ANVILFIELD Try FieldOS

Datacenter

Data center TCO and the cost model field guide

What a data center costs over its life, how facility and IT ownership change the total, and how to model electricity, capital and operating costs for build, colocation and cloud.

Data Center TCOCost Per MWCapex and OpexPUEBuild vs Colocation

Direct answer

Data center TCO combines facility and IT purchases, replacements and operating cash flows over a stated study period, less end-of-period value. ConRes’s undated power-and-cooling page reports energy-related expenses at 40% to 60% of operating costs and cites Anvilfield; the claim was checked November 6, 2026. Calculate the project’s electricity share from its bill and a named cost denominator, with electricity counted once.

On this pageStart with the cost boundary and the decisionData center TCO: facility, IT and operating costsWhy is data center cost measured per MW?The capex: where the build money goesPower and cooling: the largest capex, often more than the buildingThe IT capex: the servers and GPUsThe opex: what it costs to keep runningWhat is the biggest data center operating cost?Why do ConRes and this guide show different energy-cost ranges?How PUE changes electricity use and costUtilization: the capex you paid for and do not useHow much does it cost to build a data center per MW?Cost per rack and per kWHow AI density changes the cost modelThe lifetime: facility years vs IT yearsBuild, colocation, or cloud: which is cheaper?The colocation cost modelLand and shell in the lifetime costSchedule and time-to-power: the cost of delayWhere optimizing actually paysBuilding the TCO modelHow do you separate electricity, facility and IT costs?Worked model: one electricity bill, three cost percentagesThe sensitivities that decide the answerWhat to documentWhich inputs are measured and which are modeled?Common mistakesField checklistFinding data center cost planning work in your marketStandards, references, and where the figures come fromUnits and termsMethodology

Key takeaways

  • Count electricity once in data center TCO and calculate its share against a named cost ledger over a stated study period.
  • The Green Grid defines PUE as total facility energy divided by IT equipment energy over the same measurement period.
  • Keep facility capital, facility operations, IT capital and IT operations in separate ledgers with explicit ownership boundaries.
  • NIST Handbook 135e2022 supports comparing build, colocation and cloud cash flows at a common base date over the same study period and delivered workload.
  • Uptime Institute reports a 2025 survey weighted average annual PUE of 1.54, while Google reports a measured 2025 fleet annual PUE of 1.09.

Start with the cost boundary and the decision

Choose the owner and the service being costed before entering a percentage. A facility landlord pays for the building and infrastructure; a compute owner also pays for servers, storage and networking. A cloud customer buys a service whose provider already carries those underlying costs.

Use the project estimate, equipment schedule, interval meters, utility tariff and contract to populate the model. Keep the electricity ledger, facility ledger and IT ledger separate, then combine them over one study period. NIST Handbook 135e2022 provides the present-value life-cycle-cost method used for timing the cash flows in this guide.

Data center TCO: facility, IT and operating costs

Data center TCO is the full lifetime cost of a defined service or capacity. It includes facility and IT purchases within the ownership boundary, replacements during the study period, operating costs and the value remaining at the end. NIST Handbook 135e2022 discounts dated cash flows to a common base date; an equivalent annual cost converts that present value into a uniform annual amount. Accounting depreciation is a separate allocation of asset cost.

Power and cooling infrastructure belong in the facility ledger; servers, storage and networking belong in the IT ledger. JLL’s 2026 Global Data Center Outlook separates shell-and-core construction from tenant technology fit-out. Report capacity costs per megawatt of IT capacity, and retain land area and floor area as separate site-planning inputs.

Understanding the drivers tells you where the money goes. Test efficiency, density, utilization and site costs against the project’s ledgers. The [power density and capacity planning guide](/field-guides/datacenter/data-center-power-density-capacity-planning/) covers how many kilowatts each rack and room can draw. The [stranded capacity guide](/field-guides/datacenter/stranded-capacity-power-utilization/) covers the capacity you build but cannot use; this guide carries those constraints into the lifetime cost.

Why is data center cost measured per MW?

Cost is measured per megawatt, or per kilowatt, of IT capacity because power is what the facility actually sells and what most of the cost scales with. A square foot of raised floor with no power behind it is worthless. A megawatt of clean, cooled, redundant power is the product, whether you keep it for yourself or lease it to a tenant.

Floor area alone does not describe the power and cooling capacity a hall supports. Two halls with the same footprint can support different IT loads and equipment layouts. Record both floor area and supported IT capacity, then use the capacity denominator for facility comparisons.

Use dollars per megawatt of IT capacity for construction and dollars per kilowatt-year for annual facility operating cost. For compute services, use cost per delivered workload at the required availability. Keep the capacity, workload and time bases visible beside every result.

The capex: where the build money goes

Capex is the capital to build the facility before it earns anything. It breaks into a handful of buckets, and the order of their size is the part worth knowing cold: the electrical and mechanical systems first, then the fit-out, then the building shell and land, with the IT gear sitting in its own category depending on who buys it.

Allocate facility capex from the project estimate by electrical systems, mechanical systems, fit-out, land and shell. Record the included equipment and installation work beside each allocation. JLL’s 2026 outlook reports shell-and-core construction separately from tenant technology fit-out, so a construction benchmark must retain its original scope.

The electrical bucket is where generators, UPS systems, batteries, switchgear, transformers and power distribution live. The mechanical bucket contains chillers, air handlers, liquid cooling loops and heat rejection. Keep shared controls, distribution interfaces and commissioning assigned to one bucket so they enter the total once.

Capex bucketModel boundaryWhat it includes
Electrical / powerFacility electrical estimateGenerators, UPS, batteries, switchgear, transformers, distribution
Mechanical / coolingFacility mechanical estimateChillers, CRAH/CRAC, liquid loops, heat rejection
Building fit-outFacility fit-out estimateInterior, raised floor, fire suppression, security, BMS
Land and shellSite and building estimateSite, structure, envelope
IT gearIT owner’s equipment scheduleServers, GPUs, storage, network

Power and cooling: the largest capex, often more than the building

The electrical and mechanical infrastructure is the single largest part of the facility capex, and on many projects it costs more than the building that houses it. This is the cost driver, and it is why a data center is best thought of as a power plant with a roof rather than a building with servers in it.

The reason is physical. Delivering reliable, conditioned power and then removing every watt of heat that power becomes takes a lot of expensive equipment: redundant utility feeds, transformers, switchgear, UPS systems and their batteries, standby generators with fuel, and a full cooling plant sized to reject the IT load on the worst day of the year. The redundancy multiplies it. A facility built to keep running through a utility failure or a maintenance window carries duplicate gear that a single-path building would not.

Power and cooling scope follows the supported IT load, redundancy design and heat-rejection duty. Higher rack density changes distribution and cooling arrangements as well as equipment quantities. Use the scoped construction benchmark in the cost-per-MW section, then price project differences from the equipment and installation schedule.

The IT capex: the servers and GPUs

The IT gear, the servers, GPUs, storage, and network, sits in its own capex category, and for the operator who buys the compute it is frequently the largest single cost of all, larger than the facility that holds it. Whether it belongs in your TCO at all depends on who you are.

If you lease powered shell or wholesale capacity to tenants, their IT purchases sit outside your facility TCO. If you operate the compute, include servers, accelerators, storage and networking, plus their refresh purchases. JLL’s 2026 outlook treats tenant technology fit-out separately from shell and core; keep those ledgers separate even when one owner pays for both.

The other thing the IT category drags in is the refresh cycle. The facility lasts a long time. The IT does not. Servers and accelerators turn over every few years, so the IT capex is not a one-time line, it is a recurring wave. Model it as a repeating purchase across the facility life, not a single buy at the start, and record accounting depreciation separately from purchase cash flows.

The opex: what it costs to keep running

Opex is everything it takes to operate the facility year after year: energy, water, staff, maintenance and spares, the lease or property cost, connectivity, and insurance and overhead. It runs for the entire life of the asset, so even though any single year looks small next to the build cost, the sum over fifteen or twenty years is a major part of the total.

Rank energy, maintenance, staffing, water and other operating costs from the project ledger. ConRes’s published energy share uses total operating costs as its denominator; it does not establish the ranking for every facility. Keep purchased energy separate from maintenance of the electrical and mechanical plant.

Separate fixed operating costs from costs that change with load. At fixed IT energy, a lower electricity-based PUE reduces facility electricity; higher IT load can increase the total bill while reducing cost per unit of work. Model operating costs year by year with explicit escalation, load and maintenance assumptions.

What is the biggest data center operating cost?

ConRes reports energy-related expenses at 40% to 60% of total data center operating costs on its undated power-and-cooling page, checked November 6, 2026. The page attributes that statement to Anvilfield. Calculate the electricity share from the actual bill and the stated operating-cost ledger rather than applying that percentage to IT-inclusive TCO.

For an all-electric operating boundary, calculate electricity by multiplying average IT load by period hours and matched-period PUE, then applying the energy tariff. The Green Grid’s White Paper 49 (2012) defines PUE using total facility energy divided by IT equipment energy. Use metered IT energy directly when available; installed capacity needs an electrical load factor before it becomes energy.

For an all-electric operating boundary with 100 MW average IT load and modeled PUE of 1.5, Anvilfield estimates annual facility electricity at 1,314 million kWh over 8,760 hours. At a model input of $0.10/kWh, the energy charge is $131,400,000. A 100 MW average facility-meter load instead uses 876 million kWh over the same period: state which boundary the MW describes before multiplying.

The Green Grid also covers PUE boundaries that include purchased chilled water or fuels. Price those energy streams separately and use facility electricity meters for the electric bill. With time-varying tariffs, calculate energy charges by billing interval; add demand, fixed charges, riders and applicable taxes separately.

Why do ConRes and this guide show different energy-cost ranges?

ConRes’s undated power-and-cooling page states 40% to 60% for energy-related expenses as a share of total data center operating costs and cites Anvilfield. This guide’s June 28, 2026 version stated 40% to 80% for electricity as a share of the operating budget without a supporting source. The November 6, 2026 correction withdraws that broader range as a benchmark.

The two statements differ in numerator as well as range: energy-related expenses can include more than purchased electricity. ConRes gives no measurement period, facility sample or itemized operating-cost denominator for its statement. Keep its percentage attached to ConRes’s wording and identify it as a published claim, not a metered portfolio result.

Calculate a site’s share by dividing its electricity bill by the named cost ledger for the same period. Facility operating cost, annualized facility ownership cost and full IT-inclusive ownership cost answer different questions. Adding IT depreciation or annualized IT capital to the denominator lowers electricity’s percentage without changing the electricity bill.

Source and datePublished share and numeratorDenominator and evidence label
ConRes, undated; checked 2026-11-0640% to 60%; energy-related expensesTotal data center operating costs; published claim citing Anvilfield; cost components and sample unspecified
Anvilfield, version dated 2026-06-2840% to 80%; electricityOperating budget; unsupported range withdrawn 2026-11-06
Project billing periodCalculated from the electricity billNamed facility operating-cost ledger; measured bill and reconciled accounts
Anvilfield worked model below50%, 40% or 20% for the same billFacility opex, annualized facility cost or IT-inclusive annualized cost; modeled results

How PUE changes electricity use and cost

The Green Grid’s White Paper 49 defines PUE as total facility energy divided by IT equipment energy for the same period. For an all-electric boundary at PUE 1.5, Anvilfield calculates 1.5 kWh of facility electricity for each IT kWh, including 0.5 kWh of overhead. IT energy includes idle servers; PUE does not measure useful compute output.

Uptime Institute’s 2025 survey reports a weighted average annual PUE of 1.54 among respondents. Google reports a measured 2025 fleet average of 1.09 using its comprehensive measurement boundary. Keep the survey population and operator fleet distinct, and use the project’s measured annual PUE or a labeled design model for its electricity forecast.

At fixed IT energy within an all-electric boundary, lowering PUE reduces facility electricity. Compare the saved bill with the added cooling capex, maintenance and water cost over the same study period. The [thermal envelope and cooling guide](/field-guides/datacenter/data-center-thermal-envelope-ashrae-setpoints/) covers the engineering; the cost model carries both the efficiency benefit and the equipment cost that buys it.

Utilization: the capex you paid for and do not use

Unused capacity spreads the facility investment across less IT load. For a fixed facility investment, Anvilfield calculates that operating at half the average IT load doubles capital cost per loaded MW. Delivered compute output is a separate denominator: it also depends on hardware and workload utilization.

This is where the stranded capacity guide connects directly to the money. Capacity gets trapped behind a binding constraint, power behind cooling, cooling behind distribution, or any of them behind a redundancy policy, and the room fills up on paper while floor and rack units sit open. Every stranded megawatt is capex you are paying for and not using. The first move when the numbers look bad is almost never to build more. It is to find and reclaim what is already built.

At low IT load, fixed cooling and power losses increase overhead energy per IT kWh. Raising load spreads those fixed losses across more IT energy, while total electricity consumption can rise. Compare the measured load curve, usable capacity and delivered work before sizing an expansion.

How much does it cost to build a data center per MW?

JLL’s 2026 Global Data Center Outlook reports an average global shell-and-core construction cost of $10.7 million per MW for 2025 and forecasts $11.3 million per MW for 2026. These are construction benchmarks with tenant technology fit-out reported separately. Label the 2025 value as reported historical cost and the 2026 value as a forecast.

Compare land, utility interconnection, substation work, electrical and mechanical equipment, cooling distribution, soft costs and financing against the benchmark scope. Price each scope difference explicitly. The project’s capacity basis must be MW of IT capacity, with its design density and redundancy recorded.

Keep an owner estimate and a published benchmark in separate columns. Divide the scoped facility estimate by supported IT capacity for the project’s cost per MW, then carry IT equipment and electricity in their own ledgers. This keeps a lower construction number from concealing excluded equipment or operating cost.

Cost per rack and per kW

Below the megawatt, cost shows up per rack and per kilowatt, and the two can move in opposite directions, which confuses people. As density rises, the cost per rack climbs because each cabinet now holds far more power and cooling, but the cost per kilowatt can actually fall, because that expensive infrastructure is spread across many more watts in the same footprint.

That is the whole economic argument for density. A traditional rack at a few kilowatts and a dense AI rack at tens of kilowatts are not the same product. The dense rack costs much more to build and feed, but if it does the work of many traditional racks, the cost per unit of compute can come out ahead. Per rack soars, per kilowatt can improve, and per unit of useful work is the number that actually matters.

On the operating side, colocation makes this concrete by pricing in dollars per rack and dollars per kilowatt per month, which exposes the density tradeoff in the invoice. A low-density rack and a high-density rack at the same site can differ by a large multiple in monthly power charges. Whether the density pays depends on what the compute earns, so run the cost per useful output, not the cost per rack.

How AI density changes the cost model

AI density changes both the rack equipment and the facility systems serving it. NVIDIA describes its GB200 NVL72 as a rack-scale liquid-cooled design. Use the selected system’s power and fluid requirements to scope electrical distribution, liquid cooling and residual air cooling together.

Price liquid cooling as an installed system: server cooling interfaces, CDUs, piping, pumps, heat rejection, controls and commissioning. Put server-supplied components in the IT ledger and facility-supplied components in the facility ledger. A per-rack allowance without that boundary obscures both missing work and duplicate charges.

Compare the installed rack and cooling cost with the delivered workload. Utilization, the energy tariff and the hardware refresh schedule determine how that investment is recovered over the study period. Use dated equipment quotes and performance inputs for the selected configuration.

The lifetime: facility years vs IT years

Choose a common study period, then assign each facility component and IT asset its own replacement schedule. NIST Handbook 135e2022 includes replacements and residual value in the life-cycle-cost analysis. The study period, physical service life and accounting depreciation life are separate inputs.

Use the owner’s procurement plan and equipment inventory for IT refresh dates. An accounting useful life determines depreciation charges; a refresh plan determines when cash leaves the business. Enter each replacement at its expected purchase date and record any remaining value at the end of the study period.

Model the facility and IT clocks separately within the same cash-flow schedule. Keep equipment replacements, end-of-period value and operating costs visible by year. For an annual accounting comparison, show depreciation separately from the cash-flow comparison so an initial purchase is not also counted as a second depreciation outflow.

Build, colocation, or cloud: which is cheaper?

Compare build, colocation and cloud over the same study period and delivered workload. Building carries facility ownership; colocation buys capacity while the tenant usually retains IT ownership; cloud buys a compute service. Capacity in MW is useful for the facility comparison, while completed work, service availability, storage and network traffic define the compute comparison.

Building puts facility investment, maintenance and replacement on the owner’s ledger. Colocation replaces that facility investment with contracted space, capacity and services while the tenant usually retains IT costs. Cloud charges for compute, storage, network and support; include the workload schedule and any capacity commitments when comparing its flexibility with owned or leased capacity.

Calculate the crossover from dated project cash flows. Include the colo contract’s capacity commitment, electricity treatment, escalation and exit terms, and include cloud compute, storage, network and support charges for the same workload. The break-even date is the year the compared cumulative costs cross, or compare discounted totals at a common base date.

OptionCost shapeDecision to test
Build / ownHeavy capex, you run the opexWhether sustained demand covers facility investment and operations
ColocationLease space and power, $/kW/monthAvailable capacity, delivery date and contract flexibility
CloudRent compute by the hourWorkload schedule, service charges and capacity commitments

The colocation cost model

Colocation prices power, not floor space, which is the clearest proof that the watt is the unit. Wholesale deals are quoted in dollars per kilowatt per month, and that single figure is the spine of the colo cost model. You commit to a power draw and you pay for it monthly whether you use it or not.

Separate the contracted capacity charge from metered electricity, cross-connects, installation and other recurring services. Record which charges the lease bundles into its rate. A contract with electricity included and one with electricity passed through require different ledger entries even when both quote dollars per kW per month.

Compare colocation and ownership over the same study period and supported IT capacity. Include the lease’s recurring charges, installation and exit costs; include the owned facility’s operating costs, replacements and end-of-period value. Use dated cash flows for both options so an annual lease charge is not compared directly with a lifetime capital total.

Land and shell in the lifetime cost

Land and shell enter the facility capital ledger at their purchase and construction dates. JLL’s shell-and-core benchmark and a land-only estimate describe different scopes. Record the included work before comparing either with total facility or IT-inclusive ownership cost.

Calculate the lifetime effect of a land saving alongside the site’s power tariff, connection schedule and construction scope. A lower purchase price reduces initial investment; delayed operation and higher recurring energy costs change the dated cash flows. NIST Handbook 135e2022 provides the present-value method for comparing those timing differences.

Site selection combines available power, energization timing, cooling resources, fiber and the serving utility tariff with land and construction costs. Carry each option through the same study period. Compare the resulting lifetime cost and delivery date with the capacity and workload the site must support.

Schedule and time-to-power: the cost of delay

Schedule is a cost, and on data centers right now it can be one of the largest. A facility earns nothing until it is energized, so every month between capital going out and power coming on is carrying cost on the build and revenue or capacity you do not have yet. Time-to-power has become a primary driver of site selection precisely because it is a primary driver of cost.

Build the energization schedule from utility milestones and equipment delivery dates. Carry financing costs and site overhead through the delay period, then calculate deferred service or lease revenue separately. Lost revenue is a business-case effect; it is not an electricity or construction cash outflow and must not be added to TCO a second time.

JLL’s 2026 Global Data Center Outlook identifies speed to power as the primary site-selection criterion. Put utility milestones, equipment dates and carrying costs into explicit schedule scenarios. Compare those scenarios with differences in land and operating costs over the same horizon.

Where optimizing actually pays

Rank efficiency, density, utilization and site options by their effect on the scoped TCO. Improving PUE changes energy use; reclaiming capacity changes the investment needed to serve demand. Compare those savings with the capital and operating costs of each change.

At fixed IT energy in an all-electric boundary, a reduction of 0.1 in PUE saves 0.1 kWh of facility electricity per IT kWh, calculated from The Green Grid’s ratio. Utilization determines how much built capacity serves load, while rack density affects distribution and cooling arrangements. Compare the resulting cost per delivered workload as well as cost per MW.

Spend engineering effort on the options with the largest discounted net savings. Recurring electricity savings accumulate over the study period; land savings reduce the initial purchase. Use the same discount rate and study period to compare both, including replacement, maintenance and water costs.

Building the TCO model

Build TCO from dated purchases, replacements, operating costs and end-of-period value, then discount them to one base date. NIST Handbook 135e2022 uses this life-cycle-cost approach. Show annualized costs as a separate reporting view and state the capacity or workload used as the denominator.

Maintain separate facility, IT and electricity ledgers. Enter facility and IT purchases when paid, renew equipment on its own schedule, and add energy, maintenance, staffing, water, connectivity and other operating charges by year. Keep nominal costs with a nominal discount rate, or constant-dollar costs with a real discount rate; NIST Handbook 135e2022 explains both approaches.

State the rate, PUE boundary, electrical load, asset lives, escalation, discount rate and included costs beside the result. Report facility capacity costs per MW and compute-service costs per delivered workload, with the same study period for every option. Separate equivalent annual cost from accounting depreciation and the underlying purchase cash flows.

How do you separate electricity, facility and IT costs?

Assign each cost to an owner, a ledger and a payment date. The facility ledger contains land, shell, electrical and mechanical infrastructure and their non-electric operating costs. The IT ledger contains servers, accelerators, storage, networking, software, support and refresh purchases within the comparison boundary.

The electricity ledger contains the whole facility bill, with IT electricity and facility overhead identified as subtotals. For a shared campus, allocate common plant energy using documented submeters or a stated allocation model. When a colocation lease already includes electricity, remove the duplicate electricity charge from the combined tenant model.

NIST Handbook 135e2022 separates initial investment, replacements, operating costs and residual value in a common study period. Use those dated cash flows for discounted TCO. An annualized comparison converts capital into annual charges; show that view separately and count each purchase once.

LedgerCapital or recurring entriesElectricity treatment
FacilityLand, shell, power and cooling plant, replacements, staffing, maintenance, water and property costsWhole facility bill enters the combined model once
ITServers, accelerators, storage, network, software, support and refresh purchasesIT energy is a subtotal of the facility bill
ElectricityEnergy, demand, fixed charges, riders and applicable taxesIT kWh plus overhead kWh reconcile to the metered boundary
Colocation tenantCapacity contract, tenant IT, connectivity and servicesAdd passed-through electricity; identify energy already included in rent
Cloud customerCompute, storage, network, support and migration servicesProvider energy is embedded in service charges

Worked model: one electricity bill, three cost percentages

Anvilfield estimates annual facility electricity of 10,512,000 kWh for an all-electric operating boundary with modeled average IT load of 1 MW, PUE of 1.2 and a non-leap year of 8,760 hours. At a model energy rate of $0.10/kWh, the energy charge is $1,051,200. This worked model sets demand charges, fixed charges, riders and taxes to zero, so the modeled bill equals the energy charge.

Using The Green Grid’s energy boundary, Anvilfield estimates 8,760,000 kWh of IT electricity and 1,752,000 kWh of facility overhead in this model. Overhead includes cooling, electrical losses and other support loads. Do not add cooling electricity again as a separate operating charge after counting it through PUE.

Anvilfield estimates electricity at 50% of facility operating cost, 40% of annualized facility cost and 20% of IT-inclusive annualized cost using the inputs in the table. The electricity bill stays $1,051,200 in all three calculations; only the cost denominator changes.

Method: model inputs are 1 MW average IT load, PUE 1.2, $0.10/kWh, non-electric facility operating cost of $1,051,200, annualized facility capital of $525,600 and annualized IT capital plus non-electric IT operations of $2,628,000. The annual capital amounts are model inputs; a project model derives them from its dated cash flows, study period and discount rate. Calculate IT energy from average load and hours, multiply by PUE for facility energy, and apply the energy rate. The energy method follows The Green Grid White Paper 49 (2012); NIST Handbook 135e2022 supplies the present-value cash-flow method, with sources checked November 6, 2026.

Electricity and denominator method

IT energy = average IT kW × period hours; facility energy = IT energy × PUE; overhead energy = facility energy − IT energy; electricity share = electricity bill ÷ named cost denominator × 100%.

Annual model ledgerCost denominator ($ thousands)Electricity share
Electricity plus non-electric facility operations2,102.450%
Facility operations plus annualized facility capital2,62840%
Annualized facility cost plus annualized IT capital and non-electric IT operations5,25620%

The sensitivities that decide the answer

A sensitivity analysis shows how TCO changes when an input changes. Start with the energy tariff, PUE and utilization, then test IT purchases, refresh timing and construction costs within the ownership boundary. Rank the results by their effect on cost per delivered workload or supported capacity.

For an all-electric boundary, the energy rate and PUE multiply IT energy in the electricity calculation. Electrical load changes energy use and the share of installed capacity serving demand; workload utilization changes how much useful work that energy delivers. If an input change reverses the build, colocation or cloud ranking, show that crossover beside the assumed range.

Run the tariff, PUE and utilization across stated project ranges, then report the spread and the decision crossovers. Carry energization delays and replacement timing as separate scenarios. Keep the input source, date and evidence label beside each range.

What to document

A TCO model that nobody can audit is a number nobody should trust. The record is what lets a reviewer, a lender, or a financial professional reproduce the result and check whether reality matched it. Capture the assumptions and the actuals side by side, and revisit them as the project moves from plan to operation.

Write down the capacity basis in megawatts, the capex by bucket and what is inside each, the IT refresh assumption and cycle, the energy rate and its source, the PUE assumed and later measured, the utilization assumed and later measured, the asset lives and depreciation method, the escalation and discount rates, and the schedule with the time-to-power assumption. Then track the actuals against every one of them, because the gap between the model and the meter is the most useful number you will ever record. A field tool such as FieldOS can hold the assumptions, the readings, and the variance in one place so the model and the building stay tied together. The figures vary by market, so note the market and the date next to every input.

Cost elementCapex or opexNote (figures vary by market and time)
Land and shellCapexLand, site and shell scope; payment dates and end-of-period value
Power and cooling infrastructureCapexElectrical and mechanical scope; supported IT capacity
IT gear (servers, GPUs)Capex (recurring)IT owner, equipment scope and replacement dates
EnergyOpexAverage IT load, matched PUE boundary, hours and tariff charges
Maintenance and staffOpexStaffing plan, maintenance scope and annual escalation
Water (evaporative cooling)OpexCooling system, consumption and water/sewer tariff
Lease / colocationOpexCapacity commitment, bundled services and electricity treatment
PUE (efficiency)DriverFacility/IT energy ratio; measured or modeled; period and boundary
UtilizationDriverElectrical load factor and workload utilization recorded separately

Which inputs are measured and which are modeled?

Label each input at the point of use. Measured values come from dated meters, bills or accounting records with a defined boundary. Modeled values come from load forecasts, design PUE, replacement assumptions or cost calculations. A vendor guarantee or signed tariff is contracted evidence; a survey average is reported evidence.

The Green Grid’s White Paper 49 defines PUE using facility and IT energy within the stated boundary. Divide the period’s total facility energy by its IT energy; weight monthly PUE ratios by monthly IT energy to reproduce the annual ratio. Keep a commissioning test, a design PUE and an annual operating PUE in separate fields.

Capacity utilization is average IT electrical load divided by usable IT power capacity. Server workload utilization measures useful work or resource use and is a different input: an idle server still draws power. Forecast load and PUE together by period, then reconcile the forecast with meters and bills after occupancy.

InputEvidence label and recordUse in the model
IT loadMeasured: interval IT meters; modeled: occupancy and equipment power forecastUse average electrical load or integrated kWh, not nameplate capacity alone
PUEMeasured: matched-period energy totals; modeled: design/load curveApply to IT energy once; preserve boundary and period
Electricity costMeasured: utility invoices; contracted: serving tariff and agreementSeparate kWh charges, billing demand, fixed charges and riders
Construction costReported: dated JLL benchmark; modeled: scoped project estimatePreserve shell/core scope and supported IT MW
IT refreshModeled: dated purchase and retirement scheduleEnter replacement cash flows and end-of-period value
Energy shareMeasured: bills divided by reconciled operating costs; modeled: forecast ledgersPrint numerator, denominator, period and ownership boundary

Common mistakes

  • Choosing land on purchase price alone without modeling utility costs, capacity and energization timing.
  • Ignoring how PUE multiplies the energy bill, so a cheap building locks in an expensive operating cost.
  • Ignoring utilization and stranded capacity, paying for megawatts that sit idle while depreciation runs.
  • Thinking per square foot instead of per megawatt of IT capacity.
  • Ignoring the cost of delay and time-to-power, treating schedule as free when idle capital is not.
  • Using stale energy tariffs or omitting demand, fixed charges, riders and taxes.
  • Comparing per-MW figures with different scope inside them, so one looks cheaper only because it excludes more.

Field checklist

0 of 9 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Finding data center cost planning work in your market

A good cost-model account has a decision, a deadline, and access to the inputs. Look for a developer comparing campus phases, an enterprise owner weighing a retrofit against colocation, or a manufacturer helping an operator compare equipment options. A large roof alone is a weak qualification. Ask which megawatts the decision covers, when the owner needs the answer, and who can release the load history, utility bills, and vendor quotes.

Make the initial screen concrete. For example, focus on one 5 MW phase with four generator packages and three cooling machines to review. Separate a new phase from a ten-year-old operating building with replacement decisions ahead. Record the age of each major asset from the owner's inventory, because the building date does not establish the remaining life of its equipment. Confirm access to plant rooms and operating records before promising a survey-based model.

Find candidate accounts through planning cases, parcel ownership records, expansion permits, and public requests for feasibility or engineering services. Loudoun County's property and land-use portal illustrates the local records to start with. GSA's solicitation guidance points to SAM.gov for federal opportunities; use the relevant agency's procurement portal for local work. Match the named applicant to the operator and the party buying the study. A developer's proposed campus, a permitted phase, and an energized hall belong in different rows.

Compare dated imagery with those records to flag possible new power yards or additional heat-rejection equipment. Then verify the phase with the owner. A visible substation does not establish deliverable utility capacity, the applicable tariff, or a committed energization date. Carry each unconfirmed input as an open item, with the document or person needed to resolve it, instead of quietly treating it as fact.

The account economics should be as transparent as the model. One owner commissions an options study with a documented inventory, three scenarios, and one review meeting. For this worked account, Anvilfield estimates a $19,200 fee from model inputs of 120 hours at $160 per hour. With model inputs of loaded labor at $95 per hour and $1,800 for travel and data preparation, direct cost is $13,200 and the remainder is $6,000 before overhead and tax. Financing advice, detailed design, and repeated model updates are outside that fee. A future equipment order is a separate opportunity, not revenue already earned.

Offer the owner a model whose inputs can be checked against the actual site. To find visible power assets around campuses worth researching, use PorchRocket's power Asset Search next step, which returns the owner of record with each find.

Standards, references, and where the figures come from

NIST Handbook 135e2022 supplies the present-value framework for comparing dated investment, replacement and operating costs with residual value. JLL provides the dated construction benchmarks used here; Uptime Institute reports survey PUE and Google reports its own measured fleet PUE. Keep those evidence types attached to their values.

The Green Grid White Paper 49 (2012) defines the energy boundary used in this guide. ISO/IEC 30134-2:2026 is the second edition of the PUE standard, published January 16, 2026, according to IEC’s publication record; it covers measurement, calculation and reporting. The electricity tariff and selected equipment’s thermal requirements supply project-specific cost and cooling inputs.

Source dates and scope travel with the figures: JLL’s 2025 shell-and-core cost and 2026 forecast, Uptime Institute’s 2025 survey PUE, Google’s 2025 measured fleet PUE, and ConRes’s undated energy-cost statement checked November 6, 2026. Anvilfield estimates are calculations from stated model inputs. Project meters, invoices, contracts and equipment schedules supply the actuals.

Units and terms

Data center cost runs in a few units that show up across estimates, leases, and energy bills, and keeping them straight is half of keeping the model honest.

Capacity is in megawatts (MW) or kilowatts (kW) of IT load; energy is in kilowatt-hours (kWh). EIA defines a kWh as the energy used by one kW for one hour. A non-leap year has 8,760 hours. Label build cost in dollars per MW of IT capacity, annual operating cost in dollars per kW-year, colocation capacity charges in dollars per kW-month and energy charges in dollars per kWh.

TCO
Total cost of ownership: dated purchases, replacements and operating costs less end-of-period value over a stated study period; report discounted or annualized results with the boundary named.
Capex
Capital expenditure: the up-front cost to build, including land, shell, power and cooling, and IT gear
Opex
Operating expenditure: recurring energy, maintenance, staffing, water, lease and other costs within the ownership boundary.
Cost per MW
Build cost per megawatt of IT capacity, the headline metric; varies widely by market and time
PUE
Power usage effectiveness: total facility energy divided by IT equipment energy over the same period and boundary, as defined by The Green Grid White Paper 49 (2012).
Utilization
Share of installed capacity actually loaded; low utilization wastes the capex you already spent
Colocation
Leasing space and power in someone else's facility, priced in dollars per kilowatt per month
Time-to-power
Elapsed time until a site can be energized; carrying cost accrues until it earns

Methodology

Anvilfield estimates use the inputs printed beside each worked calculation. The electricity model applies The Green Grid’s energy ratio to average IT load and period hours; the ownership model separates facility, IT and operating cash flows using NIST Handbook 135e2022. The cost-study account uses stated model hours, billing rate, loaded labor and travel costs; its $6,000 remainder is before overhead and tax.

Update log, November 6, 2026: reconciled the ConRes citation and withdrew the unsupported energy range; separated electricity, facility and IT boundaries; corrected load and PUE treatment; added a denominator model and evidence labels; replaced unsupported construction and operating-cost claims with dated sources or explicit project inputs. Sources opened with curl and reviewed November 6, 2026.

How to cite this page: Anvilfield, Data center TCO and the cost model field guide, 2026, https://anvilfield.com/field-guides/datacenter/data-center-tco-cost-model/

Related tools

Next step: Search for campus power assets

FAQ

What is data center TCO?

Data center TCO combines facility and IT purchases, replacements and operating costs within a stated ownership boundary and study period. NIST Handbook 135e2022 provides the dated cash-flow and present-value method. Report facility capacity cost per MW and compute-service cost per delivered workload.

Why is data center cost measured per MW instead of per square foot?

JLL reports data center construction cost per MW because the supported capacity matters alongside construction scope. Floor area alone does not specify IT power or cooling capacity. Compare facility cost per MW of IT capacity and compute-service cost per delivered workload.

What is the biggest data center operating cost?

ConRes’s undated power-and-cooling page reports energy-related expenses at 40% to 60% of operating costs and cites Anvilfield. Its denominator is not itemized. Calculate the site’s electricity share from bills divided by the named facility operating-cost ledger; this guide withdraws its earlier unsupported 40% to 80% range.

How much does it cost to build a data center per MW?

JLL’s 2026 Global Data Center Outlook reports a 2025 global average of $10.7 million per MW for shell-and-core construction and forecasts $11.3 million per MW for 2026. Tenant technology fit-out is separate. Compare the project’s scope and supported IT capacity with that boundary.

Is it cheaper to build, use colocation, or use cloud?

Compare all three over the same study period and delivered workload. Building carries facility capital and operations; colocation adds contracted capacity and tenant IT; cloud purchases compute, storage and network services. NIST Handbook 135e2022 supports comparing the dated cash flows at a common base date.

How does PUE affect data center cost?

The Green Grid defines PUE as facility energy divided by IT equipment energy over a matched period. At fixed IT energy in an all-electric boundary, lowering PUE reduces electricity use; apply the tariff to calculate the bill. Uptime Institute reports a 2025 survey weighted average of 1.54; Google reports a measured 2025 fleet average of 1.09.

How does AI density change the data center cost model?

NVIDIA’s GB200 NVL72 uses a rack-scale liquid-cooled design. Cost its power delivery, liquid cooling, heat rejection and residual air cooling from the selected equipment schedule. Assign server components to IT and facility equipment to the facility ledger, then compare cost per delivered workload.

Why does utilization matter for data center TCO?

For fixed facility investment, Anvilfield calculates that halving average IT load doubles capital cost per loaded MW. Total electricity cost can still rise as load increases. Track electrical load separately from workload utilization, and compare expansion with the cost of reclaiming usable capacity.

What is the cost of delay or time-to-power for a data center?

Calculate delay from the project’s utility milestones, equipment dates, financing and site overhead. Record deferred revenue separately from ownership cost. NIST Handbook 135e2022 provides the method for comparing cash flows that occur on different dates.

What makes a data center prospect ready for a cost study?

Confirm a specific capacity decision, an owner-approved deadline, a buyer for the study, and access to operating records and vendor inputs. Record proposed, permitted, and operating phases separately. Keep unverified capacity, tariffs, and energization dates open until the responsible party supplies evidence.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.

Sources checked