Which water-supply and discharge records qualify a data center site?
Match parcel supply commitments, seasonal demand, treatment and discharge approvals before acquiring or expanding a data center site.
Direct answer
A data center site qualifies for its proposed water demand when the records establish a parcel-specific supply commitment, delivery capacity for peak and seasonal demand, a treatment design matched to the source water, and approval for each discharge route. Match the service agreement, hydraulic study, seasonal water balance and discharge approvals to the same cooling design, development phase and service date. Include reclaimed-water allocation conditions, drought restrictions and backup capacity in that comparison so the documented supply covers the plant's demanding operating conditions.
On this page
Which water-supply records qualify the site?Is a utility commitment the same as available delivery capacity?Which water quantities and boundaries must match?How do you build a seasonal water balance?Which quality and treatment records determine usable supply?Which discharge approvals must be in the register?Does reclaimed water include enough backup capacity?How much curtailment can the design absorb?What costs and approval intervals belong in feasibility?Worked example: what do the utility records change?Water-feasibility field checklistHow should the team scope water diligence and site screening?Sources, method and citationOpen the related tool for the calculation, checklist, or packet.
Which water-supply records qualify the site?
Qualify the proposed phase with five connected records: a supply commitment register, seasonal water balance, quality/treatment matrix, discharge approval register and curtailment sensitivity. Anvilfield's diligence framework keeps the issuer, document date, applicable phase, units, conditions and superseded version with each record. [S2] [S3] [S13]
A water right answers who may abstract water under its terms. A utility commitment answers what service the utility has allocated and under which conditions. An accepted connection records completion of specified works. Read the operative terms rather than assigning legal force from a document's title; a conditional will-serve letter supports only the quantity and conditions it actually states.
Place this evidence behind the water screen in the data center site selection criteria. Retain required environmental water assessments beside service instruments: an assessment records evaluated demand and resources; the service terms establish allocation. Berkeley CLEE's February 2026 report explains California's regulatory and information gaps; its policy recommendations are distinct from enacted requirements. [S10] [S13]
What does each document actually establish?
| Evidence | What it proves | Fields to extract | Remaining evidence/action | Authority |
|---|---|---|---|---|
| Utility service-area / pipe map | Infrastructure location | Parcel, pressure zone, pipe size, date | Obtain hydraulic review and allocation | Loudoun Pre-Design explicitly says capacity and flows are unavailable from its map [S2] |
| Utility inquiry / concept letter | Issuer's stated preliminary position | Requested quantity, phase, date, qualifications | Resolve conditions and reservation | Anvilfield document review framework; inquiry stage [S2] |
| Executed service / capacity agreement | The parties' actual allocation and conditions | Daily/instantaneous/seasonal limits, dates, transfer | Match hydraulics, upgrades, restrictions | Loudoun allocation and service-agreement provisions [S13] |
| Accepted hydraulic study and approved connection design | Predicted delivery under studied conditions | Pressure, gpm, concurrency, losses, outage | Match allocation; complete offsite works | Upgrade requirements and continuity terms [S13] |
| Reclaimed allocation and backup agreement | Non-potable allocation and backup | Source gpd, quality, adjustment terms | Model full interruption and source blending | Schedule E [S13] |
| Direct-source right/permit plus production test | Authorized abstraction and tested output at stated conditions | Rate/volume, drought, duration, drawdown/recovery | Match treatment, yield, infrastructure | Anvilfield framework; establish source-specific requirements locally |
| Construction permit and accepted service connection | Approved works and completed conditions | Scope, drawings, easements, inspection, activation | Retain operational service and discharge records | [S3] [S13] |
What belongs in the commitment register?
Use one row per source and phase. Capture supply type, issuing party, executed document ID, reserved quantity and time basis, connection point, earliest delivery, upgrade funding, expiration and restriction language. Keep priority class, drought reductions, reservation fees, milestone conditions, release terms and transfer provisions beside the quantities they change.
For an acquisition, obtain the seller's agreements, meter records, discharge permissions and outstanding upgrade obligations. Request the issuer's written transfer or reissuance determination for the acquiring entity and proposed phase. Resolve material prerequisites before treating the quantity as available; no universal letter-validity period replaces the actual expiration term.
A well log identifies a drilled source. Qualify direct abstraction with the right or permit, pumping-test duration, drawdown and recovery, seasonal yield and matching treatment infrastructure.
Is a utility commitment the same as available delivery capacity?
The allocation and the delivery study must support the same demand at the same connection and date. Water passes through a resource, permitted abstraction, treatment, storage, distribution and the service connection.
Loudoun Water's Pre-Design guidance, checked November 5, 2026, states that its existing-utility maps show pipe locations and sizes but do not provide pipe capacity or flows. [S2]
Request written confirmation of maximum-day volume, maximum instantaneous flow, service-boundary pressure under stated system conditions and phase-by-phase delivery dates.
Separate present service from capacity conditional on a pump station, main extension or treatment upgrade. Assign funding, construction responsibility and completion dates to each condition. The selected cooling-system type sets the process request; the fire-protection hydraulic case has its own design basis and any concurrency requirement imposed by the serving authority.
Apply the same delivery check to wastewater: obtain acceptance for the receiving treatment works and capacity through the lateral, sewer and any lift station at the proposed batch rate. A purchased average-day sewer allowance does not establish that a short commissioning discharge will fit the collection system.
Which water quantities and boundaries must match?
Record annual volume, average day, maximum day and maximum instantaneous flow separately. Annual water use and WUE relates water volume to IT energy; connection design also needs flow and pressure. Keep water withdrawn at the meter, evaporative consumption and liquid returned to sewer as separate quantities.
Trace makeup water through one site boundary: source meter to domestic branch and treatment feed; treatment feed to tower product and reject; tower makeup to evaporation, drift and blowdown; sewer to accepted domestic wastewater, reject, blowdown and separately scheduled batches. Keep electricity-generation water outside this parcel connection balance.
A closed IT loop still needs an outdoor heat-rejection path. Direct-to-chip liquid cooling connected to evaporative rejection retains tower demand. Dry rejection removes routine evaporative makeup only for the duty and weather it serves; list domestic demand, initial fills, cleaning, installed humidification or adiabatic backup, and fire service separately.
How do you avoid counting reuse and treatment twice?
Credit recovered condensate or onsite reuse only in months and rates supported by production records or an engineering calculation, with a named receiving use and acceptable chemistry. A treatment plant's product output is smaller than its feed whenever it rejects water.
Divide product demand by recovery to obtain source feed, then subtract product to obtain reject. The equations are: feed = product / recovery; reject = feed minus product; tower makeup = evaporation + blowdown + drift, adding leaks and overflow when present. DOE FEMP supplies the tower balance. [S1]
How do you build a seasonal water balance?
Build twelve monthly rows for every phase and separate maximum-day and instantaneous-flow calculations. Retain the weather-file location, period and version; coincident dry- and wet-bulb conditions; IT-load ramp; available equipment; and wet/dry mode hours. Compare normal-year, hot/dry-year and restricted-supply cases on the same boundary.
Selected-equipment calculations at local coincident load and weather establish the design demand. Preliminary equivalent full-load hours express a useful calculation basis; nominal tons alone do not establish annual consumption. Adiabatic and evaporative cooling and free cooling and economizers change the hours in each mode.
DOE FEMP's undated estimating table, checked November 5, 2026, assigns 21,920 gallons to a 400-ton chiller's tower at three cycles over 24 full-load hours; its six-hour calculation gives 5,480 gallons. [S4]
What does a completed monthly balance look like?
The Anvilfield estimates below use that DOE input with six equivalent full-load hours per day in December through February, twelve in spring and fall, and twenty-four in June through August. Domestic demand is 500 gpd and the assumed delivered allowance is 25,000 gpd. Separate treatment reject and onsite reuse are zero; retain both fields in the calculation sheet.
Multiply DOE's full-load daily value by hours divided by 24 and actual 2026 month length, then add domestic use for that month.
| Month 2026 | Days | Hours/day | Tower makeup gpd | Domestic gpd | Total gal/month | Modeled daily supply margin gpd |
|---|---|---|---|---|---|---|
| January | 31 | 6 | 5,480 | 500 | 185,380 | 19,020 |
| February | 28 | 6 | 5,480 | 500 | 167,440 | 19,020 |
| March | 31 | 12 | 10,960 | 500 | 355,260 | 13,540 |
| April | 30 | 12 | 10,960 | 500 | 343,800 | 13,540 |
| May | 31 | 12 | 10,960 | 500 | 355,260 | 13,540 |
| June | 30 | 24 | 21,920 | 500 | 672,600 | 2,580 |
| July | 31 | 24 | 21,920 | 500 | 695,020 | 2,580 |
| August | 31 | 24 | 21,920 | 500 | 695,020 | 2,580 |
| September | 30 | 12 | 10,960 | 500 | 343,800 | 13,540 |
| October | 31 | 12 | 10,960 | 500 | 355,260 | 13,540 |
| November | 30 | 12 | 10,960 | 500 | 343,800 | 13,540 |
| December | 31 | 6 | 5,480 | 500 | 185,380 | 19,020 |
| Annual total | 365 | Seasonal | 4,515,520 gal/year | 182,500 gal/year | 4,698,020 | Smallest modeled daily margin 2,580 |
How do you test peak and commissioning demand?
Anvilfield estimates convert the summer total of 22,420 gpd to 15.57 gpm averaged across twenty-four hours. Obtain maximum inlet and refill rates from valve flow, controls and hydraulic design; the daily conversion does not size them.
A 20,000-gallon initial fill over eight hours adds 41.67 gpm. On the modeled summer operating day, that fill raises withdrawal to 42,420 gallons, exceeding the daily allowance by 17,420 gallons. Schedule it separately or secure a documented temporary allowance and sufficient instantaneous delivery. Check concurrent cooling, domestic demand, meter losses and approved disposal timing before placing the fill on the construction schedule.
Which quality and treatment records determine usable supply?
Source chemistry determines the usable operating range. Obtain dated laboratory records for conductivity, hardness, alkalinity, chloride, silica, sulfate and suspended solids, identified by source, sample point, method and units. Cover normal, seasonal and backup-source conditions; target new samples at uncovered source changes.
Compare makeup quality with predicted circulating chemistry at the proposed cycles of concentration and actual equipment materials. Potable classification alone does not establish compatibility. Keep tower chemistry separate from closed liquid-loop water treatment and chemistry, and include biological control, corrosion and scale protection in the treatment scope.
Where do manufacturer limits disagree?
BAC's Product & Application Handbook Volume VI, revision 20230630, and Marley's NC Class manual 00-1301F, copyright 2008, prescribe different normal pH ranges and startup conditions. Use the supplied model manual and actual materials for the project. BAC's circulating-water guidance is based on 95°F water, and mixed materials require their own review. [S5] [S6]
Normalize chloride units before comparison. BAC reports chloride as Cl; the cited Marley manual reports it as NaCl. Anvilfield estimates convert 500 mg/L as NaCl to about 303 mg/L as chloride using molecular masses, so comparing the printed numbers alone exaggerates their difference.
| Item | BAC galvanized construction | Marley NC Class | Design consequence | Source/edition |
|---|---|---|---|---|
| Normal circulating-water pH | 6.5 to 9.0 | 6.5 to 8.0 | Use selected equipment instructions | [S5], 20230630; [S6], 00-1301F, 2008 |
| Circulating-water chloride | 250 ppm as Cl | Below 500 ppm as NaCl, about 303 ppm as Cl | Normalize basis before calculating cycles | [S5] [S6]; conversion is Anvilfield estimate |
| Galvanized startup/passivation | pH 6.5 to 8.2; calcium hardness 50 to 600 ppm as CaCO3; four to eight weeks or until zinc surfaces dull gray | pH 6.5 to 8.0; hardness and alkalinity 100 to 300 ppm as CaCO3; at least first eight weeks | Scope startup water and treatment separately | [S5], J186; [S6], p. 20 |
| Example conservative chloride screen | Makeup 50 mg/L as Cl at four cycles predicts 200 mg/L as Cl, below 250 | The same 200 mg/L as Cl is below the normalized cited limit | Chloride fits; check other constituents | Anvilfield estimate inputs; manufacturer limits [S5] [S6] |
Which result limits the proposed cycles?
The following Anvilfield estimate inputs expose a chloride-only screening error. Multiplying source concentrations by four predicts acceptable chloride but excessive sulfate and silica, with conductivity at BAC's guideline.
| Parameter | Source-water input | Four-cycle screening result | BAC galvanized guidance at 95°F, revision 20230630 | Design action |
|---|---|---|---|---|
| Chloride as Cl | 50 mg/L | 200 mg/L | 250 ppm | Chloride screen fits; retain margin and check other constituents |
| Sulfate | 80 mg/L | 320 mg/L | 250 ppm | Lower cycles or secure treatment/materials acceptance |
| Silica | 40 mg/L | 160 mg/L | 150 ppm | Include silica in treatment guarantee |
| Conductivity | 600 µS/cm | About 2,400 µS/cm | 2,400 µS/cm | No margin for variability or chemical additions |
This initial no-removal screen treats dilute-water ppm and mg/L as approximately equivalent. Conductivity multiplication is approximate and chemical additions change it. At three cycles, estimated chloride is 150 mg/L, sulfate 240 mg/L and silica 120 mg/L; sulfate retains the smallest fractional margin. Validate scaling, corrosion and biological control against the treatment design and operating temperature.
Divide a conservative-ion circulating ceiling by the source concentration to screen cycles. Do not multiply pH by cycles or use simple concentration arithmetic to accept reactive hardness or silica chemistry. Suspended-solids filtration does not remove dissolved chloride; softening addresses hardness, while membranes add a reject stream. [S1] [S11]
Include galvanized startup/passivation demand, chemistry and duration in construction scope. A proposed six-cycle plant remains conditional until product-water chemistry and the treatment guarantee support that concentration.
BAC's 20230630 guidance requires biological control during tower operation; corrosion and scale treatment alone does not control biological contamination. Retain the startup and ongoing biological-control scope, including storage-water management and authorized disposal of treated water. [S5]
Which discharge approvals must be in the register?
Identify the actual receiving system for every stream before selecting an approval route. EPA's NPDES Permit Basics distinguishes point-source pollutant discharges to waters of the United States, requiring NPDES authorization, from sanitary-sewer discharges governed by receiving-municipality requirements. A storm drain needs its own route and authorization determination. [S7]
Register tower blowdown, membrane reject, softener regeneration, basin drains, cleaning water, domestic wastewater and commissioning flushes. Obtain the receiving authority's classification for the actual additives and chemistry rather than treating all cooling discharge as noncontact cooling water.
Which federal and local thresholds matter?
EPA's explanation of 40 CFR 403.3(v), checked November 5, 2026, identifies average process wastewater of at least 25,000 gpd as a significant industrial user (SIU) trigger, excluding sanitary, noncontact cooling and boiler blowdown from that test. Other routes include categorical status, contribution of at least 5% of a publicly owned treatment works' (POTW's) average dry-weather hydraulic or organic capacity, and discretionary designation. Retain the control authority's classification and any applicable nonsignificant designation. [S8]
EPA's summary of 40 CFR 403.5 prohibits discharge below pH 5.0 unless the works is designed for it. It also prohibits heat that inhibits biological treatment and causes interference, and heat raising the POTW treatment plant above 40°C unless the approval authority approves an alternative at the POTW's request. These limits apply alongside local discharge conditions, including at smaller flows. [S9]
Loudoun's Broad Run local limits, approved by Virginia DEQ November 8, 2024, state pH 5.0 to 10.0, 40°C at the POTW and 60°C from an SIU. The program separately identifies TSS above 245 mg/L as abnormal strength requiring written approval. Apply those values to that receiving works. [S14]
EPA's construction-stormwater guidance covers disturbance of at least one acre and smaller sites within a common plan of development or sale reaching one acre, subject to applicable permitting rules. That coverage does not authorize routine blowdown or chemical flushes. [S12]
| Stream | Receiving route | Required evidence | Quantity / quality record | Decision | Authority |
|---|---|---|---|---|---|
| Tower blowdown | Sanitary sewer | Works confirmation, survey, discharge authorization | Average/maximum gpd, batch gpm, chemistry | Obtain route and chemistry acceptance | [S8] [S9] [S14] |
| Membrane reject | Sanitary sewer | Concentrate acceptance and pretreatment conditions | Example 3,333 gpd reject from 75% recovery; salinity and treatment chemicals | Add reject to sewer balance | Anvilfield estimate; [S14] |
| Softener regeneration | Sanitary sewer or other approved route | Written brine/batch route decision | Batch gallons, peak gpm, salt mass and event schedule | Include batch peak | Anvilfield register method; [S14] |
| Pollutant-bearing liquid to surface water | Authorized outfall | NPDES permit or general-permit coverage | Permit limits, sampling location, averaging basis, start/expiry dates | Retain permit and covered activity before discharge | [S7] |
| Commissioning flush / cleaning water | Specifically approved temporary sewer route, treatment route or designated hauling destination | Temporary authorization and conditions | Example fill 20,000 gal; actual flush volume and chemical analysis entered separately | Schedule temporary disposal separately | [S3] [S14] |
| Construction runoff | Stormwater system / receiving waters | Applicable construction-stormwater authorization and pollution-prevention plan | Disturbed acreage, receiving water and authorized discharges | Apply acreage/common-plan screen | [S12] |
| Domestic wastewater | Sanitary sewer | Approved connection and purchased service capacity | Occupancy-based flow, applicable connection conditions | Separate from process classification | [S3] [S8] |
| Unapproved overflow / storm-drain connection | Unconfirmed | Drain tracing and permitting authority's determination | Destination, chemical contents, maximum overflow rate | Resolve route before drainage design | [S7] [S9] |
What monitoring and transfer records belong with approval?
Transcribe instantaneous, daily-maximum, monthly-average, batch and reporting conditions into separate fields. Record sample point, grab/composite method, laboratory method, flow basis, chain of custody and responsible organization. EPA's September 2012 Industrial User Permitting Guidance Manual explains the permit-specific structure; a generic monthly sampling allowance cannot replace it. [S15]
For an existing authorization, record operator, activity, outfall, expiry, renewal status and transfer conditions. Ask whether the new phase or chemistry requires modification. A seller's permit number or submitted application does not establish the acquiring operator's authorization. Keep sewer-credit metering separate: a blowdown meter supports billed volume while route and chemistry acceptance establish the discharge permission.
Does reclaimed water include enough backup capacity?
Record reclaimed quantity, pressure, chemistry, restrictions and downtime provisions separately from potable backup. Loudoun's current reclaimed program identifies supply availability and hydraulic constraints that can limit or exclude proposed connections. [S16]
Loudoun Water's October 9, 2026 Rates, Rules and Regulations sets potable backup capacity for reclaimed-water customers project by project, with a minimum of 10% of the reclaimed allocation. Schedule E also gives the utility allocation discretion and allows adjustments when reclaimed supply changes. [S13]
Complete-interruption coverage requires confirmed delivery, usable storage or supported demand reduction.
Loudoun's October 2026 Rule 20(d) requires an approved air gap where potable service supplies plumbing or process piping that also incorporates a secondary source, including reclaimed water. Retain the approved separation and switching design, valve capacity and refill rate. [S13] Recalculate treatment and blowdown for the backup source or blend; higher limiting dissolved solids can force lower cycles. Schedule startup and temporary fills separately from the reserve credited to operating backup.
How much curtailment can the design absorb?
Anvilfield estimates that the small phase needs 7,260 usable gallons for a 72-hour reduction to 20,000 gpd, or 67,260 usable gallons for a complete 72-hour supply loss, at constant summer demand of 22,420 gpd. The assumed 20% reduction is a design sensitivity, not a utility drought rule.
Subtract confirmed supply from required demand and multiply the positive shortfall by event duration to size usable storage. Divide an existing tank's usable water by the shortfall to calculate endurance. Exclude dead storage, minimum pump submergence, protected fire volume and unavailable compartments.
| Case | Process / total demand gpd | Available supply gpd | Surplus or deficit gpd | Resulting decision | Authority |
|---|---|---|---|---|---|
| DOE-based summer load, three cycles | 21,920 / 22,420 | 25,000 | +2,580 | Daily volume fits; verify instantaneous hydraulics | [S4]; Anvilfield assumptions |
| Same summer load, 20% supply reduction | 21,920 / 22,420 | 20,000 | -2,420 | Reserve 7,260 usable gal for 72 hours or reduce demand | Anvilfield estimates |
| Same summer load, complete interruption | 21,920 / 22,420 | 0 | -22,420 | Reserve 67,260 usable gal for 72 hours | Anvilfield estimates |
| Ideal chemistry screen, evaporation 60,000 gpd, three cycles | Makeup 90,000; blowdown 30,000 | Compare to phase-specific agreement | Calculated separately | Establish supply and discharge together | Ideal balance derived from [S1]; evaporation is Anvilfield input |
| Same evaporation, six cycles | Makeup 72,000; blowdown 12,000 | Same comparison basis | Makeup -20%; blowdown -60% versus three cycles | Require chemistry and equipment acceptance | Anvilfield estimates; [S1] [S5] [S6] |
| Same evaporation, two cycles during source change | Makeup 120,000; blowdown 60,000 | Same comparison basis | Makeup +33.33%; blowdown +100% versus three cycles | Increase allowances or change design | Anvilfield estimates |
For the ideal chemistry rows, assume negligible drift and leaks, hold evaporation fixed and divide it by cycles minus one to obtain blowdown, then add evaporation for makeup: B = E / (C - 1); M = E + B. Storage is shortfall gpd × duration hours / 24.
DOE BMP 10 describes three-to-six-cycle savings as 20% makeup and 50% blowdown; the ideal fixed-evaporation balance used here gives 20% and 60%, respectively. [S1]
Record shared treatment, mains, power and drought restrictions between primary and backup sources. Two connections can share the same failure. For dry or hybrid alternatives, retain manufacturer capacity at required ambient and fluid temperatures with the available components, and include the electrical consequence in PUE and energy-efficiency calculations. Pump power, refill limits and discharge capacity remain separate checks.
Storage covers a finite interruption. For persistent curtailment, qualify a smaller wet-cooling load or another confirmed source; refilling storage requires supply above ongoing demand. Refill time equals depleted usable gallons divided by that surplus in gallons per day. Confirm the tank can recover before the next design event.
What costs and approval intervals belong in feasibility?
Loudoun's January 1, 2026 schedule charges maximum-day water capacity at $15.62 per gpd and average-day sewer capacity at $41.31 per gpd. Those denominators differ. Separate capacity purchase from metered use, then price main extensions, easements, treatment, storage, temporary service and construction with actual quantities. [S17]
The October 9, 2026 rules base commercial Tier 1 on reserved capacity, with excess at Tier 2. For the Tier 1 calculation below, 2026 rates are $4.42 per 1,000 gallons potable, $2.07 reclaimed and $6.59 sewer. Apply the governing tier rules to the phase's billing pattern. [S13] [S17]
How long do approvals take?
EPA says individual NPDES coverage can take six months or longer. Its Permit Basics gives an application interval of at least 180 days before discharge; 40 CFR 122.21(c)(1), July 1, 2025 edition, allows a later date granted by the Director and distinguishes general-permit submission dates. The filing interval is not an approval promise. [S7] [S19]
Loudoun lists ten working days for specified submittal reviews and five to ten business days for final signed construction-permit issuance after required documents are verified and approved. These are individual stages. Schedule upgrade design, easements, permit reviews, utility construction and service activation separately, with a responsible party and predecessor for each. [S3]
Worked example: what do the utility records change?
Loudoun's published January 1, 2024 connection comparison uses a 100,000-square-foot data center, 100,000 gpd maximum cooling water, 20,000 gpd average sewer, 50,000 gpd average cooling-water use and 10,000 gpd potable backup. The Anvilfield estimates below retain those quantities and apply verified 2026 prices. [S18] [S17]
The current process-meter estimating guideline instead gives 0.125 gpd per square foot sewer, yielding 12,500 gpd. It assumes 25% blowdown to sanitary sewer and excludes the domestic meter. Keep this estimating basis separate from the older comparison and secure the approved demand; the difference changes sewer capacity cost by $309,825. [S17]
| Input/result | All potable | Reclaimed plus stated backup | Provenance and scope |
|---|---|---|---|
| Data center area | 100,000 sf | 100,000 sf | Published utility example [S18], 2024 |
| Maximum-day cooling water | 100,000 gpd potable | 100,000 gpd reclaimed | Published utility example [S18] |
| Purchased potable process backup | Included in main supply | 10,000 gpd | Example [S18]; 10% is current minimum, individually determined [S13] |
| Average cooling-water use | 50,000 gpd | 50,000 gpd | [S18] annual savings calculation |
| Average sewer, retained published basis | 20,000 gpd | 20,000 gpd | [S18], kept separate from current area guideline |
| Potable capacity charge | $1,562,000 | $156,200 | Anvilfield estimates |
| Reclaimed capacity availability charge | Not applicable | $0 | Allocation must be approved; [S13] Schedule E |
| Sewer capacity charge | $826,200 | $826,200 | Anvilfield estimates using 20,000 gpd |
| Process capacity subtotal | $2,388,200 | $982,400 | Anvilfield estimates; water and sewer availability only |
| Difference in capacity subtotals | $1,405,800 | Lower reclaimed subtotal | Anvilfield estimate |
| Alternate current guideline sewer | 12,500 gpd | 12,500 gpd | 100,000 sf × 0.125 gpd/sf [S17] |
| Sewer charge at alternate basis | $516,375 | $516,375 | Anvilfield estimates |
| Difference between sewer bases | $309,825 | $309,825 | 7,500 gpd × $41.31; resolve actual approved demand |
For annual variable charges, multiply average daily use by 365, divide by 1,000 and apply the 2026 rates above. Anvilfield estimates that 18,250,000 gallons of cooling water costs $80,665 at potable Tier 1 or $37,778 reclaimed; 7,300,000 gallons of sewer costs $48,107. Combined annual charges are $128,772 and $85,885, respectively, with a $42,888 water saving calculated before rounding. Domestic service, fixed charges, extensions, treatment and storage remain separate budget lines. [S18] [S17]
Anvilfield estimates that 100,000 gpd of cooling demand with 10,000 gpd of confirmed potable backup needs 270,000 usable gallons to bridge a 72-hour loss of reclaimed supply at constant demand. Price greater firm backup, storage, a smaller phase or a supported alternate rejection mode against that shortage.
Can treatment make the same site fail both allowances?
The combined engineering balance below holds evaporation at 60,000 gpd, with negligible drift/leaks, 500 gpd domestic supply and sewer, a 100,500 gpd source ceiling and a 40,500 gpd total sewer allowance. Treatment delivers all tower makeup at 75% recovery, with all reject routed to the accepted sewer. These are Anvilfield estimate inputs, separate from the tariff example.
| Design case at equal evaporation | Tower makeup gpd | Treatment feed / reject gpd | Total source withdrawal gpd | Total sewer gpd | Supply / sewer margin gpd | Quantity decision |
|---|---|---|---|---|---|---|
| Untreated makeup, three cycles | 90,000 | 90,000 / 0, no treatment loss | 90,500 | 30,500 | +10,000 / +10,000 | Volumes fit; verify source chemistry |
| Treated makeup, three cycles, 75% recovery | 90,000 | 120,000 / 30,000 | 120,500 | 60,500 | -20,000 / -20,000 | Both fail; revise design or agreements |
| Treated makeup, six cycles, 75% recovery | 72,000 | 96,000 / 24,000 | 96,500 | 36,500 | +4,000 / +4,000 | Volumes fit; verify six-cycle chemistry and route acceptance |
Anvilfield estimates that adding 75%-recovery treatment to a tower needing 90,000 gpd of makeup raises source demand and sewer flow by 30,000 gpd each, so water-quality treatment must be included in both capacity requests.
Divide product makeup by 0.75 for treatment feed and subtract product for reject. Source withdrawal is feed plus domestic use; sewer is blowdown plus reject plus domestic wastewater. Every row closes: withdrawal equals 60,000 gpd evaporation plus sewer flow. Retain the six-cycle alternative as conditional until product chemistry, sewer acceptance and delivery evidence support it; a recovery guarantee establishes a volume ratio, while product analyses establish chemistry.
Water-feasibility field checklist
Give each item an evidence location, responsible party, date and action. Under Anvilfield's recommended practice, documented means the phase fits the applicable quantity, hydraulic, quality and discharge conditions. Conditional identifies a named prerequisite; unresolved means the corresponding quantity remains unsupported.
Tie outstanding conditions to the acquisition and engineering schedule. When a quantity fails, change the phase, rejection plant, treatment, storage or source arrangement and rerun the same balance.
- Match parcel, service boundary, owner/entity and phase across every record; correct discrepancies.
- Record executed quantity, time basis, commencement, expiry and conditions; resolve missing allocations.
- Retain direct-source rights, permits and production evidence; exclude unsupported yield.
- Confirm water delivery and pressure and sewer batch capacity; resolve upgrades and losses.
- Retain monthly, maximum-day and instantaneous demand calculations; rerun after plant or load changes.
- Separate domestic demand, treatment feed/reject, temporary fill and expansion; close the balance.
- Identify dated source-quality records covering planned sources; tie cycles to equipment manuals.
- Assign startup/passivation chemistry, duration and disposal to construction scope.
- Name every receiving works or outfall and authorization; secure temporary flush permissions separately.
- Record discharge sample point, averaging basis, method and monitoring/reporting frequency; budget the program.
- Separate reclaimed allocation from potable backup; calculate interruption coverage.
- Record usable storage after reserves and dead volume; verify pumping, refill capacity and recovery time.
- Apply current capacity tariffs, use tiers and extension responsibilities; resolve competing sewer bases.
- Assign easements, upgrades, permits and activation to dated phase milestones.
- Resolve transfer, renewal, expansion and chemistry-change conditions with each issuer.
- Retain signed instruments, source PDFs, calculations, correspondence and superseded versions; repeat review after material changes.
How should the team scope water diligence and site screening?
Commission named deliverables: utility confirmation and connection design; source sampling and treatment design; the water balance; wastewater routing and permit applications; storage or alternate-mode design; and the commercial estimate and schedule. Price temporary supply and disposal within the construction and buildout phases, including commissioning fills and flushes.
Teams building a regional cooling-water diligence program use [PorchRocket Asset Search](/asset-search?for=cooling-towers) to locate visible cooling towers and get a reviewed list with the owner of record for each find. Request the site's utility agreements, process-water balance and discharge records from that owner as the starting document set.
For an occupied site, reconcile water and blowdown meter totals with billing records, equipment runtime and source changes. Explain gaps between recorded use and the proposed phase: low occupancy, dry-mode operation or incomplete buildout can conceal the future peak. Preserve raw readings and meter boundaries with the demand model.
Sources, method and citation
Sources checked and review date: November 5, 2026. DOE's web guidance is undated; named manuals, tariffs and regulations retain their editions below. Anvilfield's registers and checklist are diligence practices; Anvilfield estimates use the stated source inputs and engineering assumptions.
- S1: DOE FEMP, Best Management Practice #10: Cooling Tower Management; undated guidance.
- S2: Loudoun Water, Pre-Design; online procedure.
- S3: Loudoun Water, Permitting Your Approved Project; online procedure.
- S4: DOE FEMP, Estimating Methods for Determining End-Use Water Consumption; undated guidance.
- S5: Baltimore Aircoil, Product & Application Handbook Volume VI, Water Quality Guidelines, file revision 20230630, pp. J184 to J186.
- S6: SPX Cooling Technologies / Marley, NC Class Cooling Tower User Manual 00-1301F, copyright 2008, pp. 19 to 20.
- S7: EPA, NPDES Permit Basics; online guidance.
- S8: EPA, Pretreatment Roles and Responsibilities: Industrial Users; current online explanation of 40 CFR 403.3(v), checked 2026-11-05.
- S9: EPA, Pretreatment Standards and Requirements: General and Specific Prohibitions; current online explanation of 40 CFR 403.5, checked 2026-11-05.
- S10: UC Berkeley CLEE, Regulating Data Center Water Use in California, February 2026.
- S11: EPA WaterSense, WaterSense at Work, original October 2012 compilation, cooling-tower section 6.3.
- S12: EPA, Stormwater Discharges from Construction Activities; online guidance.
- S13: Loudoun Water, Rates, Rules and Regulations, October 9, 2026 revision; rates effective January 1, 2026.
- S14: Loudoun Water, Commercial and Industrial Wastewater Program; Broad Run local limits approved by DEQ November 8, 2024; checked 2026-11-05.
- S15: EPA, Industrial User Permitting Guidance Manual, September 2012.
- S16: Loudoun Water, Reclaimed Water Program; online program.
- S17: Loudoun Water, Rates, Fees, Charges and Penalties; effective January 1, 2026.
- S18: Loudoun Water, Reclaimed Connection Charge Comparison; expressly effective January 1, 2024.
- S19: U.S. Government Publishing Office, 40 CFR 122.21(c)(1), July 1, 2025 annual edition, printed p. 189; checked alongside current EPA Permit Basics on 2026-11-05.
Update log, 2026-11-05: Rechecked all listed sources and calculation tables; clarified heat-discharge restrictions, sewer hydraulics, biological control, reclaimed-water separation and storage recovery; shortened repeated calculations.
How to cite this page: Anvilfield, Which water-supply and discharge records qualify a data center site?, 2026, https://anvilfield.com/field-guides/datacenter/data-center-water-feasibility-evidence/
FAQ
What proves data center water availability?
A parcel-specific supply agreement, matching hydraulic evidence, a seasonal and peak demand balance, and an approved discharge route establish availability for the proposed phase.
Does a will-serve letter guarantee water capacity?
A will-serve letter establishes the capacity and conditions its actual terms state; confirm whether it reserves quantity, sets a service date and assigns required upgrades.
Can annual WUE establish peak water demand?
Annual WUE relates water volume to IT energy, while the connection also needs a maximum-day volume and an instantaneous-flow and pressure calculation.
Which permits cover cooling makeup and discharge?
The supply arrangement establishes the incoming service, while sewer discharges follow receiving-utility requirements and pollutant discharges to surface waters require applicable NPDES authorization.
Can cooling-tower blowdown go into a storm drain?
Use only a route specifically authorized for the actual blowdown chemistry and receiving water; a nearby storm drain does not establish that authorization.
Is a sewer discharge below 25,000 gpd exempt from pretreatment?
No; categorical status, the 5% capacity test, discretionary SIU designation, local limits and general discharge prohibitions remain relevant below that flow.
Does reclaimed water come with full potable backup?
Read the purchased backup terms: Loudoun's October 2026 rules set a project-specific amount with a 10% minimum, while interruption coverage requires the actual demand balance.
How much water storage covers a 72-hour interruption?
Anvilfield estimates that a constant 90,000 gpd supply shortfall requires 270,000 usable gallons for 72 hours; exclude protected reserves and unavailable tank volume.
Is six cycles of concentration always achievable?
Six cycles requires source chemistry and the selected equipment/treatment program to support the resulting circulating-water concentrations.
How long do water and discharge approvals take?
Loudoun lists five to ten business days for final construction-permit issuance after document approval. EPA says individual NPDES coverage can take six months or longer; apply at least 180 days before the proposed process discharge unless the Director grants a later date. Schedule utility upgrades separately.
Is a utility water commitment the same as capacity at the site?
The commitment records the allocated quantity and conditions; a hydraulic study establishes delivery at the connection, and required upgrades must be ready for the same phase and date.
Does water treatment increase the discharge allowance I need?
Include reject and regeneration streams as well as tower blowdown; the combined worked balance shows how treatment changes both the incoming water request and the sewer allowance.