Electrical
Ufer ground (concrete-encased electrode) field guide for electricians
Use at least 20 ft of #4 (1/2 in) or larger qualifying rebar, with at least 2 in of concrete encasement in an earth-contact footing. What qualifies as a concrete-encased electrode, when the NEC forces you to use it, the listed connection, and why it all has to be done before the concrete is placed.
Direct answer
A Ufer ground is a concrete-encased electrode: at least 20 ft of qualifying 1/2 in (#4) or larger rebar, or 20 ft of 4 AWG or larger bare copper, encased in at least 2 in of concrete in an earth-contact footing or foundation. A ground rod contacts soil directly. Under NEC 250.50, use a qualifying CEE present in new work and bond the other required electrodes into the same system. The electrode does not replace the equipment grounding conductor or the metallic fault-return path.
On this page
Which NEC edition applies to this footing?Ufer ground vs ground rod: which should you use?Does a Ufer ground need rods or a 25-ohm test?What conductor size changes when you switch electrodes?What should the comparison and inspection record include?What a concrete-encased electrode isHow does a concrete-encased electrode contact the earth?Where the name comes fromWhat does the NEC require for a concrete-encased electrode?How do you count rebar length, laps, and concrete cover?Tied rebar counts as the electrodeIs a concrete-encased electrode required?Stub up the connection before the pourSelect a permitted connection to the rebarHow do you match the clamp to both the bar and the conductor?The grounding electrode conductor to the CEEWhat size GEC does a concrete-encased electrode need?The Ufer is one electrode in the systemDo I need a Ufer ground in an existing building?Spalling and corrosion concernsInspect the connection before the concrete is placedCoordinate with the GC and the concrete crewTesting a concrete-encased electrodeLarge foundations, data centers, and the signal referenceWhat to documentCommon mistakesField checklistHow should you scope public grounding work?MethodologyStandards and referencesUnits and termsOpen the related tool for the calculation, checklist, or packet.
FieldOS by AnvilfieldOffline-first FieldOS for job photos, proof packets, property memory, calculations, teams, billing, and owner-ready reports.Key takeaways
- NEC 250.52(A)(3) defines a concrete-encased electrode as 20 ft of #4 (1/2 in) rebar or 20 ft of 4 AWG bare copper in 2 in of concrete contacting earth.
- On new construction, NEC 250.50 makes the Ufer ground mandatory when qualifying footing rebar is present; you cannot skip it for a driven rod.
- The rebar-to-GEC joint must use a listed rebar clamp, listed direct-burial clamp, or exothermic weld (UL 467); hose clamps and unlisted parts fail inspection.
- The GEC to a concrete-encased electrode need not exceed 4 AWG copper per NEC 250.66(B), regardless of service size.
- Make and inspect the connection and stub up a tail before the pour; once poured the electrode is sealed and cannot be verified.
Which NEC edition applies to this footing?
Use the NEC edition and amendments adopted for the permit. The conductor tables in this guide use the 2023 NEC; apply the 2026 NEC where adopted and retain an earlier edition where the jurisdiction still requires it. Record the permit basis before ordering material.
Minnesota requires the 2026 NEC for permits filed on or after August 17, 2026. Earlier filings remain under 2023. Washington WAC 296-46B-010 sets its transition to the 2026 NEC for December 31, 2026, with permit and plan-review provisions controlling individual projects.
NFPA 70: 2026 NEC free access
Minnesota DLI: electrical code editionsUfer ground vs ground rod: which should you use?
Choose around the foundation and the qualifying electrodes present. A CEE must join the grounding electrode system under NEC 250.50; driving rods does not excuse missing the connection before a new footing pour. For an existing building, the exception covers reinforcing steel that cannot be accessed without disturbing concrete.
A concrete-encased electrode provides distributed contact through the footing. A rod provides direct contact along its driven length. The nVent ERICO grounding guide explains the effect of contact area and moisture; the installed resistance depends on soil and construction. Use project measurements when comparing performance.
| Field decision | Ufer / CEE | Ground rod |
|---|---|---|
| Build the electrode | 20 ft qualifying rebar or bare copper, with 2 in concrete encasement | At least 8 ft; verify material, diameter and listing |
| Plan the installation | Before the qualifying foundation is poured | Accessible soil during new work or a retrofit |
| Find the connection | Lost stub or undocumented buried connection | Buried clamp, utilities or rock blocking the drive |
| Check the reading | No national NEC 25-ohm CEE threshold | Single-rod exception uses 25 ohms or less |
| Confirm the scope | Does not prove a complete lightning protection design | Does not replace an equipment grounding conductor |
Does a Ufer ground need rods or a 25-ohm test?
The 2023 NEC does not require a rod solely to supplement a qualifying CEE, nor does its rod rule impose a 25-ohm pass limit on that CEE. Bond other required electrodes into the system. Where multiple CEEs are present, 250.52(A)(3) permits connecting only one. Utility requirements, local amendments and project specifications can require additional electrodes or testing.
For a single rod, pipe or plate electrode, 250.53(A)(2) requires a supplemental electrode unless resistance to earth is 25 ohms or less. A qualifying CEE can provide that supplement. If rods alone form the electrode system, installing a second rod is the usual alternative to demonstrating the single-rod exception. Space rods at least 6 ft apart under 250.53(A)(3); additional spacing can improve performance.
In Anvilfield's rod-selection case, a compliant 8 ft rod at an existing building measures 32 ohms and there is no other qualifying electrode. The rod needs a supplement because the reading exceeds 25 ohms. Placing the second rod 8 ft away exceeds the 6 ft minimum. Determine the combined resistance by measurement; it does not follow by halving the first reading.
Fluke explains that stakeless testing needs parallel earth paths. A clamp reading through a bonded system does not automatically establish an isolated electrode value. Record the method and circuit topology; arrange any required isolation under the approved electrical work procedure.
| Given | Result | Action |
|---|---|---|
| Single rod measures 32 ohms | 32 > 25 ohms | Supplement unless another qualifying electrode already serves |
| Two rods placed 8 ft apart | 8 ft > 6 ft minimum | Check project spacing and any separate resistance target |
| Anvilfield earth-return calculation | 4.8 A at 120 V through 25 ohms | Below the 20 A breaker rating; provide the required metallic fault-return path |
What conductor size changes when you switch electrodes?
Size the grounding electrode conductor from Table 250.66. Section 250.66(B) limits the required copper size to 4 AWG for a portion serving only CEEs; it does not establish a universal minimum. Bare copper used as the electrode itself has a separate 4 AWG minimum. Section 250.66(A) limits the required copper size to 6 AWG for rod, pipe or plate portions. A common conductor serving another electrode must meet that electrode's requirement.
Anvilfield's comparison applies those rules to separate copper electrode connections. A 2 AWG copper service conductor requires an 8 AWG copper GEC in these cases. A 3/0 AWG service requires 4 AWG to the CEE and 6 AWG to rods; a 250 kcmil service has a 2 AWG table size, reduced to 4 AWG for a CEE-only connection and 6 AWG for rods only.
| Largest copper service conductor | Table GEC | CEE only | Rods only |
|---|---|---|---|
| 2 AWG, single set | 8 AWG | 8 AWG | 8 AWG |
| 3/0 AWG, single set | 4 AWG | 4 AWG | 6 AWG |
| 250 kcmil, single set | 2 AWG | 4 AWG | 6 AWG |
What should the comparison and inspection record include?
Apply NEC 250.64 protection and routing requirements to the selected GEC. UL 467 covers grounding and bonding equipment; match the exact fitting to the conductor, electrode and exposure. BURNDY GAR6426 lists #5 to #6 rebar, so it is not the fitting for #4 rebar. Retain the manufacturer sheet with the inspection record.
- Record the adopted NEC edition, amendments, utility detail and drawing revision.
- Identify qualifying electrodes and document any existing-building accessibility exception.
- Photograph CEE length, cover, earth-contact concrete and the protected connection before concealment.
- Record rod length, location, spacing, connector model and required installation torque.
- Separate electrode material size from GEC size and conductor protection.
- Record test method, connected paths, instrument, conditions and the source of acceptance criteria.
What a concrete-encased electrode is
A concrete-encased electrode uses qualifying steel or bare copper within an earth-contact footing or foundation. The concrete provides the interface between the metal and surrounding soil. The trade name is Ufer ground; the NEC term is concrete-encased electrode, or CEE.
The footing detail determines whether the electrode qualifies. Check the electrode material, encased length, concrete cover and contact with earth. Structural reinforcing steel above an insulating layer is not automatically a qualifying electrode.
Coordinate the grounding connection before the concrete pour, then bond the CEE into the building grounding electrode system.
How does a concrete-encased electrode contact the earth?
The nVent ERICO grounding guide attributes CEE performance to the large concrete contact area and moisture retained within the concrete. Both the concrete and surrounding soil affect the resistance to remote earth.
Evaluate the actual foundation and soil instead of ranking electrode types by name. When the project sets a resistance target, the acceptance record needs the specified test method, connected paths and site conditions.
Where the name comes from
The trade name recognizes Herbert G. Ufer. The nVent ERICO guide describes his work with concrete-encased electrodes at an Arizona military installation during World War II.
Use concrete-encased electrode or CEE on drawings and submittals so the connection is tied to the NEC definition.
What does the NEC require for a concrete-encased electrode?
The code defines the concrete-encased electrode in NEC 250.52(A)(3), and the spec comes down to four things you have to hit. There must be at least 20 ft of electrode material. That material is either steel reinforcing bar 1/2 in (#4) or larger, bare or zinc-galvanized or other listed conductive coating, or at least 20 ft of bare copper conductor not smaller than 4 AWG. The electrode is encased in at least 2 in of concrete. And the concrete is in direct contact with the earth, located in a footing or foundation that touches the ground.
The cited dimensions are the 2023 NEC baseline. The adopted edition, local amendments and structural detail establish the project requirements.
Check the concrete-to-earth interface on the foundation detail. Concrete isolated from earth by a continuous insulating barrier does not supply the required contact. A perimeter footing that remains in direct earth contact must be evaluated separately from the slab above a vapor retarder.
Maintain at least 2 in of concrete around the qualifying electrode, together with any larger structural cover requirement.
| Requirement | Spec (verify adopted NEC) | Note |
|---|---|---|
| Minimum length | 20 ft of electrode material | One qualifying piece or interconnected reinforcing bars |
| Rebar option | 1/2 in (#4) or larger steel | Bare, galvanized, or listed conductive coating |
| Copper option | 4 AWG or larger bare copper | Run inside the footing concrete |
| Concrete cover | At least 2 in encasing the steel | Encasement around the qualifying metal; structural cover also applies |
| Earth contact | Concrete in direct contact with earth | Check the qualifying footing separately from the slab barrier |
How do you count rebar length, laps, and concrete cover?
Use #4 rebar, nominally 1/2 in diameter, or larger qualifying steel. Ordinary insulating epoxy coating does not meet the conductive-surface requirement. Do not scrape a structural bar to improvise an electrode; coordinate a separate approved electrode detail. Electrical continuity through tied bars does not establish the structural lap length.
Anvilfield analysis gives 22 ft of end-to-end encased length for the footing case below, leaving 2 ft beyond the electrode minimum. Keep the exposed connection tail outside the qualifying-length count.
The case uses the drawing's 3 in concrete cover, which exceeds the 2 in electrode minimum. Sacramento's detail separately specifies an 8 in exposed stub; that dimension applies to its local detail.
Larimer County: electrode material and earth contact
Sacramento: Ufer installation detail, revised January 2026| Check | Example or limit | Field decision |
|---|---|---|
| Bar diameter | #4 = 1/2 in minimum | Reject a smaller bar as the qualifying electrode |
| Connected length | 12 + 12 - 2 = 22 ft | Show both endpoints and the tied overlap |
| Cover | 3 in drawing; 2 in electrical minimum | Maintain the larger specified cover |
| Earth interface | Footing concrete contacts soil | Resolve continuous barriers before release |
Tied rebar counts as the electrode
NEC 250.52(A)(3) permits qualifying reinforcing bars to be connected by the usual steel tie wires or other effective means to create the electrode length. The structural lap and tie detail still comes from the engineer.
The connection from reinforcing steel to the GEC is a separate joint. Use a connection permitted by NEC 250.70 and identified for the conductor, bar and concrete exposure. Document that joint and the accessible tail before placement.
Is a concrete-encased electrode required?
Yes, on new construction, if it is present. NEC 250.50 requires that all grounding electrodes present at a building be bonded together into the grounding electrode system, and the concrete-encased electrode is on that list. The footing steel counts as present before the pour, because it is right there in the form. So if the footing has qualifying rebar, you are required to use it. You cannot skip it and drive a rod instead.
This changed deliberately. Older language said the concrete-encased electrode had to be used only if it was available, which crews read as optional. The code was tightened to make it mandatory when the electrode is present, and present means present before the concrete is placed. An inspector on a new building will expect the Ufer connection, and will ask where it is.
Read that as a planning requirement, because that is what it really is. The electrode being required does you no good if nobody made a connection to it before the footing was poured. The obligation to use it and the need to plan the connection ahead of the pour are the same fact seen from two sides. Treat the Ufer ground as a hold point, not an afterthought.
Stub up the connection before the pour
This is the part that determines whether the rest of it is even possible. You have to get a connection to the footing steel and bring a tail up out of where the concrete will be, before the concrete is placed. Miss that window and the electrode is buried, sealed, and unreachable without breaking the foundation.
Two common methods. Bond a length of bare copper, commonly 4 AWG or larger, to the rebar and run that conductor up out of the footing to where the service grounding will land. Or leave a section of the rebar itself bent up as a stub, tall enough to clear the pour, so you can clamp to it afterward. Either way the connection to the steel is made first, then the tail is brought up to daylight and protected so the pour does not bury the access point.
Plan where it lands. The stub should come up near the service location, inside the building footprint, somewhere it will not be cut off by a later trade or paved over. Mark it and protect it. A 4 AWG copper tail snapped off flush by a backfill crew is the same lost-access problem as no stub at all, just discovered later. The whole electrode rides on this one detail being handled before the truck shows up.
Select a permitted connection to the rebar
The joint between the grounding electrode conductor and the rebar, the one that lives in or comes out of the concrete, has to be made with a connection listed for the job. The usual choices are a listed rebar clamp, a listed grounding clamp suitable for the conductor and the bar, or an exothermic weld. Pipe-fit hose clamps, plumbing parts, and a couple of wraps of bare wire are not connections. An inspector will fail them, and the joint will corrode and loosen in the concrete besides.
When the connection is encased or buried, the listing matters even more, because you cannot get back to it. A listed direct-burial clamp is marked accordingly, often DB, and a rebar clamp is marked for the bar size it fits. Match the clamp to what you have. Exothermic welds make a permanent molecular bond and are a good pick where the joint will be encased, since there is nothing to back out over time.
The standard behind the listing for grounding and bonding connectors is UL 467. You do not have to memorize that to do the work, but you do have to use a fitting that carries the listing and is rated for concrete encasement or direct burial where that is where it ends up. The cheap unlisted clamp is the false economy that fails the inspection or the electrode.
How do you match the clamp to both the bar and the conductor?
Read both ranges on the same catalog line. ILSCO lists its GTGC family for grounding under UL 467 and for burial in earth and concrete, but the models fit different combinations. Its GTGC-6-1/0 accepts the example 4 AWG copper conductor while its rebar column lists only #3. GTGC-2-2/0 includes #4 rebar but its conductor range starts at 2 AWG. Neither is a match for a #4 bar with 4 AWG copper on that sheet.
That is a selection example, not a product recommendation. Obtain the current instructions for the exact approved fitting, including conductor construction, torque and burial suitability. A general UL mark or the word rebar does not settle those details.
| Submittal item | Evidence to retain |
|---|---|
| Bar and wire fit | Exact model with both size ranges marked |
| Concealed environment | Listing and instructions permit concrete encasement |
| Installation | Specified torque, tool setting and completed connection photo |
The grounding electrode conductor to the CEE
The grounding electrode conductor, the GEC, is the wire that ties the electrode to the grounded service equipment. From the concrete-encased electrode, the GEC runs from the listed connection on the rebar or the copper stub up to the service, where it lands on the grounding bus along with the connections from the other electrodes. The GEC is sized under NEC 250.66, and its connections follow the same rules as any electrode connection in 250.68 and 250.70.
For the 2023 NEC basis, keep the GEC continuous or use a permitted splice under 250.64(C), such as an irreversible compression connector listed for grounding and bonding or exothermic welding. The 2026 provision permits listed grounding and bonding equipment; check the adopted wording and fitting instructions. Protect the conductor where exposed to physical damage.
How the concrete-encased electrode sits alongside the other electrodes, and how the system gets bonded together, is covered in the grounding electrode system and bonding guide. The point for the CEE specifically is that its GEC has a sizing rule of its own, which is the next section.
What size GEC does a concrete-encased electrode need?
A CEE-only copper GEC need not be larger than 4 AWG under NEC 250.66(B). Start with Table 250.66: where the table requires a smaller conductor, the CEE allowance does not increase it.
A shared run must satisfy every electrode it serves. For the 3/0 AWG copper service case in the comparison table, the common portion serving the CEE remains 4 AWG copper and a branch serving only rods uses 6 AWG. For the 2 AWG copper service case, the table requires 8 AWG before physical-protection requirements are applied.
Keep the electrode material rule separate: a bare-copper CEE itself must be at least 4 AWG, regardless of the table result for its connecting GEC.
Saint Paul: 2023 NEC service grounding checklistThe Ufer is one electrode in the system
NEC 250.50 requires the qualifying electrodes present to form one grounding electrode system. Bond the CEE to other required electrode types, including qualifying water pipe and any ground ring.
Section 250.52(A)(3) permits connecting only one qualifying CEE when several are present. That allowance does not excuse omitting other required electrode types. Bonding establishes electrical continuity; it does not prove zero potential difference throughout a building during a surge.
Do I need a Ufer ground in an existing building?
No. You are not required to break open existing concrete to get to the footing steel. The code carries an exception for existing buildings: where the reinforcing bars of a concrete-encased electrode are not accessible without disturbing the concrete, that electrode is not required to be part of the grounding electrode system. The mandatory use of the Ufer applies to new work, where the steel is reachable before the pour.
So on a service upgrade or a panel change in an older building with a poured foundation and no stub left for you, you do not jackhammer the slab hunting for rebar. You use the electrodes that are present and accessible, typically a driven rod or rods, the metal water pipe where it qualifies, or building steel, and you bond what you have into the system.
If there happens to be an accessible rebar stub, an exposed grounded structural member, or a previously installed connection point, you use it. The line is accessibility. The code does not ask you to damage a finished structure to add an electrode, and it does not ask you to chase one you cannot reach.
Spalling and corrosion concerns
The nVent ERICO guide describes concrete damage under high-current conditions and the need to coordinate concrete-encased electrodes with the grounding design. A lightning protection or substation application needs its specified current paths and connections.
Select connectors identified for the metals and concrete exposure, protect exposed tails, and document continuity before concealment. Do not treat concrete encasement as proof against corrosion or physical damage.
Inspect the connection before the concrete is placed
Once the footing is poured, the electrode connection is gone from sight for good. That makes the inspection of the Ufer connection a before-the-pour event, not an after-the-fact one. The inspector who is going to sign off on the grounding electrode has to see the connection to the rebar, the listed clamp or the exothermic weld, and the stubbed-up tail, while it is still exposed.
Build that into the schedule the way you build in a footing or rebar inspection. The grounding connection lives in the same window as the structural footing inspection, and on many jobs they happen together because the same concrete is about to be placed. Call for it, get it looked at, and get the sign-off before you release the pour.
If the connection was concealed without inspection, obtain the AHJ's disposition. Seattle Tip 402 describes a local testing route for an uninspected Ufer; other jurisdictions require different evidence or exposure. Adding rods does not erase a new-work CEE requirement.
Coordinate with the GC and the concrete crew
The concrete-encased electrode is the one grounding job you cannot do alone on your own clock, because someone else controls when the concrete goes in. The connection has to be made and inspected in the gap between the rebar being set and the truck arriving, and that gap belongs to the general contractor and the concrete crew, not to you.
Confirm the pour date with the concrete crew and arrange the electrode connection and inspection before placement. Record responsibility for the exposed connection and its protection.
On a fast job the footing can be tied and poured in a single day. If you are waiting for a formal notice that never comes, you lose the electrode. Treat the pour date as your deadline, walk the footing yourself when the steel is set, and make the connection rather than waiting to be summoned.
Testing a concrete-encased electrode
A fall-of-potential test needs a suitable probe layout and a clear definition of the electrode system being measured. Record any parallel paths through the building system. A stakeless clamp test requires parallel earth paths and does not independently establish an isolated electrode value.
The NEC rod supplementation threshold is not a universal resistance target for a CEE. Where the project requires a resistance result, use the specified method and acceptance criteria.
Visual inspection before placement establishes material, length, cover, earth contact and connection suitability. A continuity reading alone cannot establish those concealed construction details.
Seattle: Tip 402, revised February 2025
Minnesota DLI: 2026 NEC inspection checklistLarge foundations, data centers, and the signal reference
Large foundations provide more reinforcing steel and potential connection locations, but their resistance still depends on soil, concrete and construction. Follow the designed bonding connections to structural steel and any signal reference network.
Mark connection locations by pour and grid line. Confirm responsibility for each tail, photograph each concealed joint, and retain the inspection release before the concrete placement.
What to document
Because the electrode disappears into the concrete, the record is the only thing that proves what got built. The connection that is now sealed in a footing can only be defended by the documentation made before it was poured and the inspection that cleared it. A photo of the connection before the pour is worth more than any note.
Capture the electrode material and length, the connection method and that it was listed, where the stub lands, the GEC size, the date and result of the before-pour inspection, and who made and who checked the connection. If the building is existing and the Ufer was not used, record why, that the rebar was not accessible without disturbing the concrete, and what electrodes were used instead.
| Field to record | Why it matters |
|---|---|
| Electrode material and length | Proves it meets the 250.52(A)(3) spec |
| Connection method, listed | The buried joint cannot be re-inspected later |
| Photo before the pour | The only visual proof once concrete is placed |
| Stub-up location | So the access point can be found at service time |
| GEC size to the CEE | Shows the 250.66(B) sizing was met |
| Before-pour inspection date and sign-off | Ties the electrode to an approval |
| If not used, the reason | Documents the existing-building exception |
Common mistakes
- Not using the concrete-encased electrode when the footing has qualifying rebar, which the NEC requires on new construction.
- Planning no stub-up or connection before the pour, so the electrode is sealed in concrete and access is lost.
- Using a non-listed clamp or a hose clamp on the rebar instead of a listed connection or an exothermic weld.
- Confusing the 4 AWG minimum for a bare-copper electrode with GEC sizing under Table 250.66 and the conditional 250.66(B) cap.
- Letting the concrete crew pour before the connection is made and inspected, because nobody got on the pour schedule.
- Treating concrete over a continuous vapor barrier as a qualifying electrode when it is not in direct contact with earth.
Field checklist
Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.
How should you scope public grounding work?
Price footing coordination and retrofit rod work as different scopes. Carry inspection attendance, utility locating, difficult driving, conductor protection, testing and restoration where required. Existing-building bids need an allowance or clarification for undocumented electrode connections; an aerial view cannot establish buried grounding condition.
Carry the connection, conductor route, protection, inspection visit and return visit if the pour moves. Assign responsibility for the stub before the concrete subcontract closes its scope. A missing connection is a coordination problem that a material allowance alone will not cover. For public foundation packages, PorchRocket's Bid Control gathers Texas city, county and school electrical bids so the estimator can budget coordination with the concrete crew.
Read the grounding drawings and bid addenda before carrying rods, testing or concrete repairs in the estimate.
Methodology
Anvilfield research uses the 2023 NEC electrode and conductor provisions as the comparison basis, cross-checked with the linked agency inspection guidance. State adoption pages establish the permit edition; manufacturer sheets establish connector ranges. These rule values remain attributed to their issuing sources.
The rod case inputs are a 32-ohm measured value, an 8 ft rod and 8 ft spacing. The earth-return calculation uses 120 V and 25 ohms in a resistive circuit: 120 / 25 = 4.8 A. The footing case uses two 12 ft bars with a 2 ft overlap: 12 + 12 - 2 = 22 ft, with 3 in cover from the case drawing. The lap detail is a case input, not an electrical-code lap requirement.
The conductor table uses one copper service conductor per phase and separate electrode-only portions, with no larger contract requirement. Construction quantities describe these defined cases.
Standards and references
The concrete-encased electrode lives in NEC Article 250. The electrode itself is defined in 250.52(A)(3), which sets the 20 ft length, the 1/2 in (#4) rebar or 4 AWG bare copper material, the 2 in of concrete cover, and the direct contact with earth. The requirement to use it when it is present at a new building, bonded with the other electrodes into one system, is in 250.50. The grounding electrode conductor to the CEE is sized under 250.66, with the 4 AWG copper cap for the CEE in 250.66(B). Electrode connections follow 250.68 and 250.70.
Article and subsection numbers move between code cycles, and the 20 ft, #4, and 2 in figures are the ones to confirm against the edition the jurisdiction has actually adopted along with any local amendments. The numbers above have held across recent editions, but verify before you put them on a submittal or argue them with an inspector.
The connection to the rebar has to be listed, and the listing standard for grounding and bonding connectors is UL 467, with clamps marked for direct burial and rebar size where they apply. Beyond the code and the listing, the inspector and the AHJ have the final say on what they will accept and when they need to see it. Stress the three things that decide whether this electrode succeeds: it must be used if it is present, the connection has to be stubbed up and made before the pour, and it has to be a listed connection that gets inspected while it is still exposed.
The linked code, agency and manufacturer documents were checked for this extension. Local inspection examples remain local; product-family literature requires confirmation against the exact fitting instructions.
Read the primary documentRead the primary documentRead the primary documentRead the primary documentRead the primary documentRead the primary documentRead the primary documentUnits and terms
The same electrode goes by several names across a drawing set, a spec, and the field, so it helps to know the synonyms before they confuse a submittal.
Concrete-encased electrode (CEE) is the formal NEC term, Ufer ground is the shop name, and both mean the rebar or copper in the footing. Rebar size is given by number, where #4 is 1/2 in diameter, and copper by AWG, where 4 AWG is the minimum bare copper. Resistance to earth is in ohms. GEC is the grounding electrode conductor, the wire from the electrode to the service. EGC is the equipment grounding conductor, a separate thing for fault current that is easy to confuse with the GEC by name alone.
- CEE / Ufer ground
- Concrete-encased electrode: rebar or copper cast in an earth-contact footing, used as a grounding electrode
- Rebar #4
- Reinforcing bar 1/2 in across, the minimum rebar size for a concrete-encased electrode
- GEC
- Grounding electrode conductor, connecting the grounding electrode system to the applicable system or equipment grounding point
- Stub-up
- The rebar tail or bonded conductor brought up out of the footing before the pour to keep the connection accessible
- Exothermic weld
- A metal connection formed by an exothermic process using the specified materials and connection kit
- Fall-of-potential
- A ground-resistance test using separate current and potential probes at selected distances from the electrode
FAQ
What is a Ufer ground?
A Ufer ground is a concrete-encased electrode: qualifying rebar or bare copper within earth-contact foundation concrete. The trade name refers to Herbert Ufer; the NEC term is concrete-encased electrode.
Is a concrete-encased electrode required?
On new construction, yes, if it is present. NEC 250.50 requires bonding every electrode present at a building into the grounding electrode system, and the footing rebar counts as present before the pour. If the footing has qualifying steel, you must use it. You cannot skip it for a driven rod.
Why is a concrete-encased electrode better than a ground rod?
Performance depends on the soil and installation. A CEE provides contact through earth-bearing concrete and retained moisture; compare electrodes using the project test method rather than a promised resistance ranking.
What size rebar is needed for a Ufer ground?
The reinforcing bar must be at least 1/2 in across, which is #4 rebar, and you need at least 20 ft of it, per NEC 250.52(A)(3). The bar can be bare or galvanized, and the 20 ft can be one piece or several bars bonded together with the usual tie wire. Confirm against the adopted code.
What size GEC does a concrete-encased electrode need?
Start with Table 250.66. NEC 250.66(B) limits the required copper size to 4 AWG for a CEE-only portion, but does not establish a universal minimum. A common portion serving other electrodes must satisfy their requirements. Bare copper used as the CEE itself has a separate 4 AWG minimum.
Do I need a Ufer ground in an existing building?
Use an accessible qualifying CEE in an existing building. The NEC exception applies where accessing its reinforcing steel would disturb concrete; it does not exempt a usable existing connection.
Can I connect to the rebar with any clamp?
No. Use an electrode connection permitted by NEC 250.70 and identified for the bar, conductor and exposure. A general direct-burial mark does not establish the correct rebar range or concrete-encasement use.
Does a vapor barrier under the slab disqualify a concrete-encased electrode?
A barrier disqualifies concrete that it isolates from the earth. Evaluate an earth-contact perimeter footing separately from the slab above a vapor retarder, and retain the approved foundation detail.
When does the Ufer connection need to be inspected?
Arrange the required inspection before concrete placement. Keep the electrode, connection and outgoing conductor available for review, and retain the approved detail, photographs and inspection record before releasing the pour.
Can a Ufer ground replace two ground rods?
A qualifying CEE can serve without supplemental rods under the 2023 NEC national rules. Other required electrodes still join the system. Check the locally adopted edition, amendments, utility rules and project specification before omitting rods.
People also ask
Codes cited in this guide
This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.
Sources checked
- NFPA 70: National Electrical Code, current edition and code access Current edition: 2026. Examples use 2023 Article 250; use 2026 wherever adopted. Curl checked November 5, 2026.
- NFPA: Code-Making Panel 5 public-input responses Cross-check of baseline 2023 sizing and electrode text. Proposed changes are not adopted requirements. Curl checked November 5, 2026.
- Washington WAC 296-46B-010: adopted standards 2023 NEC and the December 31, 2026 transition, with permit provisions.
- South Dakota Electrical Commission: grounding electrode systems Foundation coordination and rebar dimensions; state details are not national requirements. Curl checked November 5, 2026.
- nVent ERICO: Practical Guide to Electrical Grounding Pages 3, 15 and 17-18: earth resistance, rods and CEE behavior. Historical guide, not current adoption authority. Curl checked November 5, 2026.
- UL Solutions: grounding and lightning protection component certification UL 467 scope for grounding and bonding components. Curl checked November 5, 2026.
- BURNDY GAR6426: conductor, rod and rebar compatibility UL 467 listing, concrete burial suitability and #5 to #6 rebar range. Curl checked November 5, 2026. Manufacturer sheet mirrored by Graybar.
- Fluke: stakeless earth-ground measurement Parallel earth paths and limits of clamp-based measurements. Curl checked November 5, 2026.
- NFPA 70: 2026 NEC free access Published code access; select the permit edition. NFPA registration may be required.
- Minnesota DLI: electrical code editions 2026 adoption effective August 17, 2026, with the permit filing date determining the edition.
- Minnesota DLI: 2023 NEC inspection checklist Electrode dimensions, conductor protection and rod supplementation.
- Sacramento: Ufer installation detail, revised January 2026 20 ft encased length and 2 in encasement; the 8 in exposed stub is a local detail.
- Saint Paul: 2023 NEC service grounding checklist Table 250.66 sizing and the 4 AWG copper limit on the required CEE conductor size.
- ILSCO: GTGC grounding clamp data Separate conductor and rebar ranges; UL 467 listing and suitability for earth and concrete.
- Seattle: Tip 402, revised February 2025 Local permitting, inspection and testing provisions under the 2023 Seattle Electrical Code.
- Minnesota DLI: 2026 NEC inspection checklist Grounding electrode system, conductor protection and rod supplementation provisions.
- Minnesota DLI: 2026 adoption review Change to GEC splice provisions; use the adopted code and listed fitting instructions.