Suction lift
Calculate suction lift as impeller-centerline elevation minus pumping water-surface elevation; record it in feet or meters. This is the elevation component of an above-water pump's inlet conditions. For shallow-well sizing, Goulds' TTECHWP R7 budgets 25 ft at sea level for lift and suction friction together. A vacuum reading includes flow effects, so it cannot isolate that elevation component. Intake submergence measures the water covering the inlet, a separate dimension.
Vertical distance from the water surface up to a pump mounted above it, practically limited to roughly 20 to 25 ft
How to measure the surface-to-pump elevation
Use the impeller centerline as the pump datum, following KSB's geodetic-lift convention. Survey that elevation and the source surface from one benchmark. Record the pumping flow beside the water level so another technician can reproduce the operating lift. Keep the elevation result and friction allowance in separate fields.
Submergence is the inlet's depth below the surface. Moving the inlet deeper changes pipe length and intake conditions while leaving the surface-to-impeller elevation gap unchanged. Carry these separate measurements into the irrigation pump selection record.
What a suction vacuum gauge tells you
Goulds Water Technology's GSSERVICE R10 (August 2025) converts 1 in. Hg of vacuum to approximately 1.13 ft of water head. A 20 in. Hg reading therefore represents 22.6 ft of vacuum head. Report that result as a pressure deficit at the tap, rather than a surveyed water depth.
Goulds' GSSERVICE R10 uses a gauge at the shallow-well adapter for its running-pump diagnostic: 22 in. Hg or more points to an inlet buried in mud, a stuck foot/check valve, or lift beyond pump capacity. Low or zero vacuum points to a suction leak or an unsubmerged inlet.
KSB's NPSH relation accounts for velocity head and the elevation difference between the suction nozzle and impeller datum. Enter the gauge unit and tap location in the NPSHa calculation, and retain the raw reading in the pump diagnosis record.
How much suction lift is usable at altitude?
Goulds' GSSERVICE R10 gives a shallow-well rule of thumb: start with 25 ft at sea level and deduct 1 ft for each 1,000 ft of elevation. Its TTECHWP R7 explains that the 25 ft allowance includes suction friction. At 5,000 ft, that rule leaves about 20 ft for elevation lift and friction together.
Goulds' TTECHWP R7 (June 2024) lists atmospheric head as 33.9 ft of water at sea level and 28.2 ft at 5,000 ft elevation. That difference removes 5.7 ft from the available head before any pipe or pump requirement is deducted.
For a pump-specific calculation, Cornell Pump's method gives maximum elevation lift = atmospheric head - vapor-pressure head - suction losses - NPSHr - margin. Use the altitude-table pressure and express every term in feet of the pumped liquid. Cornell's July 2016 guidance reserves 2 ft for NPSH margin; use the selected pump's specified margin and NPSHr at the operating duty. The altitude deduction belongs in the atmospheric term once.
Why a 23 ft lift can require larger suction pipe
In Goulds' TTECHWP R7 steel-pipe table, 7 gpm through 100 ft loses 3.56 ft of head in nominal 1 in. pipe and 0.93 ft in 1-1/4 in. pipe.
Using the manual's elevation-plus-friction convention, its 23 ft lift becomes 26.56 ft with the smaller pipe and 23.93 ft with the larger pipe. Goulds rounds the latter to 24 ft in its diagram. The larger line recovers 2.63 ft without changing pump elevation.
Against Goulds' 25 ft sea-level allowance, the smaller pipe already exceeds the budget; the larger pipe leaves only 1.07 ft for valves, fittings and intake losses. Calculate those losses at 7 gpm. Record the material and full developed pipe length beside the elevation lift in the well-pump survey.
Distinctions
- Static suction lift
- The geometric component, tabulated separately from flow resistance. A pumping water level can supply the surface elevation; static describes the head component being counted, not a requirement to measure only with the pump stopped.
- Dynamic suction lift
- Goulds' TTECHWP R7, page 20, includes velocity head in addition to elevation and friction. Its page 51 sizing example uses a simplified elevation-plus-friction total. Label the convention so a vacuum reading, pipe-sizing allowance and surveyed lift remain distinct quantities.
- Refrigerant suction lift
- Use the refrigerant-piping guide when a drawing means the suction vapor riser. Label that dimension as suction-riser height so it cannot be mistaken for a surface-water lift measurement.
Frequently asked questions
How do I calculate suction lift from a closed tank?
Tank pressure and surveyed lift are separate inputs. In Cornell's calculation, substitute the tank's absolute surface-pressure head for atmospheric head. For a gauge-pressure reading, add local atmospheric pressure before converting the result to head of the pumped liquid.
Sources checked
- KSB Centrifugal Pump Lexicon: geodetic suction lift and impeller-centerline reference
- Goulds Water Technology: Submersible and Jet Pumps Service Manual, GSSERVICE R10, August 2025, pp. 88-89
- Goulds Water Technology: Water Products Technical Data and Pump Fundamentals, TTECHWP R7, June 2024, printed pp. 2, 19-20, 23 and 51 (PDF pp. 4, 21-22, 25 and 53)
- Cornell Pump: Simple Way to Determine Suction Lift, July 31, 2016, lift calculation and 2 ft NPSH margin recommendation
- KSB Centrifugal Pump Lexicon: NPSH, velocity head and suction-nozzle/impeller reference elevations
Also defined as
- HVAC: The pump above the water level, lifting it; the static term goes negative and the NPSH margin is tighter