ANVILFIELD Try FieldOS

Field glossary · component

MBJ / SBJ

A building with a utility service and an isolating transformer can contain both an MBJ, the service's main bonding jumper, and an SBJ, the transformer's system bonding jumper. Label each bond by its source on the one-line. On a large parallel supply, bonding-jumper sizing can exceed electrode-conductor sizing, so copying a copper size from the GEC schedule can leave the source bond undersized.

Main bonding jumper at service equipment and system bonding jumper at the permitted point of a separately derived system

Used across 2 Anvilfield field guides, most in Electrical.
Updated

Identify the source before counting its bonds

OSHA 1910.304(g)(4) places the equipment-grounding connection to the grounded circuit conductor at the supply side of the service disconnect, or the corresponding disconnecting or overcurrent point of a separately derived system. That distinction separates the service bond from a derived-source bond.

A utility service and an isolating transformer secondary can each require their own source bonding connection in the same building. Trace each source on the grounding and bonding one-line. Counting neutral-to-ground connections throughout the building without identifying sources confuses legitimate source bonds with improper connections on feeder circuits.

Why the bonding jumper can exceed the GEC size

These calculations use the 2023 NEC; the current published edition is 2026. Table 250.102(C)(1) moves to a 12.5 percent area calculation above 1,100 kcmil copper or 1,750 kcmil aluminum. For a single copper MBJ or SBJ serving copper parallel conductors, total the area within one phase before applying that percentage.

Four 500 kcmil copper conductors per phase total 2,000 kcmil. The proportional minimum for a copper bonding jumper is 250 kcmil. Table 250.66 selects a 3/0 AWG copper GEC at that same supply-conductor basis before electrode-specific allowances. The two conductors do not become interchangeable simply because they meet at the grounded source point.

Mixed materials require another step. The 2023 table note bases a copper jumper on equivalent-ampacity copper supply conductors when the installed supply is aluminum. Applying 12.5 percent directly to aluminum circular mils and calling the result a copper requirement bypasses that conversion.

Identify the screw or the specified bonding assembly

NEC 2023 250.28(B) requires a screw-only main or system bonding jumper to have a green finish visible after installation. That identifies the bonding screw in the completed assembly. A provided strap or cable must instead be identified from the equipment's parts and assembly information; the screw-only identification rule does not describe every jumper shape.

The grounding versus bonding guide supplies the system context. The closeout drawing should name each jumper, its source, location, material, and whether it is the identified equipment part or a field-sized conductor.

Distinctions

Equipment bonding jumper
A jumper on the load side of protection is sized under its applicable equipment-bonding rules. It does not automatically use the source-side calculation.
Grounding electrode conductor
The GEC follows electrode-conductor sizing and connection allowances. Its required size can be smaller than the source bonding jumper.

Frequently asked questions

Does a transformer SBJ add an improper second building bond?

It establishes the bond for that separately derived source. The improper connection is a further neutral-to-equipment bond on the load side of that source's permitted bonding arrangement.

Can I size both jumpers from the breaker amperage?

The main and system bonding jumper calculation follows the associated ungrounded supply conductors. The circuit EGC table uses a different protection-based sizing approach.

Sources checked

Where this shows up

Next step: Find power installation owners

Back to the full field glossary