Field glossary · measurement
Available fault current
Available fault current describes prospective short-circuit duty at a named point in a power system. The number changes with source strength, feeder impedance and switch positions, so a useful study result includes its voltage, fault type and operating configuration. Use the maximum applicable case for equipment-duty comparisons and retain minimum-current cases for clearing-time analysis. A motor running downstream can contribute fault current even though it consumes power during normal operation.
The maximum fault current available at the equipment; interrupting and short-circuit current ratings must be at least equal to it
Calculate both a cold-conductor and a hot-conductor case
Schneider Electric's Electrical Installation Guide uses conductor resistance at 20°C for maximum short-circuit current and at the maximum permitted steady operating temperature for minimum short-circuit current in breaker-protected circuits. Cold conductors have lower resistance, so the supply delivers more current through the same route.
Schneider's table gives design copper resistivity as 18.51 mΩ·mm²/m at 20°C and 23.69 mΩ·mm²/m at 90°C for XLPE-insulated cable in its IEC-based calculation method. The hot value is about 28 percent higher. On a 50 m, 50 mm² copper conductor, those values give approximately 18.51 mΩ cold and 23.69 mΩ hot for the conductor resistance.
That resistance change does not mean the complete fault current changes by 28 percent. Source and transformer reactance remain in the total impedance. In a three-phase calculation, add the series resistances together, add the series reactances together, then calculate the magnitude from those two totals. Treating every impedance as a scalar sum loses that distinction.
A source contribution can arrive from the load side
A running induction motor briefly supplies current into a nearby fault as its rotating field collapses. Schneider's simplified method estimates three-phase motor contribution at 3.5 times motor rated current and calls for including it when simultaneously running motor power exceeds 25 percent of total transformer power. This is the manufacturer's calculation method, rather than a universal motor constant.
For a group totaling 200 A of rated motor current, that estimate adds 700 A at the contribution point before intervening impedance is applied. Identify which motors are operating in each modeled condition. A one-line that shows only the utility transformer misses this source of current.
Transfer and tie positions matter for the same reason. A normally open tie, a closed tie and an emergency-source configuration form different networks. Carry each applicable arrangement into the short-circuit study rather than attaching one service value to every downstream bus.
Retain the boundaries of a transformer-only result
Schneider Electric's terminal-fault method gives 13.7 kA for its 400 kVA, 420 V no-load secondary, 4 percent impedance example while neglecting upstream MV impedance. The stated voltage is the no-load secondary voltage used in that method. A finite utility source, secondary feeder and additional parallel sources change the system result.
Use the highest applicable result for the equipment-duty comparison, and retain the lower-current cases for protection analysis. A lower fault current can operate a protective device more slowly; the largest current number alone does not establish the longest clearing time. Keep the calculation date, topology and impedance inputs with the result so later conductor or source changes are traceable.
Distinctions
- Interrupting rating
- For a breaker selection, the study supplies the prospective fault duty and the breaker data supply the tested interrupting capability at the stated voltage. Preserve both values rather than labeling either one simply fault amps.
- Arcing current
- An arc introduces impedance and produces a current different from a bolted short. Available bolted fault current is an input to an arc-flash analysis, not an incident-energy result.
Frequently asked questions
Does a clamp reading establish fault duty?
A normal clamp reading captures current already flowing. A fault study models the low-impedance connection that does not exist during that reading, including transformer impedance and brief motor contributions. Deliberately creating a short is not a measurement method.
Sources checked
Also defined as
- The maximum current the supply can deliver into a bolted short at the panel location, a property of the install
- The maximum short-circuit current at a point in the system, the level selectivity must hold to