Crown
A crown is a high drainage line dividing two runoff slopes; on a 22 ft road with a centered 4% crown, it stands 5.28 in above equal-height edges. Calculate each side from its own horizontal width when the high line is offset. FHWA's 2015 gravel-road guide recommends a straight profile on each side, so matching the center and edge elevations alone does not establish the correct shape.
The raised centerline and cross-slope that sheds water off the road surface to the ditches
Calculate crown height over half the road
FHWA's Gravel Roads: Construction and Maintenance Guide, August 2015, recommends a straight shoulder-to-centerline profile rising about 4%, approximately 1/2 in per foot. On a symmetrical road, use the distance from the centerline to one edge when calculating that rise. Multiplying the slope by the full road width doubles the intended crown height.
For a 22 ft road with a centered crown and 4.00% slopes, each side spans 11 ft. The rise is 11 × 0.04 = 0.44 ft, or 5.28 in. With both edges at elevation 100.00 ft, the center is 100.44 ft and the halfway point on either side is 100.22 ft. Using the rounded 1/2 in per foot instead produces 5.50 in, so carry the plan's actual percentage into the aggregate-road layout.
Find the flat middle of a parabolic crown
A rounded section can have the correct center and edge elevations while retaining very little slope near the center. Shoot intermediate offsets to expose that shape. In the 22 ft section above, a halfway elevation of 100.40 ft instead of 100.22 ft leaves only 0.04 ft of fall through the inner 5.5 ft. That inner slope is approximately 0.73%, followed by a much steeper outer portion.
FHWA's 2015 gravel-road guide recommends straightening a grader cutting edge when center wear reaches roughly 1/2 to 3/4 in. The guide connects that wear with the rounded profile it calls a parabolic crown. Checking blade shape alongside the surveyed section helps identify why repeated grading keeps recreating a flat center.
A sports-field crown changes the playing surface
Cornell's Sports Field Management guidance calls for at least 1.5% slope on native-soil soccer fields and at least 1% where underground drainage is installed. At 1.5%, a 100 ft drainage run needs 1.5 ft of fall. The same run at the gravel-road value of 4% needs 4 ft, which changes playing geometry substantially. Select the field's surface and drainage arrangement before carrying a road-crown number into the grading plan.
Cornell also identifies a crowned layout as unsuitable for shared ball-control sports such as soccer and field hockey. On a shared field, map each playing rectangle against the proposed high line and grade breaks. Carry that layout into the sports-field construction record with the sideline outlet elevations; a high center without a receiving collection route leaves part of the drainage design unresolved.
Distinctions
- One-way cross-slope
- A single plane drains toward one edge. It has no interior high line dividing runoff, even when its maximum elevation is called the high side in field notes.
- Pipe crown
- Pipe inspection uses crown for the upper part of the pipe section. A crown elevation in a culvert or sewer record therefore identifies pipe geometry rather than the road's drainage ridge.
Frequently asked questions
Can both road edges be level and still have crown?
Yes. Equal edge elevations say nothing about the intervening high line. Measure from each edge to the crown and include intermediate offsets.
Does the crown have to be at the center?
An offset high line creates unequal drainage widths. On a 22 ft road divided into 9 ft and 13 ft sides, a crown at 100.44 ft with 4% slopes reaches edges at 100.08 ft and 99.92 ft. Equal slopes on unequal widths require different edge elevations; calculate both sides before setting the blade.
Sources checked
Also defined as
- Landscaping: The raised centerline of a field that slopes to the sidelines to shed surface water