Field glossary · process
Makeup air
In kitchen ventilation, makeup air is outdoor air supplied specifically to replace hood exhaust. Replacement air is the broader balance that also includes HVAC supply and transfer air from adjacent rooms. A 4,000 cfm hood therefore does not automatically require a 4,000 cfm dedicated makeup unit. Allocate each available path once, and keep the kitchen balance separate from the whole-building outdoor-air balance.
Air brought in to replace what is exhausted, by ducted outside air, transfer air, or surplus supply
Follow the air across each room boundary
ASHRAE's 2023 HVAC Applications chapter on kitchen ventilation identifies replacement air as the combination of dedicated makeup air, HVAC supply air, and transfer air. That distinction matters when a dining-room air handler also supplies the air that eventually reaches a kitchen hood.
A kitchen exhausts 4,000 cfm, receives 2,800 cfm through a makeup unit, and receives 1,200 cfm from the dining room. Its room balance totals 4,000 cfm. At the building boundary, the transfer is internal: the dining-room system must introduce that 1,200 cfm outdoors to complete this balance, assuming no other exhaust or pressure offset. A supply fan merely recirculating dining-room air leaves a 1,200 cfm outdoor-air deficit.
Account for moisture as well as supply temperature
The 2024 International Mechanical Code, Section 508.1.1, requires kitchen HVAC capacity to address both latent and sensible loads introduced by makeup air, or dedicated conditioning that meets its temperature-difference provision. Washington's State Building Code Council publishes the model-code change showing the added latent-load language.
That 2024 IMC provision limits the dedicated-conditioner makeup-air temperature difference to 10°F, or 6°C, from the kitchen design setpoint, with an exception for makeup air supplied to a compensating hood. A dry-bulb temperature within that band does not by itself demonstrate that the space system can carry the moisture load. Carry the entering-air humidity condition and resulting latent load into the equipment selection.
Transfer air is a design resource with a real path
ASHRAE's kitchen-ventilation guidance describes using available transfer air from adjacent spaces to reduce the dedicated makeup-air requirement. The transfer route must function during actual operation. A closed door, undersized opening, or altered adjacent-zone schedule can remove air that the original balance counted on.
Document the transfer-air origin, the opening or duct it crosses, and the fan schedule that keeps it available. Measure the kitchen with the adjacent zone in its actual operating mode. Put those transfer readings beside the duties in the commercial exhaust fan schedule, so the balance identifies which system supplies each portion rather than treating hood and makeup-unit airflow as the entire building.
A report that lists only hood exhaust and makeup-unit airflow misses this room-to-room relationship. Include the adjacent-zone supply and return balance so a future HVAC change does not quietly consume the transfer air assigned to the kitchen.
Distinctions
- Outdoor ventilation air
- Ventilation air is introduced for occupant and contaminant needs. The same air may later serve as transfer air, but it must not be counted twice at the same boundary.
Frequently asked questions
Does every exhaust cfm require a cfm from a dedicated makeup unit?
The total replacement-air balance must be satisfied. A dedicated unit supplies only the portion assigned to it after conditioned supply, usable transfer air, and the intended pressure relationship are accounted for.