Evaporation rate

Evaporation rate is an area-based water flux, reported in kg/m²/hour or lb/ft²/hour. Calculate a measured value as water mass lost divided by exposed area and elapsed time: 25 grams from 0.050 square meter in 30 minutes equals 1.0 kg/m²/hour. An open pan measures free-water drying demand. Its result must stay distinct from actual water loss through a concrete surface after the exposed water film has disappeared.

The water leaving the fresh surface per area per time, read from the ACI chart; precautions apply near 0.2 lb/sq ft/hr

Used across 2 Anvilfield field guides, most in Concrete.
Updated

What the concrete evaporation chart estimates

FHWA's 2006 curing guide explains that the ACI nomograph represents evaporation from a free-water surface, rather than water loss from concrete after its exposed water film has disappeared. That distinction matters when comparing a weather calculation with a sample that has already developed a dry-looking skin.

ACI PRC-305-20 places estimated evaporation in Section 4.2. In a pour record, label each result by its origin: weather estimate, water-pan measurement, or concrete-specimen mass loss. Compare protection decisions with the evaporation guide while preserving those different measurement bases.

Measure water loss with area and elapsed time

FHWA's 2006 guide describes direct evaporation measurement by weighing water lost from an open container near the construction site. Divide the lost water mass by the exposed water area and the elapsed time. Container dimensions matter: a mass loss without the water-surface area is not an evaporation rate.

For a container exposing 0.050 square meter of water, a loss of 25 grams in 30 minutes gives 1.0 kg/m²/hour: 0.025 kg divided by 0.050 m² and 0.5 hour. Losing the same 25 grams over a full hour gives 0.5 kg/m²/hour. These are interval averages; a short wind event within either interval is hidden in the average.

Record spills, rain, and water additions separately from evaporation. Weigh the same container assembly at both ends of the interval, and preserve its exposed area. Keep water temperature with the result so a cool container in shade is not silently treated as a duplicate of a sun-warmed slab.

Separate surface temperature from the delivery reading

FHWA's 2006 discussion favors concrete surface temperature for the evaporation calculation because evaporative cooling changes the exposed surface relative to the bulk concrete. Retain the delivery acceptance temperature as its own measurement. Label the sensing location and method whenever an additional surface reading is used.

AVR's ready-mix calculator specifies averaged wind speed at 20 inches above the concrete. AVR places air temperature and relative humidity in shade, upwind, and 4 to 6 feet above the concrete. These inputs therefore require different sensor positions. Record local conditions after a windbreak or shade changes the placement environment, alongside the time the protection went into service.

Distinctions

Mass-loss rate
Water mass lost per time, such as grams per minute. Dividing by exposed area produces the area-based evaporation rate used for concrete surfaces.

Field example

A pour record shows 0.5 kg/m²/hour of free-water evaporation demand and a separately measured bleeding rate of 0.2 kg/m²/hour. Demand exceeds replenishment by 0.3 kg/m²/hour, equivalent to a 0.225 kg/m² shortfall over 45 minutes if both rates persist. Keep the two rates and their measurement intervals beside that balance; the evaporation figure alone leaves the supply side uncounted.

Frequently asked questions

Can two water pans lose the same weight but have different evaporation rates?

Yes. If one exposes twice the water area over the same interval, its area-based rate is half as large for the same mass loss. Compare area, elapsed time, temperature, and exposure together.

Does the weather calculation measure concrete bleeding?

No. It estimates atmospheric drying demand. Bleeding supplies water from inside the concrete, so a bleeding observation or test is a separate input to interpreting surface conditions.

Sources checked

Also defined as

  • Water leaving the fresh surface per area per time, in lb per square foot per hour or kg per square meter per hour

Where this shows up

Next step: Map industrial yard accounts

Back to the full field glossary