GEC

GEC means grounding electrode conductor on an electrical drawing. For an AC system, the sizing worksheet needs the largest ungrounded supply conductor, parallel sets per phase, and the electrodes served by each segment. A breaker ampere rating alone leaves those inputs unresolved. Keep the conductor schedule with a route sketch: a common section serving several electrode types can need a larger wire than the final connection to a rod.

Grounding electrode conductor, connecting the grounding electrode system to the applicable system or equipment grounding point

Used across 6 Anvilfield field guides, most in Electrical.
Updated

Add parallel conductor area within one phase

The AC sizing examples here use NEC 2023 Table 250.66; NFPA's current published NEC edition is 2026. For two 500 kcmil copper conductors on each phase, enter 1,000 kcmil in the table lookup. Adding all three phases would incorrectly turn that input into 3,000 kcmil. NFPA's public development record preserves the 2023 table used for these comparisons.

The copper examples below follow Table 250.66 before electrode-specific allowances. Increasing a breaker setting without changing the supply conductors does not produce the same table change as adding another parallel conductor per phase.

Copper conductors per phaseEquivalent phase area2023 NEC table copper GEC
Two 500 kcmil1,000 kcmil2/0 AWG
Three 500 kcmil1,500 kcmil3/0 AWG

A smaller electrode connection does not shrink the trunk

NEC 2023 250.66(A) permits the sole connection to rod, pipe, or plate electrodes to stop at 6 AWG copper when it does not continue to another electrode requiring a larger conductor. NEC 2023 250.66(B) gives the corresponding 4 AWG copper allowance for a concrete-encased-electrode-only connection. The route and connected electrodes determine where either allowance applies.

A common conductor connecting building steel and then a rod cannot be sized as rod-only along its entire length. Separate the table-sized common portion from the electrode-only branch on the grounding electrode system drawing. That route detail explains why two GEC segments at the same service can legitimately have different sizes.

What belongs beside GEC on a conductor schedule?

A schedule entry such as 'GEC: 2/0 Cu, source ground bus to structural-steel electrode' identifies a different segment from '6 Cu, electrode bonding connection to rods only.' Pair those descriptions with the ground ring guide and the actual electrode plan. The endpoints explain which sizing provision was used.

The Oregon inspector reference lists NEC 250.66 for a GEC and 250.122 for an EGC. That distinction belongs on the schedule even when both conductors are copper. The 250.66 examples above apply to AC electrode conductors; DC grounding uses a separate code sizing basis.

Distinctions

EGC
An EGC is sized for the protected circuit and accompanies its conductors. The GEC calculation starts from a different supply-conductor and electrode basis.
MBJ / SBJ
Bonding-jumper sizing can continue upward proportionally on large systems after the GEC table reaches its highest copper size.
GEC in a soil report
FHWA uses GEC for Geotechnical Engineering Circular. A publication number in a soil report is unrelated to an electrical conductor size.

Frequently asked questions

Is every 200 A service GEC the same size?

No. Supply conductor material and size, permitted service-conductor sizing, and electrode configuration establish the result. Amperage alone omits those inputs.

Can a GEC be larger than the electrode allowance?

Yes. The allowance limits the required size for the specified connection; it does not prohibit a larger conductor with suitable terminations.

Sources checked

Also defined as

  • Grounding electrode conductor, the connection from the service or source to the grounding electrode system and the earth
  • Grounding electrode conductor, the connection to the earth electrodes, sized from 250.66 by the service conductors

Where this shows up