Density differential
Density differential is the measured joint-to-mat or spot-to-mat deficit, reported in density units or percentage points of Gmm: 94.0% Gmm minus 91.5% Gmm is 2.5 points. The relative reduction from that mat is about 2.66%, a different calculation. Keep the reference location, unit and Gmm basis with the result so a pcf limit is not mistaken for a percentage-point limit.
How far the joint density falls below the adjoining mat density, commonly limited to about 2 percent
Keep pcf and percentage points on separate lines
For mass density, subtract the joint result from the mat result and retain lb/ft³, also written pcf. For results normalized to the same Gmm, subtract their percentages and report percentage points. Converting a pcf difference into percentage points requires the maximum theoretical density in pcf: difference ÷ maximum density × 100.
A 3.0 pcf gap against a 150.0 pcf maximum equals 2.0 percentage points. Against a 160.0 pcf maximum, it equals 1.875 points. Carry the mixture's actual maximum theoretical density into the calculation when converting the differential discussed in the longitudinal-joint guide.
TxDOT tests two conditions together
TxDOT's 2024 Item 341, Section 4.9.3.3.4.2, fails a joint record test when the joint is more than 3.0 pcf below the mat at the random core location and its correlated density is below 90.0%. That provision calls for an evaluation at every pavement edge that is or will become a longitudinal joint in each sublot, excluding its defined miscellaneous areas. The preceding informational-test provision uses a maximum 3.0 pcf deficit from a reading at or near the mat center and requires additional evaluations at least once per sublot unless directed otherwise.
Tex-207-F, January 2020, calculates correlated joint density by multiplying core density as a percentage of Gmm by the joint-to-interior gauge-density ratio. With a 93.0% core result, 142.0 pcf interior gauge reading and 137.0 pcf joint reading, the correlated result is 93.0 × 137.0 ÷ 142.0 = 89.7%. The 5.0 pcf gap and the sub-90.0% result trigger both parts of the Item 341 record-test criterion.
Apply the strict inequalities in that particular clause. A 5.0 pcf gap with 90.3% correlated density misses the density condition; a 2.5 pcf gap with 89.7% misses the differential condition. Neither combination triggers this two-condition failure rule. Retain the absolute joint result because other project acceptance provisions still apply.
Reproduce the gauge location before comparing results
TxDOT's Tex-207-F, January 2020, Part VII places the gauge center 8 in from the joint edge, with its long dimension parallel to the joint. It locates the interior reference more than 2 ft from the pavement edge and takes joint readings perpendicular to that reference location. A reading centered directly over the seam samples a different position from this prescribed offset.
Tex-207-F, Part VII requires three backscatter readings of at least one minute each at both gauge locations when using a nuclear gauge; its electrical-impedance option uses two readings at each location. The correlated calculation uses the average readings. Record the confined or unconfined edge condition, the gauge averages and the reference core result together. For a segregated spot, identify the surrounding comparison area explicitly because that profile has different sampling geometry.
Distinctions
- Minimum joint density
- A minimum controls the joint's absolute result. A differential controls its relationship to a reference area. Two equally low results can have a small differential while the joint still misses an absolute minimum.
- Density range
- A profile's highest-to-lowest range uses its two extremes. An average-to-lowest difference uses a different reference and generally gives a different result. Preserve the specified comparison.
Frequently asked questions
Is a 3 pcf differential always 2%?
It equals 2 percentage points only when the maximum theoretical density is 150 pcf. Divide by the actual reference density to convert it.
Can a joint meet the differential limit and still be too open?
Yes. If the adjoining mat is also poorly compacted, subtracting the two results conceals their shared low density. Retain the absolute joint result alongside the difference.
Sources checked
Also defined as
- The gap in density between a segregated spot and the surrounding mat