Field glossary · measurement
Freeboard
A pond freeboard check subtracts the specified design water elevation from the lowest controlling crest elevation, using the same survey datum. A settled crest at 104.20 feet above that datum and design water at 103.00 feet leave 1.20 feet of freeboard. Report the design storm and outlet condition with the result. Comparing the crest with today's normal pool instead answers a different question about present clearance.
The vertical distance between the design high-water level and the top of the embankment, a safety margin against overtopping
Which pond elevation controls the clearance?
Read the approved routing result alongside the grading plan. Identify the design peak water elevation, the settled embankment top and the auxiliary spillway crest as three separate elevations. Freeboard above flowing water and height above a dry spillway crest answer different questions. The pond management guide covers the operating structures; this elevation comparison establishes the clearance those structures must preserve.
Subtract the design water elevation from the lowest controlling embankment-top elevation. Survey the earth crest rather than the top of grass, mulch or deposited debris. A higher point elsewhere along the berm does not replace a low point that water can overtop. Record the control mark, datum, crest station and the routing document used for the subtraction.
One foot above water and two feet above a spillway
NRCS's North Dakota Pond standard, Code 378, July 2025, requires at least 1 foot between auxiliary-spillway design high water and the settled embankment top. Its scope includes qualifying low-hazard embankment ponds and excavated ponds; the freeboard provisions here concern embankments.
NRCS North Dakota's July 2025 Code 378 also requires at least 2 feet from auxiliary spillway crest to settled embankment top when drainage area exceeds 20 acres or effective dam height exceeds 20 feet. Test both clearances against the same embankment elevation. With an auxiliary crest at 100.00 feet and design high water at 101.40 feet, the two tests require a settled crest of at least 102.00 and 102.40 feet respectively; 102.40 feet controls. The 2-foot crest allowance is not added above the flowing water.
For ponds without an auxiliary spillway, NRCS North Dakota's July 2025 Code 378 requires at least 1 foot above the design hydrograph's peak water elevation. Record which spillway arrangement the approved design uses before choosing the comparison.
NRCS North Dakota's July 2025 Code 378 bases its minimum settlement allowance on 5 percent of total dam height at each cross section. A smaller allowance needs detailed laboratory soil testing and settlement analyses, or experience in the area demonstrating that it is adequate. Use total height for this allowance, rather than the effective height used in the spillway criterion. The extra construction height preserves the required settled crest.
A wheel rut changes the pond calculation
A design peak at elevation 103.00 feet and settled crest at 104.20 feet leave 1.20 feet of freeboard. A vehicle crossing that lowers one controlling crest section to 103.75 feet reduces the clearance to 0.75 foot. Against the 1-foot design criterion, the deficit is 0.25 foot even though the surrounding berm still stands at 104.20.
Keep the original crest profile with the new survey. The comparison distinguishes loss of embankment elevation from a higher predicted water surface caused by outlet or drainage changes. Restoring a rut and revising an outlet are different repair scopes, and the elevation record identifies which condition changed.
Why 110 percent does not settle tank freeboard
EPA's SPCC Guidance for Regional Inspectors, Chapter 4, explains that containment sized to 110 percent of the largest tank can still lack adequate precipitation capacity. The guidance discusses a 25-year, 24-hour storm as a design reference and explicitly distinguishes that reference from an enforceable SPCC freeboard standard.
The extra capacity depends on the containment footprint as well as tank volume. The same rainfall depth occupies more volume in a wider enclosure. For a fuel tank containment scope, retain the rainfall basis and displacement calculation instead of using a tank-capacity percentage as a vertical clearance.
Distinctions
- Detention storage
- Keep the freeboard interval out of the storage volume used to demonstrate a detention basin's design performance. A revised routing that raises the peak water elevation consumes clearance even when the embankment survey has not changed.
- Floating dock freeboard
- A dock inspection states the loading condition with the water-to-deck measurement. A pond inspection states the routing condition with the water-to-crest measurement. Keep those reference conditions attached to the number.
Frequently asked questions
Can I measure freeboard from the normal pond level?
That establishes present clearance. Design freeboard uses the water elevation assigned to the design event and outlet configuration. Attach that modeled elevation to the crest survey so the reported clearance has a reproducible basis.
Sources checked
Also defined as
- The height of a floating dock's deck above the water surface, set by the buoyancy and the load