Liquid-cooling air lock or blockage? A low-flow diagnostic guide

Separate trapped gas from hydraulic restriction with paired pressure-flow evidence, approved purge boundaries and a branch-by-branch restoration record.

Liquid coolingLow-flow diagnosisAir locksCDU commissioningCooling restoration

Direct answer

Separate a liquid-cooling air lock from a restriction by recording branch flow, local pressure loss and pump state together: sustained recovery after an approved gas-removal intervention supports trapped gas, while excess component pressure loss at matched flow supports restriction. Gas can cause unstable flow or interrupt circulation, while a loaded filter, partly closed valve or obstructed connector can produce persistent low flow. Restore service only after the affected branches meet their flow requirements and the loop carries the required heat load within its temperature and pressure limits.

On this pageIs low coolant flow an air lock or a restriction?Fault differential: which cause fits the whole pattern?What should you measure before changing anything?Map the high points and their local pressuresRead pressure-flow trends without confusing cause and effectCould this be cavitation, control hunting or a measurement error?What purge limits apply to this equipment?How do you localize a restriction after de-airing?Worked example: what does restored flow prove?What record proves that cooling duty is restored?How long does diagnosis take and what belongs in the scope?Field checklist and recurrence checksReview history and how to cite this guide

Is low coolant flow an air lock or a restriction?

Separate a liquid-cooling air lock from a restriction by recording branch flow, local pressure loss and pump state together: sustained recovery after an approved gas-removal intervention supports trapped gas, while excess component pressure loss at matched flow supports restriction. Gas can cause unstable flow or interrupt circulation, while a loaded filter, partly closed valve or obstructed connector can produce persistent low flow. Restore service only after the affected branches meet their flow requirements and the loop carries the required heat load within its temperature and pressure limits.

Start by locating the loss of service: one server branch, one rack, or every branch served by the coolant distribution unit (CDU). Compare the condition with the last accepted operating point. A post-service timestamp raises the priority of trapped gas, incomplete quick-disconnect (QD) engagement and incorrect valve lineup, but does not identify which occurred.

An air lock is a gas pocket that obstructs or breaks a liquid circulation path. Trapped pockets, moving entrained bubbles and dissolved gas released by warming or pressure reduction behave differently; Caleffi’s idronics 2 (2007) explains these distinctions. Noncondensable gas also differs from coolant vapor formed at inadequate local absolute pressure. [S7]

This guide addresses post-service diagnosis in single-phase, positive-pressure technology cooling systems (TCS). Identify the separate facility water system (FWS) across the heat exchanger and follow dedicated gas-management instructions for intentionally negative-pressure equipment. Bürkert distinguishes those architectures. [S10]

When branch flow or IT temperature violates an approved limit, apply the site’s load-reduction or isolation sequence before diagnostic adjustments. Record the affected asset and its actual limit. Use initial liquid-loop commissioning for filling and balancing, and direct-to-chip cooling paths to identify the serviced circuit.

Fault differential: which cause fits the whole pattern?

Use the whole hydraulic pattern to choose the next test. Anvilfield’s differential combines the cited manuals and hydraulic guidance.

Table A. Fault differential
Suspected causeFlow/pressure patternDiscriminating checkConfounder or next actionBasis
Trapped noncondensable gasFluctuating flow or sustained near-zero branch flow; pump may still rotateApproved high-point venting, gas discharge and sustained matched-condition improvementStable low flow can still be gas; check for coexisting restrictionS1, S2, S7; Anvilfield synthesis
Loaded filterExcess filter loss at comparable flow; flow can fall or pump speed riseCompare clean baseline and inspect isolated filterRaw differential pressure can fall as flow fallsS3, S4
Partly closed valveLocal pressure loss and low downstream flowVerify actual travel/position and bracket valve with tapsDisplayed command does not prove travelS4, S5; diagnostic synthesis
QD/hose restrictionOne branch low with acceptable header supplyVerify compatibility, engagement, bends and lossUse the installed QD service procedure; never crack a connection to ventS4, S6, S16
Server path obstructionExcess loss remains after upstream checksBracket complete server path and compare its approved curveDoes not identify fouling substance or authorize reverse flushingS4
Vapor cavitation/inadequate suctionNoise and loss of performance linked to suction pressure, temperature and speedCompare available inlet condition with installed pump NPSH requirementsGas noise can sound similarS9
Controls or pump faultCommand/actual-speed mismatch or oscillating setpoint/valve behaviorCorrelate mode, RPM, command and event logOverride expiry can change the operating pointS2, S5
Measurement faultReported low flow inconsistent with independent flow/thermal evidenceVerify sensor zero, installation, units and independent readingDo not use aggregate heat balance to dismiss a starved branchS3, S4, S5

Name each pressure-tap pair: filter loss, branch driving pressure and pump rise span different boundaries; static fill pressure is a local gauge reading. [S3, S5]

One branch versus every branch

One affected branch directs the first checks to its valves, hose bends, connector engagement and high points. Compare a healthy parallel branch under the same header conditions: adequate header differential pressure with one low-flow path focuses the search downstream. [S4] [S6]

Low flow across all branches directs attention to common filters, pump performance, supply availability, makeup and control setpoints. Changed bypass position or demand also moves the operating point. Persistent low flow does not exclude a stationary gas pocket, and fluctuating flow does not establish gas. [S2] [S3] [S5]

What should you measure before changing anything?

Capture synchronized total and affected-branch flow, pump command and actual RPM, control mode, pump inlet/discharge pressures, filter inlet/outlet pressures and manifold pressures. Add coolant supply/return temperatures, fluid product and concentration, reservoir or fill status, vent activity and IT load. Save alarms before resetting them. [S2] [S4] [S5]

With the load protected, Anvilfield recommends one-second samples for ten minutes before and after an approved intervention, retaining raw minima, maxima and event timestamps. Match faster acquisition to the sensor response and controller update rate when the event is shorter than that interval; one-second logging cannot establish subsecond failover performance.

Verify sensor zero, range, units, pressure type and calibration; independently check a reported zero flow. Compare pressure taps at equal elevation and bore, or correct elevation and velocity head before calling the difference component friction loss, following Hydraulic Institute’s System Curves guidance, updated July 19, 2024. [S15] Use telemetry calibration and measurement uncertainty to document the instrument chain.

Preserve the control state

Constant-pressure control can mask resistance by increasing speed; constant-flow control can mask it by increasing pressure. Identify whether the controller regulates pump-outlet pressure, pump differential pressure or remote manifold differential pressure. Record the controlled tap pair. [S2] [S5]

Tag override expiry and automatic reversion; see Table E. Compare authorized fixed-speed intervals with valve and bypass positions recorded. At constant flow compare component loss; at constant differential pressure compare flow and speed. The CDU controls and duty acceptance guide covers the broader control sequence.

Resolve small component losses with an instrument suited to that differential. Subtracting two large gauge readings can leave an error comparable to the loss being diagnosed; record both instruments’ accuracy and zero checks, or use an approved differential instrument. At zero flow, a corrected pressure difference across an isolated gas pocket is not a liquid friction-loss measurement. Verify the measurement chain before assigning that difference to fouling.

Map the high points and their local pressures

Map every place gas can collect and distinguish an installed vent from a survey location. OCP’s Guidelines to Rack Manifold Requirements and Qualification, §3.3, calls for bleed or vent valves at the manifold top to remove trapped air and a drain at the bottom for sediment removal and servicing. [S6]

High-point and pressure-tap mapSelected layout with separate facility water, CDU heat exchanger, pump taps, filter taps, an overhead crest, two parallel server branches, a bypass, expansion connection and low drain. H1 is a survey-only hose arch without an added vent.Figure 1. Selected TCS layout and high-point surveyCDU / HXPumpFilterInletDischargeFilter inFilter outV1 crest, 6 mSupply riserV2, 2 mSupply manifoldV3, 2 mReturn manifoldH1 arch, 3 mServer branch AServer branch BControlled bypassP0, 0 mExpansion connectionD1 low drain, 0 mFWS: separate HX sideV1/V2/V3: selected installed vents. H1: survey only; no improvised vent.At each point: pump-off p ___; pump-on p range ___; coolant T ___;actual RPM / mode ___; instrument ID ___. Record pressures locally.
Anvilfield map, not to scale. Survey installed hardware and local pressures; selected elevations match Table B.

Table B uses selected elevations with a stopped pump, a connected water column, density rounded to 1,000 kg/m³ and gravity of 9.81 m/s². Anvilfield estimates local gauge pressure by subtracting elevation head from the datum pressure: p(z) = 100 − 9.81z kPa. Elevation changes local pressure; it does not add net pumping head around a filled closed loop. [S3] [S15]

Table B. High-point survey and static-pressure calculation
Map ID/locationElevation above datumCalculated static pressureWhat to record/checkSource
P0 CDU datum0 m100 kPa gaugeGauge ID, expansion connection, fill stateS3, S7; Anvilfield estimate
V1 overhead crest6 m41 kPa gaugeInstalled vent/access, local pressure under flowS3, S7; Anvilfield estimate
V2 rack supply top2 m80 kPa gaugeTop vent and complete branch lineupS6; Anvilfield estimate
H1 raised hose arch3 m71 kPa gaugeHose route and approved means of gas removal; do not add an unapproved ventS4; Anvilfield estimate
V3 rack return top2 m80 kPa gaugeSeparate return-side vent/pressure locationS6; Anvilfield estimate
D1 manifold low drain0 m100 kPa gaugeLow-point drainage and contamination sample locationS6; Anvilfield estimate

At a selected datum of 50 kPa gauge, the same sealed column has approximately −9 kPa gauge at the overhead crest. Substitute the actual coolant density and pump-on pressure profile for site work. [S7]

Why a vent can admit air instead of releasing it

Anvilfield’s diagnostic rule is to measure local vent pressure before opening, during discharge and after closure: positive pressure at the CDU does not establish positive pressure at an elevated or pump-suction location. An open vent below atmospheric pressure can admit air. Keep the vent closed when its local pressure is outside the installed venting procedure’s permitted range; correct the pressure condition within the loop’s limits before venting. [S7]

Brief pressure or flow changes during opening can result from discharge and makeup. Judge recovery after the vent closes and conditions settle; liquid-only discharge proves clearance at that location and condition, not at every parallel hose arch. Recurrent air requires expansion-pressure and air-separation checks, plus ingress and makeup investigation. Raise fill pressure only within every connected component’s operating envelope. [S2] [S7] [S8]

Read pressure-flow trends without confusing cause and effect

Compare local pressure loss at matched flow, coolant temperature, concentration and component lineup. A falling flow can reduce measured differential pressure while resistance increases. Table C gives Anvilfield diagnostic predictions. [S3] [S4] [S15]

Table C. Expected traces at comparable duty
CaseFlow traceLocal loss traceCompanion eventInterpretation and limit
Gas movementUneven or interruptedVariable; location-dependentGas release/makeup with ventingSustained improvement supports gas involvement
Stable gas pocketLow and steady, possibly zeroDepends on trapped locationApproved gas removal restores pathSteadiness does not rule out gas
Fixed restriction, fixed speedLower settled flowIncreased loss at matched reference flowNo sustained matched-condition benefit from ventingLocalize restriction; raw Δp alone can mislead
Restriction, constant-flow controlFlow held until pump limitRequired head/speed risesNo corresponding gas-release eventFlow alarm can arrive late
Controls huntingRepeated flow movementFollows command/valve movementCommand leads or coincides with responseInspect control tuning and modes
Successful restorationStable branch flow in specified envelopeComparable clean-condition lossesAutomatic control restored, no leakageProve required heat duty and branch temperatures too
Gas versus restriction intervention tracesFive aligned strips per panel show branch flow, high-point pressure, component pressure loss, actual speed and control mode, and vent/makeup events. Gas removal supports recovery only at comparable driving pressure. Restriction persists after vent closure. Qualitative event order has no amplitude or duration scale.Figure 2. Anvilfield diagnostic schematicsGas contributionBaselineOpenCloseSettledBranch flowHigh-point gauge pComponent ΔpActual RPM / modeVent / makeupCompare loss at matched liquid flowFixed authorized mode / speedVent openLog gas discharge and every makeup eventPersistent restrictionBaselineOpenCloseSettledBranch flowHigh-point gauge pComponent ΔpActual RPM / modeVent / makeupCompare loss at matched liquid flowFixed authorized mode / speedVent openLog gas discharge and every makeup eventHorizontal axis: event order only. Transient amplitude and duration are unnumbered.Gas: settled flow recovers. Restriction: flow stays low; matched-flow component loss remains excessive.Record manifold driving pressure separately. A pressure rise, speed change or bypass change can explain recovery.
Gas can begin as steady low flow. Compare closed-vent settled states at comparable driving pressure; exclude makeup-induced pressure changes before assigning recovery to gas removal.

Log vent opening, closure, gas and makeup. Sustained recovery at comparable driving pressure supports gas involvement; persistent excess liquid-filled loss supports restriction. Exclude pressure, speed and bypass changes before assigning cause. [S2] [S3] [S7]

Normalize a loss only when the flow regime permits it

Scale corrected component loss by the square of the reference-flow ratio for comparable, liquid-filled, constant-coefficient conditions: Δp_ref = Δp_measured × (q_ref/q_measured)². Hydraulic Institute’s System Curves (updated July 19, 2024) supports this approximation. [S15]

Table D. Pressure-loss calculation
State/inputFlowComponent ΔpΔp scaled to 150 L/minMeaning
Selected clean baseline150 L/min20 kPa20 kPaReference resistance
Selected low-flow condition90 L/min18 kPa50 kPa2.50 times reference resistance despite a lower raw Δp
Selected intermediate condition after gas removal120 L/min32 kPa50 kPaResidual restriction remains despite improved flow
Selected restored condition after restriction service150 L/min20 kPa20 kPaBaseline hydraulic loss recovered

Anvilfield estimates that a component losing 18 kPa at 90 L/min would lose 50 kPa at 150 L/min under a quadratic-loss approximation, showing why a modest measured differential pressure can conceal increased resistance when flow has fallen. [S15]

Use same-elevation, same-bore boundaries. Caleffi’s idronics 16 (2015), Formula 4-2, uses a 1.75 exponent for smooth pipe; Anvilfield estimates 44.01 kPa and a 2.20 ratio for these inputs using that exponent. Turbulence alone does not make the square law exact. [S3]

Use the manufacturer’s curve for laminar cold-plate channels, active regulators, non-Newtonian fluids or strongly changing viscosity. Do not normalize across changing gas fraction as though it were a measured fouling factor. See flow and pressure balancing for the relationship between branch resistance and distribution.

What if gas removal improves flow but leaves a restriction?

Table D’s intermediate state separates the two repairs. Anvilfield estimates 32 kPa at 120 L/min for the same restricted liquid-filled component that loses 18 kPa at 90 L/min; both normalize to 50 kPa at the reference flow. Gas discharge with sustained branch recovery supports a gas contribution, while unchanged normalized filter loss keeps the filter investigation open.

After isolated restriction service and the necessary de-airing, the selected final state returns to the clean curve. Record both interventions, their makeup quantities and the settled conditions separately. The calculation uses the stated constant-coefficient model; actual fault assignment requires the corresponding gas observation, component inspection and matched-condition trends.

Could this be cavitation, control hunting or a measurement error?

Vapor cavitation is a suction-pressure and vapor-pressure problem. Evaluate inlet absolute pressure against coolant vapor pressure and the installed pump’s required net positive suction head (NPSH) at actual flow, accounting for velocity and inlet losses. A positive gauge reading alone does not establish adequate NPSH. [S9]

Record temperature, inlet pressure and the installed pump curve. Gas also causes noise; the Grundfos allowance in Table E applies only to its named pump family.

Flow movement correlated with speed commands, setpoints or valve motion calls for a controls investigation. Bubbles can interfere with some flowmeters; the installed meter manual controls fluid compatibility, accuracy and straight-run requirements. Resolve installation and independent-reading discrepancies before accepting a sensor trace as proof. [S4] [S5]

Normal TCS flow with warm supply coolant redirects attention to FWS conditions, heat-exchanger performance and load. Approach temperature alone cannot diagnose blockage. Record temperatures on the correct sides of the heat exchanger before assigning the fault. [S5]

What purge limits apply to this equipment?

Apply the installed model’s complete procedure and identify its operating stage before selecting speed, pressure or duration. Table E separates reservoir-based ALX and pressurized CDU 121 procedures.

Table E. Manufacturer-specific boundaries
Equipment/source editionInstruction/valueWhere it appliesApplication boundary
Koolance ALX-750/1450/2000, English v1.1Leave about 13 mm reservoir headspace; unit needs about 1 L plus external volumeFilling, printed p.9Reservoir instructions, not pressurized CDU targets
Same ALX manual0 L/min with nonzero pump RPM after filling can mean unfinished primingTroubleshooting, printed p.15RPM is not proof of coolant flow; do not tilt fixed racks
Vertiv CoolChip CDU 121, SL-80277 Rev A, 09-25Initial filling starts circulation at PS1 1.2 to 1.5 bar; maintain PS1 0.8 to 1.5 bar while pump 1 runs§6.2.4, pp.22-24, unit offlineBelow 0.8 bar: stop circulation pump 1, continue filling. Above 1.5 bar: stop fill pump. Displayed PS1 boundaries for this sequence
Same CDU 121 guideInitial fill uses staged pump 1 commands of 50%, 70% and 100%, with even liquid discharge for 5 seconds at the specified vent checks§6.2.4, pp.23-24, unit offlineUse complete procedure; then prove branch flow and duty
Same CDU 121 guideApproximately 30 minutes reduced-speed circulation; minimum speed 30%§6.4, p.27Subsequent circulation stage, separate from initial filling
Same CDU 121 guideDefault override inactivity timeout 15 minutes§6.5, p.27Record automatic reversion; it changes trend interpretation
Caleffi idronics 2, 2007At least 5 psi positive static pressure at system top in its conventional hydronic guidancep.23Conventional hydronic guidance only
Grundfos CM self-priming booklet 98514505, 1013Minimum 0.5 m head allowance in inlet-pressure calculationp.10Pump-family requirement; use installed CDU pump's curve and margin

Koolance’s ALX English v1.1 filling procedure, printed p.9, requires unplugging the AC supply before adding more coolant. Its troubleshooting section permits model-specific priming adjustments and temporary tilting with the fill port closed; those instructions do not transfer to fixed racks or pressurized CDU assemblies. [S1]

Before opening the fluid boundary, identify the isolated zone, protected load, approved vent tool, discharge route, available coolant, residual pressure and energy-control procedure. Keep leak detection and isolation response effective and discharge away from electronics. Plan cooling continuity during isolated service before taking the affected branch out of operation. [S2] [S6]

Vertiv’s SL-80277 Rev A (September 2025) initial fill requires unit-offline commissioning; transfer or isolate affected IT load. [S2]

Stop and restore the pressure boundary

Stop the intervention when the model’s suction/fill limit, approved load envelope, coolant supply or discharge containment cannot be maintained. Do not defeat a protective trip to keep an IT load running during diagnosis. Commissioning overrides belong to the model’s approved unloaded sequence; filter opening and hose repair require the prescribed isolation and depressurization. [S2] [S6]

Close and secure the vent, restore valve lineup, check for leakage, return controls to automatic and record replacement coolant. Falling reservoir level or repeated makeup after initial gas removal calls for leak and pressure-profile checks. [S1] [S2] [S7]

For U.S. general-industry servicing covered by OSHA’s 29 CFR 1910.147, paragraph (b) distinguishes control commands from energy-isolating devices, while (d)(5) and (d)(6) require stored-energy control and verification before servicing. A zero-speed command therefore does not isolate the loop. Identify electrical supplies, remote restart, pressurized headers and expansion vessels in the equipment-specific energy-control procedure. [S17]

How do you localize a restriction after de-airing?

Follow the pressure-loss path: common filter, header valve, branch hose, QD pair, manifold and complete server path. Bracket each tested boundary with identified taps. Verify compatible, fully seated connectors, actual valve travel and accessible hose geometry before opening a component. [S4] [S5] [S6]

OCP’s Cold Plate Cooling Loop Requirements, Rev 2, ties filtration to sensitive loop components, including connector and microchannel geometry. Use the installed filter/CDU replacement criterion and clean baseline; a borrowed pressure alarm is not a filter specification. Increasing speed can conceal restriction while consuming pressure margin. [S4]

Check quick-disconnect pressure loss and compatibility against the installed pair, including the pressure-test boundary. Preserve debris from an isolated filter instead of forcing it downstream through cold plates.

Gas and contamination can require separate repairs

A filter change can remove resistance and introduce air in the same service event. Record component replacement separately from venting, restore the boundary and remeasure after approved gas removal.

Persistent server-path loss localizes a hydraulic problem without identifying the deposit or authorizing reverse flushing. Route the assembly through its approved service process and use coolant chemistry and contamination evidence to investigate recurrence. OCP’s October 9, 2019 Rev 1.0 cold-plate requirements also support retaining filtration and commissioning history. [S4] [S11]

A rated dry-break disconnection differs from opening a fitting to bleed air. CPC’s undated Everis UQD06/UQDB06 product guidance permits disconnection under pressure for that connector family; the installed coupling limits and server service sequence still govern. Never loosen threaded joints or hold a QD partly engaged as a venting method. OCP’s Rev 2 loop requirements describe QDs as limiting air inclusion, not eliminating it. [S16] [S4]

Worked example: what does restored flow prove?

Restored flow establishes hydraulic delivery; heat duty requires flow and temperature evidence together. Table F applies OCP’s Rev 1.0 reference rating-flow factor to a selected generic 100 kW water loop. OCP’s rating conditions specify water on the FWS and propylene glycol on the TCS; this water calculation uses the flow factor, with its own declared fluid properties. [S5]

Convert volumetric flow to mass flow, then multiply by specific heat and return-minus-supply temperature. Following the sensible-heat method in Caleffi’s idronics 16 (2015), P = ρ × (q/60,000) × cp × ΔT, with P in kW, q in L/min, density in kg/m³ and cp in kJ/(kg·K). [S3]

Table F. Worked thermal duty
Input/resultValueProvenance or calculation
Selected duty100 kWAnvilfield calculation input
CDU rating flow factor1.5 L/min per kWOCP CDU test methodology Rev 1.0, §3.3.2.4; recommendation, not server flow requirement
Calculated reference flow150 L/min100 × 1.5
Rounded water density and specific heat1,000 kg/m³; 4.18 kJ/(kg·K)Declared engineering approximations for Anvilfield estimate; S3 heat-rate method
Reference mass flow2.50 kg/s150/60,000 × 1,000
Required rise at reference flow9.57 K100/(2.50 × 4.18)
Selected reduced flow90 L/min, or 1.50 kg/sAnvilfield input and conversion
Required rise at reduced flow15.95 K100/(1.50 × 4.18)
Duty at 90 L/min and 10 K62.70 kW1.50 × 4.18 × 10
Duty at 150 L/min and 10 K104.50 kW2.50 × 4.18 × 10
Temperature-difference error example±0.4 K at 10 K, or 4%Worst-case sum of two selected ±0.2 K bounds
Flow-plus-temperature error exampleApproximately 6% before property errorFirst-order worst-case sum of selected 2% flow and 4% ΔT bounds
Lower duty bound at nominal 150 L/min and 10 K98.31 kWSelected lower inputs: 147 L/min and 9.6 K, holding declared properties fixed
Selected stronger thermal result108.68 kW nominal; 102.41 kW lower bound150 L/min and 10.4 K nominal; 147 L/min and 10 K at the lower input bounds

Method: Anvilfield estimates use Table F’s cited flow factor and declared inputs. Substitute actual coolant properties at mean temperature; concentration and temperature affect thermal duty and hydraulic comparisons.

Why aggregate heat balance is only one part of acceptance

Compare liquid-side heat with the load actually entering that loop: account for residual air cooling, pump heat and energy storage during temperature change. Rack electrical input is not automatically liquid duty, and a bypass can preserve total flow while starving a server branch. [S3] [S4] [S5]

Table F uses a first-order sum for the approximate error allowance and multiplies the lower flow and temperature inputs for the lower duty bounds. Include coolant-property uncertainty and sensor placement or mixing error in the site decision. Under Anvilfield’s proposed lower-bound rule, the nominal thermal pass remains on hold when its lower bound falls below required duty.

Apply the same agreed decision rule to flow: a selected 150 L/min reading bounded by ±2% has a 147 L/min lower bound, so it does not demonstrate a 150 L/min minimum under that rule. OCP’s rating recommendation does not establish any installed server’s minimum. Pair measurement uncertainty with branch-flow and IT-temperature results before applying Table H.

When both flow and temperature rise look adequate, check whether the branch is actually carrying its assigned load. Low flow with a small temperature rise can mean reduced IT demand, a bypass, mixing or a bad sensor; it does not establish spare cooling capacity. A high temperature rise at low flow becomes a repair criterion only when compared with that server’s approved flow and coolant-temperature envelope. [S4] [S5]

What record proves that cooling duty is restored?

Anvilfield’s restored-duty record joins as-found, intervention and as-left evidence; the job’s agreed limits and measurement decision rule govern release. [S2, S4, S5, S6]

Table G. Restored-duty record
Record fieldRequired entryAcceptance comparisonRetained evidence
Identity and scopeCDU/rack/branch IDs, serials, incident and work-order IDsAll affected assetsAnnotated loop map
Governing limitsActual minimum branch flows, maximum temperatures/pressures, approved test load and holdManual revision and approved procedureLimit sheet with source pages
As-found conditionFlow, local Δp, inlet pressure, fluid temperatures, RPM, control mode, load and timestampComparable accepted baselineRaw pre-service trend
Fluid conditionProduct, concentration, mean temperature, makeup quantity, sample IDApproved coolant specificationSample/makeup record
InterventionVent ID or replaced part, valve lineup, discharge observation, start/end timeAuthorized procedure completedEvent log and filter/part photos
Hydraulic restorationTotal and every affected branch flow; same-boundary lossesEach branch passes agreed decision rulePost-service trend and calibration IDs
Thermal restorationLoad entering loop, flow, supply/return temperature and calculated dutyRequired duty and IT temperaturesCalculation, properties and uncertainty
Protection and controlLeak inspection, interlock state, overrides cleared, automatic mode, alarmsApproved normal sequence restoredControls/event-log export
RedundancyAffected test result or unchanged redundancyApproved scope and recovery criteriaRequired witness result
Release and follow-upRelease role, time, hold interval, recurrence checksSignoffs and observation completeSigned restoration record
Table H. Return-to-service decisions
Finding at the required operating dutyDecisionEvidence needed to close
Total CDU flow recovered, one affected branch below its approved minimumHold affected loadRestore that branch; identify bypass or flow redistribution
Bubble-free liquid at one approved vent, remote branch remains lowLocalize furtherMap, driving pressure and branch loss
104.50 kW nominal heat transfer for a 100 kW requirement, lower bound 98.31 kW under Table F inputsHold thermal pass under the proposed lower-bound ruleReduce uncertainty or prove duty within temperature limits
108.68 kW nominal, lower bound 102.41 kW before property errorThermal criterion clears 100 kW only if remaining error allowances fit the marginProperty errors, branch flows, IT temperatures and observation
Flow and heat duty pass but leak remains, protective override remains or required redundancy proof failsHold releaseRestore boundary, controls and affected redundancy functions
Every applicable hydraulic, thermal, protection and observation criterion passes under the job's agreed decision ruleRelease by operating authorityTable G, traces and signed release

Set the stabilization and observation interval before testing, then retain actual start and end times. Branch minimums, pressure limits, coolant and IT temperatures, leak checks and protective controls must pass together at required duty.

The service crew records physical restoration, the controls team verifies overrides and interlocks, and the operating authority releases the load. Include the commissioning witness where the contract requires witnessed acceptance. If service disturbed redundancy, repeat the affected approved failover proof with load protected; use CDU acceptance and redundancy testing for those larger scopes.

Start the acceptance hold after automatic control and the intended valve lineup are restored. An unloaded circulation test closes the gas-removal task; the record remains open for required-duty proof when the specified load is unavailable. Record the tested duty and the outstanding load test explicitly, then keep the affected load within the operating authority’s permitted envelope.

How long does diagnosis take and what belongs in the scope?

Anvilfield estimates 2 to 4 elapsed site hours and 4 to 8 technician-hours for an accessible two-person diagnostic visit with isolation approved and instruments ready. These are November 2026 scope estimates.

Method: allocate 30 to 60 minutes each for records and lineup, measurements, one authorized intervention, and restoration evidence. Multiply elapsed hours by two technicians to estimate staffing.

Define the diagnostic package separately from component replacement. Waiting for access, load authorization, parts, chemistry results or a longer specified duty hold extends the visit. A low-flow diagnostic package specifies branch measurements, one authorized intervention and a restoration record; PorchRocket’s Bid Control tracks public HVAC solicitations where contractors bid that cooling-service scope.

Carry separate allowances for coolant, filters, QDs, waste handling, instruments and load-bank support, using actual quantities and supplier quotes. Include required witness time and controls support explicitly. An inaccessible high point or missing test port changes the scope before the crew starts.

Field checklist and recurrence checks

  1. Identify the TCS/FWS boundary and positive- or negative-pressure architecture.
  2. Protect the IT load using the approved operating sequence; identify affected branches and the last service/change event.
  3. Preserve pre-intervention alarms and trends with a common clock.
  4. Confirm the applicable branch flow, temperature and pressure limits.
  5. Identify the permitted venting and component-service boundaries.
  6. Verify instruments, units, pressure datum and calibration status.
  7. Record control mode, pump command, actual speed and overrides.
  8. Verify valves, QD engagement and accessible hose routing.
  9. Map high points, vents, pressure taps, expansion connection and drain route.
  10. Compare filter and branch losses at comparable flow and coolant condition.
  11. Confirm offline/load-transfer requirements, authorize model-specific purge or isolated component service, and prepare containment.
  12. Record gas release, makeup and any persistent restriction separately.
  13. Restore the fluid boundary and verify leak-tightness and valve lineup.
  14. Restore automatic controls and alarms; complete affected redundancy proof with load protected.
  15. Prove affected-branch flow, required heat duty and IT temperatures over the approved interval using the agreed uncertainty decision rule.
  16. Save the as-left evidence, obtain release and schedule event-based recurrence reviews.

Anvilfield recommends recurrence reviews during the first stable post-service run, the next operating shift and the next comparable load period. Compare low-flow events, makeup activity and local pressures at equivalent load and control state. These are event-based checks; scheduled sampling and filter maintenance follow the OEM and coolant specification.

Returning gas directs the investigation toward local pressure, expansion arrangements, ingress, leakage and fill practice. Returning filter loss directs it toward debris origin, coolant chemistry and filter selection. Join the leak-response record to the coolant condition record so repeated bleeding or replacement does not become the default repair. [S4] [S7] [S8]

Review history and how to cite this guide

Byline: Anvilfield. Editorial review date: 2026-11-05. Sources checked: the manufacturer manuals, OCP publications, hydronic references and regulator guidance listed below. Source access: 2026-11-06 UTC.

Update log, 2026-11-05: verified manual editions and purge limits; corrected the QD service boundary and uncertainty method; added a staged gas-plus-restriction diagnosis, measurement checks and acceptance-hold rules.

Cite a specific evidence object using its fragment: fault differential, high-point survey, pressure-flow signatures, purge boundaries or restored-duty record.

How to cite this page: Anvilfield, Liquid-cooling air lock or blockage? A low-flow diagnostic guide, 2026, https://anvilfield.com/field-guides/datacenter/liquid-cooling-air-lock-low-flow-diagnosis/

Related tools

Next step: Find public HVAC bids

FAQ

How do you diagnose liquid cooling air locks and low flow?

Compare branch flow, local pressure losses, pump state and the sustained response to an approved venting intervention.

How do you distinguish CDU gas from a restriction?

Gas release with sustained recovery supports gas involvement; excess local loss at matched flow supports a restriction, and both can occur together.

What high-point vent pressure trends matter?

Track local pressure during pump operation and venting because an elevated vent can approach or fall below atmospheric pressure while the CDU gauge remains positive.

What proves coolant flow and cooling duty are restored?

Every affected branch must meet its requirement while the loop carries the required heat load and stays within temperature, pressure and protection limits.

Can a pump run while coolant flow is zero?

Yes; Koolance's ALX English v1.1 manual identifies zero indicated flow with nonzero pump RPM after filling as possible unfinished priming.

Does a low filter differential pressure rule out blockage?

No; falling flow can reduce differential pressure even as the filter's resistance increases.

How long should a CDU purge run?

Plan about 30 minutes for the CoolChip CDU 121's low-speed circulation stage after initial filling, according to Vertiv's SL-80277 Rev A (September 2025). The complete diagnostic visit, load transfer and return-to-duty observation need separate time allowances.

Can you open any high-point fitting to bleed air?

Use the installed approved vent and containment procedure within its permitted pressure and operating range. Do not loosen a fitting or partly engage a QD to bleed air; rated dry-break service follows its own connector and server instructions.

Why does air return after bleeding?

Check local sub-atmospheric pressure, leaks or air ingress, expansion arrangements and replenishment instead of repeating the purge without investigating the cause.

Should you raise pump speed to clear low flow?

Change speed only within the approved procedure because added speed can hide restriction, exceed pressure limits or worsen inadequate suction conditions.