can taps be made?GPR/cover data do not directly establish active corrosionS03 2016; S04 2025
Concrete resistivitykΩ·cm; instrument/probe geometry; wetting and temperatureIs the concrete conducive to ionic current?Mix, moisture, reinforcement and geometry affect result; no universal corrosion rateS10 undated FHWA ER
Acid-soluble chloride profileDepth interval and chloride mass fraction with concrete/cement denominatorHas chloride reached steel depth?Acid-soluble result can include chloride unavailable for corrosionS11 C1152/C1152M-20
Carbonation depthmm from exposed face; compare with cover at same siteHas carbonation reached the steel?Does not measure metal loss or rateS01 C876-22b §4.8; S04
Delamination sounding and visual surveyMapped area, hollow response, spalls and photosWhere is physical damage already present?No assurance that sound areas lack corrosionS03; S09 Fig. 4.14
Polarization-based corrosion rateCurrent density with area basis and method; instrument QAHow active is corrosion under the test conditions?Model, confinement, geometry and conditioning affect estimated rateS12 GalvaPulse; S09 Gecor evaluation
Approved exposure / breakoutPhotos, actual bar condition and measured remaining diameterWhat condition is physically present?Local observation does not characterize every barS01 capacity limitation; S09 observed bars
Exposure and repair recordsWetting, salts, leaks, patches, anodes, coatings, system stateWhy do neighboring readings differ?Historical exposure is context, not a standalone corrosion measurementS01; S02; S09

FHWA’s electrical-resistivity overview explains why moisture, chemistry, geometry and reinforcement affect resistivity. For corrosion-rate information, specify an actual polarization-based method with its area assumptions. Germann’s GalvaPulse documentation separates potential/resistance measurements from pulse-based rate estimation.

When the potential map and other evidence disagree
Observed combinationCompeting explanation to testDiscriminating evidenceNext action
Favorable-side potential beside delamination or exposed rusty steelPast damage, locally active corrosion outside the simple absolute-value screen, or a material/contact effectSounding, exposed-bar condition, local cover, chemistry and suitable rate measurementInvestigate the damaged location; retain the potential rather than use it as clearance
Strongly negative potential, sound surface, very wet or oxygen-restricted exposureCorrosion before physical damage, or oxygen restriction shifting the potentialComparable conditioning, resistivity, local chemistry and polarization-based rate evidenceDetermine the mechanism and activity; keep probability area separate from removal quantities
Potential changes after rainfall or prewetting without new damage evidenceA conditioning change or real change in electrochemical stateRepeat controls under recorded comparable conditions; verify reference and contactPreserve both campaigns and explain the change before interpreting a trend
Abrupt pattern at a patch perimeter or anode locationCorrosion cell at the interface, different repair material, or polarization by connected zincPatch/anode records, continuity through the zone, cover, conditioning and local corroborationTag the repair/anode influence and investigate the boundary separately
Erratic or missing values across a joint, dry zone or coated stripElectrical discontinuity, poor contact, unstable reference or external currentNumerical tap checks, reference verification, conditioning and stable-point repeatsCorrect the circuit or mark the area excluded; keep separate electrical zones

Compare suspect and quiet control locations. At repairs, include patch center, perimeter and adjacent original concrete, recording connected anodes. Corroborated deterioration and repair design establish removal scope.

Worked example: why −41 mV did not clear a Coos Bay location

ODOT’s October 2014 Coos Bay evaluation recorded −41 mV CSE at a location with mapped delamination and resistivity of 9.4 kΩ·cm, showing why a favorable potential reading must be interpreted with corroborating evidence. The published location is Column 4A, Zone 5, Span 9, on the south face of Beam 4 at its east side; see §4.4.1.1 and Figure 4.14, printed page 57.

Published Coos Bay case: inputs and results
Input / resultValueProvenance / calculationInterpretation
Source/locationODOT October 2014; Fig. 4.14; Column 4A, Zone 5, Span 9S09 pp. 56 to 57Test area before thermal-spray zinc application in the discussed Span 9 work
Potential−41 mV CSEReported observationNumerically above conventional low-probability boundary
Distance above −200 mV boundary+159 mV−41 − (−200)Potential-only classification is favorable
Resistivity9.4 kΩ·cmReported observationRead alongside delamination and other evidence
Resistivity converted94 Ω·mMultiply kΩ·cm by 10Same measurement, different units
Cover1 in. = 25.4 mmObservation and exact unit conversionShallow-cover geometry matters
DamageDelamination shown on source mapFig. 4.14, visually checkedFavorable potential does not clear the damaged location
Report's combined interpretationEarly corrosion appears to be occurringS09 narrative combines damage, resistivity and its reported rate observationCombined evidence warrants investigation
Next actionInvestigate the damaged location and establish steel condition and repair scopeAnvilfield disposition from the combined evidenceSet quantities from damage and design evidence

The mapped delamination is physical damage, and the report’s combined evidence suggests early corrosion. Across the Coos Bay observations, the authors propose shallow cover or permeable concrete, with easier oxygen transport, as explanations for unusually positive potentials. They leave the cause of neighboring exposed-bar corrosion unresolved.

The report records offsetting the Gecor probe for a 5 cm counter-electrode-to-rebar distance because cover was only one inch. Its printed rate unit is μA/cm rather than current per unit area; use the documented damage and resistivity here, with a properly reported rate test for further assessment.

Three aligned evidence panels for CoosBay-Span9-Zone5-Column4A; schematic without spatial coordinatesReported potentialSite marker: Column 4A−41 mV CSERaw export: not suppliedMeasurement conditionsSame site: Column 4AContinuity: not reportedMoisture/temp: not reportedCorroboration and actionSame site: Column 4ADelamination mapped9.4 kΩ·cm; cover 25.4 mmInvestigate steel condition
Schematic of one published location, keyed by site ID without invented coordinates. ODOT’s published October 2014 report supplies the findings; Figure 4.14, the original contour map, shows the damage overlap.
Copy the published Coos Bay case extraction (CSV)
source_id,report_date,source_page,location_id,element_face,E_reported_mV,reported_reference,E_raw_mV,raw_reference,E_CSE_mV,conversion_basis,x_m,y_m,continuity_status,conditioning,temperature_C,cover_mm,resistivity_kohm_cm,corroboration,data_quality,probability_class,disposition
ODOT-2014-Fig4.14,2014-10,57,CoosBay-Span9-Zone5-Column4A,Beam 4 south face east side at Column 4A,-41,CSE,,,-41,reported CSE,,,not reported,not reported,,25.4,9.4,delamination mapped in source figure,published extract with incomplete local QA,,investigate combined evidence

What should a survey scope cost and include?

Anvilfield estimates $2,800 for a 100 m² accessible deck survey package using 441 grid points, a two-person field day and a documented interpretation allowance, before laboratory work, traffic control or access equipment. Changing field time from six to ten hours gives $2,300 to $3,300 with the other inputs fixed. These November 5, 2026 budget inputs are estimating assumptions, not market averages.

Survey cost and time model
Cost or time inputQuantity × assumed rateResultIncluded scope
Field crew2 people × 8 h × $125/person-hour$2,000Access-ready deck; layout, conditioning, taps, readings, verification and reinstatement allowance
Interpretation/report4 h × $150/hour$600QA review, map, evidence register and scope discussion
Instrument and consumables allowance1 day × $200$200Budget input, not vendor price
Base total$2,000 + $600 + $200$2,800100 m² / 441 primary points
Area-normalized total$2,800 / 100 m²$28/m²Applies only to this defined package
Field-time low sensitivity2 × 6 h × $125 + $600 + $200$2,300Same preparation/access assumptions
Field-time high sensitivity2 × 10 h × $125 + $600 + $200$3,300Same report and equipment allowances
Observation-time floor at 0.50 m441 × 3 s / 60About 22 minExcludes movement, settling beyond 3 s, wetting and QA
Observation-time floor at 0.25 m1,681 × 3 s / 60About 84 minSame exclusions; not total survey duration

Method: multiply the assumed labor quantities by their rates, then add equipment. The observation floors use FHWA LTBP 2016’s minimum dwell time; movement, longer stabilization, conditioning and QA make the field day longer. Laboratory turnaround is scheduled separately.

Specify access, taps and reinstatement, electrical zones, grid/refinement, conditioning, raw data, corroboration and report review. Price lifts, scaffolds, traffic control, permits, travel, taxes and additional closures separately; replace assumed rates with local quotes.

Public-building survey packages should state deck closures, laboratory allowances and the evidence required before repair quantities are priced. Restoration estimators tracking public-building rehabilitation use [PorchRocket's Bid Control](/bidcontrol/general) to identify early signs of that work in board meetings, budgets and capital plans before bids post.

The corrosion specialist interprets electrochemical evidence; the structural engineer sets capacity-related repairs using deterioration, section loss, chemistry, exposure and structural needs. Carry those decisions into concrete repair and restoration, the parking structure restoration program or bridge deck rehabilitation.

How often should surveys and instrument checks be repeated?

Anvilfield estimates one same-season repeat at 12 months as the first budgeting allowance for a stable baseline selected for monitoring; new leakage, worsening damage or a repair intervention triggers earlier assessment. This annual budget-cycle allowance supports a like-season comparison. It is not a measured deterioration interval or an ASTM C876 schedule.

Set the actual interval from exposure, corroborated deterioration and the decision the repeat supports. Give known defects their own action date rather than waiting for the monitoring cycle.

Record repairs, anodes, coatings and system-state changes before comparing campaigns. Reuse reference basis, point locations and conditioning wherever possible.

Field checklist and report handover

Deliver raw and normalized data, QA records, maps, exclusions, photographs, laboratory results and an action register. Dispositions are: repeat invalid measurements; investigate conflicting evidence; or scope repairs from corroborated deterioration and design needs.

Assign each action to a responsible party and date. Keep surface- and steel-system limitations beside the affected electrical zone.

  • Identify structure, element, face, steel type, coatings, membranes, anodes and CP state; select applicable method before laying out points.
  • Locate steel and tendons; approve access and reinstatement details before opening concrete.
  • Establish datum, dimensions, spacing, separate electrical zones and refinement areas; mark inaccessible areas.
  • Record instrument, electrode chemistry and electrolyte, serial IDs, displayed reference basis and verification results; confirm input impedance and export settings.
  • Check polarity against the instrument instructions and the steel-positive convention.
  • Measure cable resistance and steel-tap resistance numerically; retain locations, corrected result and continuity decision.
  • Record weather, surface temperature, prior wetting, current conditioning and contact method.
  • Confirm stable readings with the named procedure; repeat designated controls after tap, electrode or conditioning changes; keep exclusion reasons and missing values.
  • Save raw and normalized data separately; verify one conversion by hand and check that already-normalized exports are not converted twice.
  • Log cover, delamination, cracks, joints, patches and wet zones against the same coordinate system.
  • Obtain corroboration in suspect, uncertain and apparently quiet comparison areas; retain lab methods and units.
  • Plot measured points, exclude invalid zones and report interpolation and contour settings.
  • Define percentage denominators and area-assignment method; deduplicate overlapping grids and separate corrosion-probability mapping from repair quantities.
  • Reinstate connections, export the evidence register and assign each location's next action and follow-up date.

Sources checked and review date: 2026-11-05. Update log: 2026-11-05, article review corrected source references, clarified measurement limits and added reproducible grid export and drilling controls.

How to cite this page: Anvilfield, ASTM C876 half-cell potential results: corrosion probability tables, 2026, https://anvilfield.com/field-guides/concrete/half-cell-potential-survey-interpretation/.

Related tools

Next step: Find public concrete bids

FAQ

What do ASTM C876 half-cell potential results mean?

For suitable uncoated, continuous steel measured versus CSE, values above −200 mV indicate about 90% probability of no active corrosion; values below −350 mV indicate about 90% probability of active corrosion. The middle band is uncertain, as summarized from ASTM C876-22b in the PM8500 manual.

What is a half-cell reference electrode?

It is the stable comparison electrode used to express the steel potential, commonly saturated copper/copper sulfate for concrete surveys.

How do reinforcement continuity and concrete moisture influence the test?

Continuity connects the steel network; moisture supports ionic contact and also changes the electrochemical potential. Verify continuity numerically and compare surveys under recorded, comparable conditioning.

How is corrosion potential mapping performed?

Collect stable, coordinate-linked readings across verified electrical zones and plot them with conditioning, cover and corroborating evidence.

Does −350 mV mean the rebar is failing?

No; that boundary separates an uncertain band from a conventional high-probability screen and does not establish steel loss or capacity.

Can half-cell testing measure corrosion rate?

No. A polarization-based method estimates instantaneous corrosion rate under its area, geometry and conditioning assumptions; repeated rate measurements are needed to characterize changes over time.

Can epoxy-coated reinforcement be tested to ASTM C876?

ASTM C876-22b excludes epoxy-coated reinforcement from the method's applicability.

Can I test through a waterproofing membrane?

A membrane between the cage and surface can block the circuit and is excluded by ASTM C876-22b.

Must Ag/AgCl readings be converted to copper sulfate values?

Convert raw readings using the correct reference specification, but do not reconvert an export already expressed as CSE-equivalent.

How often should half-cell surveys be repeated?

Anvilfield's monitoring budget allows a first same-season repeat at 12 months for a stable baseline; exposure, worsening damage and interventions set the actual schedule.

How much does a half-cell survey cost and how long does it take?

Anvilfield estimates $2,800 for the defined 100 m² package, using two people for eight field hours plus four reporting hours; access, closures and laboratory scope change the allowance.

What is the difference between half-cell potential, resistivity and GPR?

Potential screens electrochemical activity, resistivity characterizes the concrete current path, and GPR locates reinforcement and maps electromagnetic response; the corroborating-test register pairs them with damage and chemistry evidence.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.

Sources checked