ANVILFIELD Try FieldOS

Field glossary · material

HRWR / superplasticizer

HRWR, or superplasticizer, reduces concrete's water demand, with NRMCA's CIP 15 reporting a 12% to 40% reduction at equal slump. Liquid dosage uses a different basis: Sika's ViscoCrete-2100 typically takes 1 to 6 fl oz per 100 lb of cementitious material. For a 600 lb/yd3 binder mix, 4 fl oz per 100 lb becomes 24 fl oz/yd3. An ASTM performance type does not set that dispenser quantity.

High-range water reducer, ASTM C494 Type F or G, cutting water at least 12 percent or giving high flow

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Water reduction and liquid dosage are different quantities

NRMCA's CIP 15 gives a 12% to 40% reduction in mixture water at equal slump for HRWRs. That percentage compares water demand, while the dispenser measures liquid admixture. A trial mixture reduced from 300 to 255 lb of water per cubic yard has a 15% water reduction: (300 - 255) / 300 x 100. Its liquid admixture dose still comes from the approved trial record.

ASTM C494/C494M-24 assigns Type G to high-range water reduction with retardation; ViscoCrete-2100 instead lists Types A and F on its March 2024 sheet, so slump retention alone does not make it a Type G submittal. Record the trial's measured slump retention and setting behavior alongside the product's declared classification.

Convert cementitious mass into the dispenser quantity

Sika's March 2024 ViscoCrete-2100 data sheet gives a typical dosage of 1 to 6 fluid ounces per 100 lb of cement or cementitious material, with up to 12 fl oz per 100 lb for maximum water reduction. These are quantities per binder mass; use the approved trial dose for the calculation, not the top of the published range.

An approved dose of 4 fl oz per 100 lb applied to a mix with 600 lb of cementitious material per cubic yard requires 24 fl oz per cubic yard. An 8 cubic yard load therefore takes 192 fl oz: 4 x 600 / 100 x 8. Write the selected dose and the calculated load quantity on separate lines so the dispenser setting is auditable.

At the same 4 fl oz per 100 lb dose, increasing binder from 600 to 650 lb per cubic yard changes the dispenser quantity from 24 to 26 fl oz per cubic yard. For an 8 cubic yard load that is 208 fl oz instead of 192. Resolve which supplementary materials are included in the approved cementitious total before applying the admixture classifications to a batch ticket.

Type, chemistry and qualification are different fields

ViscoCrete-2100 uses polycarboxylate technology and its data sheet identifies compliance with Types A and F. That combination shows why the ASTM letter is not a polymer name or a single dosage setting. Keep the exact product and formulation identity beside the specified performance type.

ASTM C494/C494M-24 separates testing into three levels: initial qualification, limited retesting and purchaser-specified lot uniformity or equivalence testing. A qualification report and a delivery-lot check therefore answer different questions. Identify which evidence the submittal actually contains.

ASTM's public scope recommends supplementary testing with the project's materials, proportions and batching sequence. Attach each trial's cement and supplementary-material identities to its dose and measured results. A source change then has a specific comparison record, including the flow and stability observations used for SCC placement.

Storage condition can explain erratic dosing results

Sika specifies a one-year shelf life for ViscoCrete-2100 in original packaging under dry warehouse storage at 40 to 80 F. Its storage instructions require temperatures above 40 F and direct thawing and thorough agitation if the liquid freezes.

Keep the manufacture date, storage history and container identity with the delivery record. A dosing investigation needs both the quantity metered and the condition of the material that passed through the dispenser. A correct volume does not establish that an aged or separated supply was homogeneous.

The ViscoCrete-2100 instructions require separate dispensing when combined with other admixtures and prohibit mixing the product with dry cement. Record addition order and mixing with the batch data, so a performance change can be traced to the material, the quantity or the sequence.

Frequently asked questions

Is 4 fluid ounces per hundredweight the same as 4 fluid ounces per yard?

No. Multiply the dose by the cementitious mass in each cubic yard divided by 100 lb, then by the load volume. Keep fluid volume distinct from the binder's mass.

Does Type F identify a specific superplasticizer chemistry?

Type F identifies high-range water-reducing performance. Read the product data for the chemistry and the approved trials for its behavior in the actual mixture.

Sources checked

Also defined as

  • High-range water reducer, the admixture that gives flow without adding water

Where this shows up