ANVILFIELD Try FieldOS

Field glossary · measurement

kW/ton

For a reporting period, calculate kW/ton from accumulated electrical kWh divided by delivered refrigeration ton-hours on the same boundary. DOE/LBNL uses this integrated definition for plant performance. A plant using 330 kWh to deliver 600 ton-hours reports 0.55 kW/ton. An ordinary average of its interval ratios can give a different result. Keep pump and tower-fan loads in a plant total and identify any chiller-only result separately.

Total plant power divided by tons of cooling; the plant efficiency metric, lower is better

Used across 2 Anvilfield field guides, most in HVAC.
Updated

Choose the plant boundary before collecting power

DOE and LBNL's Data Center Metering and Resource Guide defines chiller-plant energy as the energy used by chillers, pumps and cooling-tower fans. Its separate treatment of computer-room air-handler fans shows why a plant boundary must be named rather than inferred from the word cooling.

A chiller display and a plant feeder meter therefore need not produce the same numerator. List the loads represented by each meter. An improvement at the compressor can be offset by greater pump or tower power, so retain the plant total when judging a plant-control change.

Use the same metering boundary before and after a chiller sequencing change, then aggregate matching electrical and thermal intervals. A revised meter boundary cannot establish an operating saving.

Weight the result by cooling delivered

The DOE/LBNL guide defines period plant performance as electrical kWh divided by integrated cooling in ton-hours, with the resulting units equivalent to kW/ton. Integrate power and cooling over matching time intervals and then divide the totals.

During one hour, a plant delivering 100 tons at 80 kW operates at 0.80 kW/ton. During a second hour, it delivers 500 tons at 250 kW, or 0.50 kW/ton. The two-hour totals are 330 kWh and 600 ton-hours, giving 0.55 kW/ton. The arithmetic average of the two displayed ratios, 0.65, gives the low-load hour too much weight.

Variable-length trend intervals also require their actual durations. Multiplying every observation by an assumed five minutes after a logging interruption corrupts both totals. Align timestamps and identify missing readings before comparing a week with a baseline period.

Keep idle energy and zero-load hours visible

At zero delivered cooling, an instantaneous kW/ton ratio is undefined. Idle pump or control energy still belongs in the reporting period's kWh when those loads lie inside the selected boundary. Omitting those hours makes the period result look better without reducing consumption.

DOE's Process Cooling System Cheat Sheet defines a refrigeration ton as 12,000 Btu/h and distinguishes it from a 15,000-Btu/h cooling-tower ton. Use refrigeration tons in the efficiency denominator. A heat-rejection capacity expressed in tower tons does not represent delivered evaporator cooling.

DOE's Process Cooling System Cheat Sheet gives kW/ton = 12 / (COP × 3.413). A cooling COP of 6 corresponds to about 0.586 kW/ton at the same condition and boundary. Applying that conversion to compressor-only COP still produces a compressor-only result; it does not add pump or tower energy.

Present the period's kWh and ton-hours alongside the ratio. Those totals reveal whether a lower ratio accompanied a different load mix or a change in operating hours. Compare matched weather and load conditions when attributing a difference to a control adjustment rather than to the reporting period itself.

Distinctions

IPLV
A rating calculated from prescribed part-load conditions and weights. It is not the measured energy divided by cooling delivered over a particular building's operating period.

Frequently asked questions

Can I average monthly kW/ton values to get the annual result?

Weight each month by its delivered ton-hours, or divide the annual kWh total by the annual ton-hour total. Equal month weights disregard different cooling quantities.

Does lower kW/ton always mean fewer kWh?

No. A more efficient plant can use more electricity while delivering more cooling. Report both efficiency and total energy.

Sources checked

Also defined as

  • Compressor power per ton of cooling; the lower the number, the more efficient the machine
  • Compressor kilowatts per ton of cooling; the efficiency measure, lower is better

Where this shows up

Next step: Map cooling-plant service territory

Back to the full field glossary